Fall / Planering och styrning
Planering och styrning

Driv ett kontrakt på Hijri-datum och gregorianska datum

Ställ in arbetsveckan söndag till torsdag och de helgdagar som flyttar sig, registrera kontraktstiden i den kalender kontraktet är skrivet i, planera de förkortade arbetstiderna under Ramadan, registrera varje utgång som är daterad i Hijri, och avgör en försening mot datum båda sidor kan kontrollera.

7 steg14 minGeneralentreprenörProjekt- / byggledningsföretagByggherre / beställareSpecialunderentreprenör

Så fungerar det, steg för steg

7 steg genom plattformen - vad du gör i varje och varför det spelar roll.

1

Set the working week the site actually keeps

4D-tidplan

Set the project calendar to the Saudi working week, Sunday through Thursday with Friday and Saturday as the weekend, and record the normal working day at the Labour Law maximum of eight hours, or forty eight hours in the week, whichever standard the contract of employment adopts.

Skärmbild, steg 1: Set the working week the site actually keeps (4D-tidplan, Driv ett kontrakt på Hijri-datum och gregorianska datum)
4D-tidplan: Set the working week the site actually keeps

Varför: A programme built on a Monday to Friday default is wrong twice a week, every week, and the error compounds silently into every float calculation and every completion date the programme produces. It also puts planned work on Fridays, which is the day it will not happen, so the first progress report reads as a delay that never occurred.

IndataProject and its countryWorking hours agreedResultatWork calendar setSunday to Thursday week
2

Put the holidays that move next to the ones that do not

Avancerat schema

Load the public holidays for the programme years ahead. Founding Day on 22 February and National Day on 23 September are fixed Gregorian dates. Eid al-Fitr and Eid al-Adha are Hijri and shift about eleven days earlier each Gregorian year, and the exact days off are confirmed close to the time, so plan the window and confirm the days rather than the other way round.

Skärmbild, steg 2: Put the holidays that move next to the ones that do not (Avancerat schema, Driv ett kontrakt på Hijri-datum och gregorianska datum)
Avancerat schema: Put the holidays that move next to the ones that do not

Varför: A concrete pour or a shutdown planned into an Eid week is not a scheduling inconvenience, it is a crew that is not in the country. Because the Eids move, a programme copied from a job that ran two years earlier puts them in the wrong place, and the mistake is invisible until the week arrives.

IndataWork calendarProgramme yearResultatFixed national daysMoving Eid periods
3

Record the period in the calendar the contract uses

Kontrakt

Read the contract for how the period of performance is expressed, in Hijri months, in Gregorian months or in days, note which it is on the contract record, and compute the completion date from the commencement date on that basis. Show the same date in the other calendar beside it, marked as the conversion rather than as the term.

Skärmbild, steg 3: Record the period in the calendar the contract uses (Kontrakt, Driv ett kontrakt på Hijri-datum och gregorianska datum)
Kontrakt: Record the period in the calendar the contract uses

Varför: This is where the disputes come from. Eighteen Hijri months and eighteen Gregorian months are more than a fortnight apart, and on a contract with liquidated damages a fortnight is a number. Naming the calendar the contract chose, once, means the completion date is computed rather than negotiated, and the conversion stays visible as a convenience for the reader instead of quietly becoming the obligation.

IndataSigned contractCommencement dateResultatContract calendar namedCompletion date in both
4

Plan Ramadan at the hours the law allows

Resurser & personal

Set the crews to the Ramadan working day and replan the month's output on it. Article 98 of the Labour Law reduces actual working hours during Ramadan for Muslim workers to six a day, or thirty six a week, against the normal eight and forty eight, and most sites apply the reduced day to everyone rather than run two rotas.

Varför: A quarter of the working hours disappears for a month, and it is a statutory reduction rather than a productivity dip, so it belongs in the plan rather than in the excuses. A programme that carries eight hour days through Ramadan is not optimistic, it is arithmetically impossible, and the recovery plan written in the following month is paying for a decision made a year earlier.

IndataCrews and shiftsRamadan windowResultatReduced hours appliedOutput replanned
5

Register every expiry with the calendar it is written in

Tidsfrister

Put the guarantees, the insurances, the classification and commercial registration certificates, the municipal permits and the residence permits of the staff on one register, each with its expiry and a note saying whether that expiry was written in Hijri or in Gregorian, and set the reminder far enough ahead to renew rather than to react.

Varför: Almost every instrument on that list has teeth and none of them warn you. A residence permit that lapses stops a man working, a lapsed guarantee can cost the contract, and a bank guarantee written for twelve Hijri months expires eleven days before the anniversary somebody has in their diary. The register is not paperwork, it is the only place the two calendars are reconciled once instead of forty times.

IndataGuarantees, licences, permitsResidence and permit datesResultatOne expiry registerCalendar noted on each
6

Measure a delay against the calendar that was agreed

Kravbevis

When an extension of time is claimed, count the delay in working days on the project calendar, with the weekends, the national days and the Eid closures the calendar already holds, and attach the diary entries and correspondence that show what happened on each of them.

Skärmbild, steg 6: Measure a delay against the calendar that was agreed (Kravbevis, Driv ett kontrakt på Hijri-datum och gregorianska datum)
Kravbevis: Measure a delay against the calendar that was agreed

Varför: A claim counted in calendar days and answered in working days is two parties disagreeing about arithmetic while believing they disagree about the facts. Counting on the calendar both signed up to removes that argument entirely and leaves the real one, which is whether the event was the employer's risk.

IndataSite records and diariesAgreed work calendarResultatDelay measured in working daysEvidence pack
7

Report dates the client reads the same way you do

Rapporter

Publish the period report with the contract completion date, the forecast completion and the remaining float, each shown in the calendar the contract uses, and the conversion given alongside where the audience needs it.

Skärmbild, steg 7: Report dates the client reads the same way you do (Rapporter, Driv ett kontrakt på Hijri-datum och gregorianska datum)
Rapporter: Report dates the client reads the same way you do

Varför: A monthly report is where a date error gets ratified. Print the completion date in one calendar for a year and both parties stop checking it, and the correction, when it comes, arrives with a claim attached. Showing the contract calendar first and the conversion second keeps the obligation and the convenience clearly apart.

IndataProgress this periodContract and programme datesResultatReport both sides can readForecast completion
Moduler

Moduler i denna playbook

7 / 190 plattformsmoduler

The market this case is written for

Saudiarabien

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Saudi Building Code
  • Government Tenders and Procurement Law

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.