Rapprocher les matériaux sur la fiche M-29

Prenez la consommation normée des travaux réellement achevés dans le mois, confrontez-la à ce que le magasin a réellement délivré, distinguez les pertes autorisées du dépassement réel, faites expliquer par écrit chaque dépassement et clôturez le mois avec la position cumulée.

7 étapes14 minEntreprise généraleSous-traitant spécialisé

Comment ça marche, étape par étape

7 étapes à travers la plateforme - ce que vous faites à chacune et pourquoi c’est important.

1

Take the norm consumption for the work you are reporting

Normes de production

For each position in the report, take the material consumption the norm fixes per unit of measure, and note which material the norm actually names, because anything substituted on site has to be converted to the normed material before it can be compared at all.

Pourquoi: The first section of M-29 is the normative requirement, and it is derived rather than stated: the quantity of work multiplied by the norm per unit. Taking it from the norm instead of from last month's figure is the whole reason the comparison means anything.

EntréePositions in the reportNorm consumption per unitRésultatNormative requirementSubstituted materials converted
2

Separate the losses the norm allows from real overrun

Coefficients de perte

Set the allowance for trimming, offcuts, breakage and transport loss for each material, so the difference between what was purchased and what was built into the work reads as a known figure rather than as an unexplained gap.

Pourquoi: Part of the difference between norm and actual is not overrun: it is loss the norm already contemplates or that the delivered form of the material imposes. Mixing the two makes every position look like a problem, and a report in which everything is a problem stops being read.

EntréeMaterials in scopeDelivery and cutting formRésultatAllowed loss per materialPurchase quantity explained
3

Fix the volume of work the month actually completed

Avancement

Record the quantity of each type of work completed in the reporting month, measured in the same units and by the same rule the smeta uses, because this quantity is what the whole normative requirement is calculated from.

Pourquoi: M-29 compares consumption against the norm for the work done, not for the work planned. An overstated volume hides a material overrun completely, which is exactly why the same measurement has to feed both the KS-2 act and this report rather than being produced twice.

EntréeMeasurement on siteUnits the smeta usesRésultatVolume completed this monthSame figure as the acceptance act
4

Record what was really issued and consumed

Inventaire de chantier

Book the deliveries in, the issues out against each work position and the returns, then close the month with a physical stock check, so consumption means what left the store for that work rather than what was bought during the month.

Pourquoi: Purchased is not consumed. Material standing on site at the end of the month belongs to the next report, and treating a delivery as consumption produces an alarming overrun in one month and an impossible saving in the following one, which is how the report loses its credibility.

EntréeDeliveries booked inIssues to each positionRésultatActual consumptionClosing stock counted
5

Compare actual against norm position by position

Post-calcul

Set the actual consumption against the normative requirement for each material and each position: the post-calculation reads the material money the estimate allowed against what the store issued for the quantity installed, line by line, and the stock ledger behind it gives the physical difference per material. Sort the result by money rather than by percentage.

Pourquoi: The second section of M-29 is exactly this comparison, and its value lies in being read by position. One concrete or reinforcement line can carry more overrun in roubles than every other position together, while a cheap material with a dramatic percentage swing costs almost nothing and pulls the whole discussion away from where the money went.

EntréeNormative requirementActual consumptionRésultatVariance per positionVariance in money
6

Get every overrun explained and signed for

Circuits d'approbation

Route each overrun above the agreed threshold to the person who has to explain it, with the reason written down, and on to the person who has to accept or refuse that explanation. Keep the refused ones visible rather than closing them.

Pourquoi: An overrun on M-29 is not written off by the site that caused it. The form is drawn up by the site manager, checked by the production and technical department and approved by the chief engineer, and that approval is what turns a number into either an accepted cost or a matter for recovery. Without a route, the explanation is a corridor conversation that nobody can produce six months later.

EntréeOverruns above thresholdWritten reason from the siteRésultatAccepted explanationsRejected and referred on
7

Close the month with the cumulative position

Rapports

Issue the report with both sections, the normative requirement and the comparison against actual, with the explanations attached, and show the position from the start of the job next to the position for the month.

Pourquoi: A single month is noise, the cumulative line is the finding. A position running three percent over every month for six months is invisible monthly and unmistakable cumulatively, and that cumulative figure is also what reconciles against the material cost the estimate budgeted in the first place.

EntréeVariance with explanationsPosition from previous monthsRésultatSigned report for the monthCumulative position
Modules

Modules de ce playbook

7 / 190 modules de la plateforme

Le marché pour lequel ce cas est écrit

Russie

Tout dans ce cas suit la façon dont les travaux sont métrés, chiffrés et payés sur ce marché. Les formulaires, la décomposition des coûts et les règles de paiement sont ceux qui y sont utilisés, pas une version générique.

Normes qu’il suit

  • GESN/FER
  • KS-2 / KS-3

Vous n’avez rien de tout cela à paramétrer à la main. Au premier démarrage, la plateforme demande sur quel marché vous travaillez. Choisissez celui-ci et elle règle la langue de l’interface, charge la base de coûts correspondante, enregistre la classification des coûts et ajoute un projet d’exemple que vous pouvez ouvrir tout de suite.

Les contrôles propres à ce marché sont eux aussi fournis avec la plateforme. Une fois activés, un devis auquel il manque quelque chose que le marché attend est signalé pendant que vous y travaillez, et non après l’envoi de l’offre.

Plus dans Chantier & terrain

Chantier & terrain

Gérer la journée de chantier

Clôturez correctement la journée : consignez le journal, saisissez les heures de main-d'œuvr…

4 étapes9 minOuvrir
Chantier & terrain

Répondre à une DDI

Transformez une question venant du terrain en demande suivie, faites-la parvenir au responsa…

3 étapes9 minOuvrir