केस / योजना और नियंत्रण
योजना और नियंत्रण

अनुबंध को Hijri और ग्रेगोरियन दोनों तारीख़ों पर चलाएं

रविवार से गुरुवार वाला सप्ताह और बदलती छुट्टियां तय करें, अनुबंध अवधि उसी कैलेंडर में दर्ज करें जिसमें अनुबंध लिखा है, रमज़ान के घटे हुए घंटों की योजना बनाएं, Hijri में तारीख़ वाली हर समाप्ति दर्ज करें, और देरी का निपटारा ऐसी तारीख़ों पर करें जिन्हें दोनों पक्ष जांच सकें।

7 चरण14 मिनटमुख्य ठेकेदारप्रोजेक्ट / निर्माण प्रबंधन फर्मडेवलपर / क्लाइंटविशेषज्ञ उपठेकेदार

यह कैसे काम करता है, चरण दर चरण

प्लेटफ़ॉर्म भर में 7 चरण - हर एक में आप क्या करते हैं और यह क्यों मायने रखता है।

1

Set the working week the site actually keeps

4D शेड्यूल

Set the project calendar to the Saudi working week, Sunday through Thursday with Friday and Saturday as the weekend, and record the normal working day at the Labour Law maximum of eight hours, or forty eight hours in the week, whichever standard the contract of employment adopts.

स्क्रीनशॉट, चरण 1: Set the working week the site actually keeps (4D शेड्यूल, अनुबंध को Hijri और ग्रेगोरियन दोनों तारीख़ों पर चलाएं)
4D शेड्यूल: Set the working week the site actually keeps

क्यों: A programme built on a Monday to Friday default is wrong twice a week, every week, and the error compounds silently into every float calculation and every completion date the programme produces. It also puts planned work on Fridays, which is the day it will not happen, so the first progress report reads as a delay that never occurred.

इनपुटProject and its countryWorking hours agreedपरिणामWork calendar setSunday to Thursday week
2

Put the holidays that move next to the ones that do not

उन्नत अनुसूची

Load the public holidays for the programme years ahead. Founding Day on 22 February and National Day on 23 September are fixed Gregorian dates. Eid al-Fitr and Eid al-Adha are Hijri and shift about eleven days earlier each Gregorian year, and the exact days off are confirmed close to the time, so plan the window and confirm the days rather than the other way round.

स्क्रीनशॉट, चरण 2: Put the holidays that move next to the ones that do not (उन्नत अनुसूची, अनुबंध को Hijri और ग्रेगोरियन दोनों तारीख़ों पर चलाएं)
उन्नत अनुसूची: Put the holidays that move next to the ones that do not

क्यों: A concrete pour or a shutdown planned into an Eid week is not a scheduling inconvenience, it is a crew that is not in the country. Because the Eids move, a programme copied from a job that ran two years earlier puts them in the wrong place, and the mistake is invisible until the week arrives.

इनपुटWork calendarProgramme yearपरिणामFixed national daysMoving Eid periods
3

Record the period in the calendar the contract uses

अनुबंध

Read the contract for how the period of performance is expressed, in Hijri months, in Gregorian months or in days, note which it is on the contract record, and compute the completion date from the commencement date on that basis. Show the same date in the other calendar beside it, marked as the conversion rather than as the term.

स्क्रीनशॉट, चरण 3: Record the period in the calendar the contract uses (अनुबंध, अनुबंध को Hijri और ग्रेगोरियन दोनों तारीख़ों पर चलाएं)
अनुबंध: Record the period in the calendar the contract uses

क्यों: This is where the disputes come from. Eighteen Hijri months and eighteen Gregorian months are more than a fortnight apart, and on a contract with liquidated damages a fortnight is a number. Naming the calendar the contract chose, once, means the completion date is computed rather than negotiated, and the conversion stays visible as a convenience for the reader instead of quietly becoming the obligation.

इनपुटSigned contractCommencement dateपरिणामContract calendar namedCompletion date in both
4

Plan Ramadan at the hours the law allows

संसाधन और दल

Set the crews to the Ramadan working day and replan the month's output on it. Article 98 of the Labour Law reduces actual working hours during Ramadan for Muslim workers to six a day, or thirty six a week, against the normal eight and forty eight, and most sites apply the reduced day to everyone rather than run two rotas.

क्यों: A quarter of the working hours disappears for a month, and it is a statutory reduction rather than a productivity dip, so it belongs in the plan rather than in the excuses. A programme that carries eight hour days through Ramadan is not optimistic, it is arithmetically impossible, and the recovery plan written in the following month is paying for a decision made a year earlier.

इनपुटCrews and shiftsRamadan windowपरिणामReduced hours appliedOutput replanned
5

Register every expiry with the calendar it is written in

समय-सीमाएँ

Put the guarantees, the insurances, the classification and commercial registration certificates, the municipal permits and the residence permits of the staff on one register, each with its expiry and a note saying whether that expiry was written in Hijri or in Gregorian, and set the reminder far enough ahead to renew rather than to react.

क्यों: Almost every instrument on that list has teeth and none of them warn you. A residence permit that lapses stops a man working, a lapsed guarantee can cost the contract, and a bank guarantee written for twelve Hijri months expires eleven days before the anniversary somebody has in their diary. The register is not paperwork, it is the only place the two calendars are reconciled once instead of forty times.

इनपुटGuarantees, licences, permitsResidence and permit datesपरिणामOne expiry registerCalendar noted on each
6

Measure a delay against the calendar that was agreed

दावा साक्ष्य

When an extension of time is claimed, count the delay in working days on the project calendar, with the weekends, the national days and the Eid closures the calendar already holds, and attach the diary entries and correspondence that show what happened on each of them.

स्क्रीनशॉट, चरण 6: Measure a delay against the calendar that was agreed (दावा साक्ष्य, अनुबंध को Hijri और ग्रेगोरियन दोनों तारीख़ों पर चलाएं)
दावा साक्ष्य: Measure a delay against the calendar that was agreed

क्यों: A claim counted in calendar days and answered in working days is two parties disagreeing about arithmetic while believing they disagree about the facts. Counting on the calendar both signed up to removes that argument entirely and leaves the real one, which is whether the event was the employer's risk.

इनपुटSite records and diariesAgreed work calendarपरिणामDelay measured in working daysEvidence pack
7

Report dates the client reads the same way you do

रिपोर्ट

Publish the period report with the contract completion date, the forecast completion and the remaining float, each shown in the calendar the contract uses, and the conversion given alongside where the audience needs it.

स्क्रीनशॉट, चरण 7: Report dates the client reads the same way you do (रिपोर्ट, अनुबंध को Hijri और ग्रेगोरियन दोनों तारीख़ों पर चलाएं)
रिपोर्ट: Report dates the client reads the same way you do

क्यों: A monthly report is where a date error gets ratified. Print the completion date in one calendar for a year and both parties stop checking it, and the correction, when it comes, arrives with a claim attached. Showing the contract calendar first and the conversion second keeps the obligation and the convenience clearly apart.

इनपुटProgress this periodContract and programme datesपरिणामReport both sides can readForecast completion
मॉड्यूल

इस प्लेबुक के मॉड्यूल

प्लेटफ़ॉर्म के 190 में से 7 मॉड्यूल

The market this case is written for

सऊदी अरब

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Saudi Building Code
  • Government Tenders and Procurement Law

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

योजना और नियंत्रण में और देखें

योजना और नियंत्रण

अर्जित मूल्य और पूर्वानुमान

देखें कि काम वाकई योजना और बजट के मुकाबले कहां खड़ा है: प्रोग्राम को अपडेट करें, CPI और SPI…

3 चरण13 मिनटखोलें