M-29 formuyla malzemeleri mutabakat edin

Ayın fiilen tamamlanan işi için norm tüketimini alın, bunu deponun gerçekte verdiğiyle karşılaştırın, izin verilen kayıpları gerçek aşımdan ayırın, her aşımı yazılı olarak açıklatın ve ayı kümülatif kalemle kapatın.

7 adım14 dkAna yükleniciUzman taşeron

Nasıl çalışır, adım adım

Platform genelinde 7 adım - her birinde ne yapacağınız ve neden önemli olduğu.

1

Take the norm consumption for the work you are reporting

Üretim Normları

For each position in the report, take the material consumption the norm fixes per unit of measure, and note which material the norm actually names, because anything substituted on site has to be converted to the normed material before it can be compared at all.

Neden: The first section of M-29 is the normative requirement, and it is derived rather than stated: the quantity of work multiplied by the norm per unit. Taking it from the norm instead of from last month's figure is the whole reason the comparison means anything.

GirdiPositions in the reportNorm consumption per unitÇıktıNormative requirementSubstituted materials converted
2

Separate the losses the norm allows from real overrun

Fire Katsayıları

Set the allowance for trimming, offcuts, breakage and transport loss for each material, so the difference between what was purchased and what was built into the work reads as a known figure rather than as an unexplained gap.

Ekran görüntüsü, adım 2: Separate the losses the norm allows from real overrun (Fire Katsayıları, M-29 formuyla malzemeleri mutabakat edin)
Fire Katsayıları: Separate the losses the norm allows from real overrun

Neden: Part of the difference between norm and actual is not overrun: it is loss the norm already contemplates or that the delivered form of the material imposes. Mixing the two makes every position look like a problem, and a report in which everything is a problem stops being read.

GirdiMaterials in scopeDelivery and cutting formÇıktıAllowed loss per materialPurchase quantity explained
3

Fix the volume of work the month actually completed

İlerleme

Record the quantity of each type of work completed in the reporting month, measured in the same units and by the same rule the smeta uses, because this quantity is what the whole normative requirement is calculated from.

Ekran görüntüsü, adım 3: Fix the volume of work the month actually completed (İlerleme, M-29 formuyla malzemeleri mutabakat edin)
İlerleme: Fix the volume of work the month actually completed

Neden: M-29 compares consumption against the norm for the work done, not for the work planned. An overstated volume hides a material overrun completely, which is exactly why the same measurement has to feed both the KS-2 act and this report rather than being produced twice.

GirdiMeasurement on siteUnits the smeta usesÇıktıVolume completed this monthSame figure as the acceptance act
4

Record what was really issued and consumed

Saha Envanteri

Book the deliveries in, the issues out against each work position and the returns, then close the month with a physical stock check, so consumption means what left the store for that work rather than what was bought during the month.

Ekran görüntüsü, adım 4: Record what was really issued and consumed (Saha Envanteri, M-29 formuyla malzemeleri mutabakat edin)
Saha Envanteri: Record what was really issued and consumed

Neden: Purchased is not consumed. Material standing on site at the end of the month belongs to the next report, and treating a delivery as consumption produces an alarming overrun in one month and an impossible saving in the following one, which is how the report loses its credibility.

GirdiDeliveries booked inIssues to each positionÇıktıActual consumptionClosing stock counted
5

Compare actual against norm position by position

İş sonrası maliyet analizi

Set the actual consumption against the normative requirement for each material and each position: the post-calculation reads the material money the estimate allowed against what the store issued for the quantity installed, line by line, and the stock ledger behind it gives the physical difference per material. Sort the result by money rather than by percentage.

Ekran görüntüsü, adım 5: Compare actual against norm position by position (İş sonrası maliyet analizi, M-29 formuyla malzemeleri mutabakat edin)
İş sonrası maliyet analizi: Compare actual against norm position by position

Neden: The second section of M-29 is exactly this comparison, and its value lies in being read by position. One concrete or reinforcement line can carry more overrun in roubles than every other position together, while a cheap material with a dramatic percentage swing costs almost nothing and pulls the whole discussion away from where the money went.

GirdiNormative requirementActual consumptionÇıktıVariance per positionVariance in money
6

Get every overrun explained and signed for

Onay rotaları

Route each overrun above the agreed threshold to the person who has to explain it, with the reason written down, and on to the person who has to accept or refuse that explanation. Keep the refused ones visible rather than closing them.

Ekran görüntüsü, adım 6: Get every overrun explained and signed for (Onay rotaları, M-29 formuyla malzemeleri mutabakat edin)
Onay rotaları: Get every overrun explained and signed for

Neden: An overrun on M-29 is not written off by the site that caused it. The form is drawn up by the site manager, checked by the production and technical department and approved by the chief engineer, and that approval is what turns a number into either an accepted cost or a matter for recovery. Without a route, the explanation is a corridor conversation that nobody can produce six months later.

GirdiOverruns above thresholdWritten reason from the siteÇıktıAccepted explanationsRejected and referred on
7

Close the month with the cumulative position

Raporlar

Issue the report with both sections, the normative requirement and the comparison against actual, with the explanations attached, and show the position from the start of the job next to the position for the month.

Ekran görüntüsü, adım 7: Close the month with the cumulative position (Raporlar, M-29 formuyla malzemeleri mutabakat edin)
Raporlar: Close the month with the cumulative position

Neden: A single month is noise, the cumulative line is the finding. A position running three percent over every month for six months is invisible monthly and unmistakable cumulatively, and that cumulative figure is also what reconciles against the material cost the estimate budgeted in the first place.

GirdiVariance with explanationsPosition from previous monthsÇıktıSigned report for the monthCumulative position
Modüller

Bu senaryodaki modüller

7 / 190 platform modülü

The market this case is written for

Rusya

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GESN/FER
  • KS-2 / KS-3

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Saha ve şantiye kategorisinde daha fazlası

Saha ve şantiye

Saha gününü yürütün

Günü doğru şekilde kapatın: günlüğü kaydedin, işçilik ve ekipman saatlerini işleyin, fotoğra…

4 adım9 dkAç
Saha ve şantiye

Bir RFI'yı yanıtlayın

Saha çalışmasından gelen bir soruyu izlenebilir bir talebe dönüştürün, cevabı vermekle sorum…

3 adım9 dkAç