Veďte smlouvu v datech Hijri i gregoriánského kalendáře

Nastavte pracovní týden od neděle do čtvrtka a pohyblivé svátky, zaznamenejte dobu plnění v kalendáři, ve kterém je smlouva psána, naplánujte zkrácené hodiny během ramadánu, zaevidujte každou platnost datovanou podle Hijri a vypořádejte prodlení proti datům, která si obě strany ověří.

7 kroků14 minGenerální dodavatelProjektová / stavební manažerská firmaDeveloper / klientSpecializovaný subdodavatel

Jak to funguje, krok za krokem

7 kroků napříč platformou - co na každém uděláte a proč na tom záleží.

1

Set the working week the site actually keeps

4D Harmonogram

Set the project calendar to the Saudi working week, Sunday through Thursday with Friday and Saturday as the weekend, and record the normal working day at the Labour Law maximum of eight hours, or forty eight hours in the week, whichever standard the contract of employment adopts.

Snímek obrazovky, krok 1: Set the working week the site actually keeps (4D Harmonogram, Veďte smlouvu v datech Hijri i gregoriánského kalendáře)
4D Harmonogram: Set the working week the site actually keeps

Proč: A programme built on a Monday to Friday default is wrong twice a week, every week, and the error compounds silently into every float calculation and every completion date the programme produces. It also puts planned work on Fridays, which is the day it will not happen, so the first progress report reads as a delay that never occurred.

VstupProject and its countryWorking hours agreedVýstupWork calendar setSunday to Thursday week
2

Put the holidays that move next to the ones that do not

Pokročilý harmonogram

Load the public holidays for the programme years ahead. Founding Day on 22 February and National Day on 23 September are fixed Gregorian dates. Eid al-Fitr and Eid al-Adha are Hijri and shift about eleven days earlier each Gregorian year, and the exact days off are confirmed close to the time, so plan the window and confirm the days rather than the other way round.

Snímek obrazovky, krok 2: Put the holidays that move next to the ones that do not (Pokročilý harmonogram, Veďte smlouvu v datech Hijri i gregoriánského kalendáře)
Pokročilý harmonogram: Put the holidays that move next to the ones that do not

Proč: A concrete pour or a shutdown planned into an Eid week is not a scheduling inconvenience, it is a crew that is not in the country. Because the Eids move, a programme copied from a job that ran two years earlier puts them in the wrong place, and the mistake is invisible until the week arrives.

VstupWork calendarProgramme yearVýstupFixed national daysMoving Eid periods
3

Record the period in the calendar the contract uses

Smlouvy

Read the contract for how the period of performance is expressed, in Hijri months, in Gregorian months or in days, note which it is on the contract record, and compute the completion date from the commencement date on that basis. Show the same date in the other calendar beside it, marked as the conversion rather than as the term.

Snímek obrazovky, krok 3: Record the period in the calendar the contract uses (Smlouvy, Veďte smlouvu v datech Hijri i gregoriánského kalendáře)
Smlouvy: Record the period in the calendar the contract uses

Proč: This is where the disputes come from. Eighteen Hijri months and eighteen Gregorian months are more than a fortnight apart, and on a contract with liquidated damages a fortnight is a number. Naming the calendar the contract chose, once, means the completion date is computed rather than negotiated, and the conversion stays visible as a convenience for the reader instead of quietly becoming the obligation.

VstupSigned contractCommencement dateVýstupContract calendar namedCompletion date in both
4

Plan Ramadan at the hours the law allows

Zdroje a personál

Set the crews to the Ramadan working day and replan the month's output on it. Article 98 of the Labour Law reduces actual working hours during Ramadan for Muslim workers to six a day, or thirty six a week, against the normal eight and forty eight, and most sites apply the reduced day to everyone rather than run two rotas.

Proč: A quarter of the working hours disappears for a month, and it is a statutory reduction rather than a productivity dip, so it belongs in the plan rather than in the excuses. A programme that carries eight hour days through Ramadan is not optimistic, it is arithmetically impossible, and the recovery plan written in the following month is paying for a decision made a year earlier.

VstupCrews and shiftsRamadan windowVýstupReduced hours appliedOutput replanned
5

Register every expiry with the calendar it is written in

Termíny

Put the guarantees, the insurances, the classification and commercial registration certificates, the municipal permits and the residence permits of the staff on one register, each with its expiry and a note saying whether that expiry was written in Hijri or in Gregorian, and set the reminder far enough ahead to renew rather than to react.

Proč: Almost every instrument on that list has teeth and none of them warn you. A residence permit that lapses stops a man working, a lapsed guarantee can cost the contract, and a bank guarantee written for twelve Hijri months expires eleven days before the anniversary somebody has in their diary. The register is not paperwork, it is the only place the two calendars are reconciled once instead of forty times.

VstupGuarantees, licences, permitsResidence and permit datesVýstupOne expiry registerCalendar noted on each
6

Measure a delay against the calendar that was agreed

Důkazy nároků

When an extension of time is claimed, count the delay in working days on the project calendar, with the weekends, the national days and the Eid closures the calendar already holds, and attach the diary entries and correspondence that show what happened on each of them.

Snímek obrazovky, krok 6: Measure a delay against the calendar that was agreed (Důkazy nároků, Veďte smlouvu v datech Hijri i gregoriánského kalendáře)
Důkazy nároků: Measure a delay against the calendar that was agreed

Proč: A claim counted in calendar days and answered in working days is two parties disagreeing about arithmetic while believing they disagree about the facts. Counting on the calendar both signed up to removes that argument entirely and leaves the real one, which is whether the event was the employer's risk.

VstupSite records and diariesAgreed work calendarVýstupDelay measured in working daysEvidence pack
7

Report dates the client reads the same way you do

Reporty

Publish the period report with the contract completion date, the forecast completion and the remaining float, each shown in the calendar the contract uses, and the conversion given alongside where the audience needs it.

Snímek obrazovky, krok 7: Report dates the client reads the same way you do (Reporty, Veďte smlouvu v datech Hijri i gregoriánského kalendáře)
Reporty: Report dates the client reads the same way you do

Proč: A monthly report is where a date error gets ratified. Print the completion date in one calendar for a year and both parties stop checking it, and the correction, when it comes, arrives with a claim attached. Showing the contract calendar first and the conversion second keeps the obligation and the convenience clearly apart.

VstupProgress this periodContract and programme datesVýstupReport both sides can readForecast completion
Moduly

Moduly v tomto playbooku

7 / 190 modulů platformy

The market this case is written for

Saúdská Arábie

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Saudi Building Code
  • Government Tenders and Procurement Law

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Více v kategorii Plánování a řízení

Plánování a řízení

Založení projektu a jeho předání

Provedete zakázku od úplně prvního založení až po předání. Založíte ji, oceníte práce, naplá…

5 kroků20 minOtevřít
Plánování a řízení

Dosažená hodnota a prognóza

Zjistěte, kde zakázka skutečně stojí vůči plánu a rozpočtu: aktualizujte harmonogram, přečtě…

3 kroků13 minOtevřít