Uskladiti materijal na obrascu M-29

Uzmite normirani utrošak za radove stvarno izvedene tijekom mjeseca, usporedite ga s onim što je skladište zaista izdalo, odvojite dopuštene gubitke od stvarnog prekoračenja, ishodite pisano obrazloženje za svako prekoračenje i zaključite mjesec kumulativnim iznosom.

7 koraka14 minGlavni izvođačSpecijalizirani podizvođač

Kako funkcionira, korak po korak

7 koraka kroz platformu - što radite u svakom i zašto je važno.

1

Take the norm consumption for the work you are reporting

Proizvodne norme

For each position in the report, take the material consumption the norm fixes per unit of measure, and note which material the norm actually names, because anything substituted on site has to be converted to the normed material before it can be compared at all.

Zašto: The first section of M-29 is the normative requirement, and it is derived rather than stated: the quantity of work multiplied by the norm per unit. Taking it from the norm instead of from last month's figure is the whole reason the comparison means anything.

UlazPositions in the reportNorm consumption per unitRezultatNormative requirementSubstituted materials converted
2

Separate the losses the norm allows from real overrun

Faktori otpada

Set the allowance for trimming, offcuts, breakage and transport loss for each material, so the difference between what was purchased and what was built into the work reads as a known figure rather than as an unexplained gap.

Zašto: Part of the difference between norm and actual is not overrun: it is loss the norm already contemplates or that the delivered form of the material imposes. Mixing the two makes every position look like a problem, and a report in which everything is a problem stops being read.

UlazMaterials in scopeDelivery and cutting formRezultatAllowed loss per materialPurchase quantity explained
3

Fix the volume of work the month actually completed

Napredak

Record the quantity of each type of work completed in the reporting month, measured in the same units and by the same rule the smeta uses, because this quantity is what the whole normative requirement is calculated from.

Zašto: M-29 compares consumption against the norm for the work done, not for the work planned. An overstated volume hides a material overrun completely, which is exactly why the same measurement has to feed both the KS-2 act and this report rather than being produced twice.

UlazMeasurement on siteUnits the smeta usesRezultatVolume completed this monthSame figure as the acceptance act
4

Record what was really issued and consumed

Zalihe na gradilištu

Book the deliveries in, the issues out against each work position and the returns, then close the month with a physical stock check, so consumption means what left the store for that work rather than what was bought during the month.

Zašto: Purchased is not consumed. Material standing on site at the end of the month belongs to the next report, and treating a delivery as consumption produces an alarming overrun in one month and an impossible saving in the following one, which is how the report loses its credibility.

UlazDeliveries booked inIssues to each positionRezultatActual consumptionClosing stock counted
5

Compare actual against norm position by position

Naknadna kalkulacija

Set the actual consumption against the normative requirement for each material and each position: the post-calculation reads the material money the estimate allowed against what the store issued for the quantity installed, line by line, and the stock ledger behind it gives the physical difference per material. Sort the result by money rather than by percentage.

Zašto: The second section of M-29 is exactly this comparison, and its value lies in being read by position. One concrete or reinforcement line can carry more overrun in roubles than every other position together, while a cheap material with a dramatic percentage swing costs almost nothing and pulls the whole discussion away from where the money went.

UlazNormative requirementActual consumptionRezultatVariance per positionVariance in money
6

Get every overrun explained and signed for

Rute odobravanja

Route each overrun above the agreed threshold to the person who has to explain it, with the reason written down, and on to the person who has to accept or refuse that explanation. Keep the refused ones visible rather than closing them.

Zašto: An overrun on M-29 is not written off by the site that caused it. The form is drawn up by the site manager, checked by the production and technical department and approved by the chief engineer, and that approval is what turns a number into either an accepted cost or a matter for recovery. Without a route, the explanation is a corridor conversation that nobody can produce six months later.

UlazOverruns above thresholdWritten reason from the siteRezultatAccepted explanationsRejected and referred on
7

Close the month with the cumulative position

Izvješća

Issue the report with both sections, the normative requirement and the comparison against actual, with the explanations attached, and show the position from the start of the job next to the position for the month.

Zašto: A single month is noise, the cumulative line is the finding. A position running three percent over every month for six months is invisible monthly and unmistakable cumulatively, and that cumulative figure is also what reconciles against the material cost the estimate budgeted in the first place.

UlazVariance with explanationsPosition from previous monthsRezultatSigned report for the monthCumulative position
Moduli

Moduli u ovom playbooku

7 / 190 modula platforme

The market this case is written for

Rusija

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Više u kategoriji Gradilište i teren

Gradilište i teren

Provedite dan na gradilištu

Pravilno zatvorite dan: zabilježite dnevnik, unesite sate rada i mehanizacije, učitajte foto…

4 koraka9 minOtvori
Gradilište i teren

Odgovorite na RFI

Pretvorite pitanje s gradilišta u praćeni zahtjev, proslijedite ga strani koja treba dati od…

3 koraka9 minOtvori