Llevar un contrato con fechas Hijri y gregorianas

Fije la semana de domingo a jueves y los festivos que se mueven, registre el plazo del contrato en el calendario en que el contrato está escrito, planifique la jornada reducida de Ramadán, registre cada vencimiento fechado en Hijri, y resuelva un retraso con fechas que ambas partes puedan comprobar.

7 pasos14 minContratista generalGestora de proyectos / construcciónPromotor / clienteSubcontratista especialista

Cómo funciona, paso a paso

7 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.

1

Set the working week the site actually keeps

Cronograma 4D

Set the project calendar to the Saudi working week, Sunday through Thursday with Friday and Saturday as the weekend, and record the normal working day at the Labour Law maximum of eight hours, or forty eight hours in the week, whichever standard the contract of employment adopts.

Por que: A programme built on a Monday to Friday default is wrong twice a week, every week, and the error compounds silently into every float calculation and every completion date the programme produces. It also puts planned work on Fridays, which is the day it will not happen, so the first progress report reads as a delay that never occurred.

EntradaProject and its countryWorking hours agreedResultadoWork calendar setSunday to Thursday week
2

Put the holidays that move next to the ones that do not

Cronograma avanzado

Load the public holidays for the programme years ahead. Founding Day on 22 February and National Day on 23 September are fixed Gregorian dates. Eid al-Fitr and Eid al-Adha are Hijri and shift about eleven days earlier each Gregorian year, and the exact days off are confirmed close to the time, so plan the window and confirm the days rather than the other way round.

Por que: A concrete pour or a shutdown planned into an Eid week is not a scheduling inconvenience, it is a crew that is not in the country. Because the Eids move, a programme copied from a job that ran two years earlier puts them in the wrong place, and the mistake is invisible until the week arrives.

EntradaWork calendarProgramme yearResultadoFixed national daysMoving Eid periods
3

Record the period in the calendar the contract uses

Contratos

Read the contract for how the period of performance is expressed, in Hijri months, in Gregorian months or in days, note which it is on the contract record, and compute the completion date from the commencement date on that basis. Show the same date in the other calendar beside it, marked as the conversion rather than as the term.

Por que: This is where the disputes come from. Eighteen Hijri months and eighteen Gregorian months are more than a fortnight apart, and on a contract with liquidated damages a fortnight is a number. Naming the calendar the contract chose, once, means the completion date is computed rather than negotiated, and the conversion stays visible as a convenience for the reader instead of quietly becoming the obligation.

EntradaSigned contractCommencement dateResultadoContract calendar namedCompletion date in both
4

Plan Ramadan at the hours the law allows

Recursos y personal

Set the crews to the Ramadan working day and replan the month's output on it. Article 98 of the Labour Law reduces actual working hours during Ramadan for Muslim workers to six a day, or thirty six a week, against the normal eight and forty eight, and most sites apply the reduced day to everyone rather than run two rotas.

Por que: A quarter of the working hours disappears for a month, and it is a statutory reduction rather than a productivity dip, so it belongs in the plan rather than in the excuses. A programme that carries eight hour days through Ramadan is not optimistic, it is arithmetically impossible, and the recovery plan written in the following month is paying for a decision made a year earlier.

EntradaCrews and shiftsRamadan windowResultadoReduced hours appliedOutput replanned
5

Register every expiry with the calendar it is written in

Plazos

Put the guarantees, the insurances, the classification and commercial registration certificates, the municipal permits and the residence permits of the staff on one register, each with its expiry and a note saying whether that expiry was written in Hijri or in Gregorian, and set the reminder far enough ahead to renew rather than to react.

Por que: Almost every instrument on that list has teeth and none of them warn you. A residence permit that lapses stops a man working, a lapsed guarantee can cost the contract, and a bank guarantee written for twelve Hijri months expires eleven days before the anniversary somebody has in their diary. The register is not paperwork, it is the only place the two calendars are reconciled once instead of forty times.

EntradaGuarantees, licences, permitsResidence and permit datesResultadoOne expiry registerCalendar noted on each
6

Measure a delay against the calendar that was agreed

Evidencia de reclamaciones

When an extension of time is claimed, count the delay in working days on the project calendar, with the weekends, the national days and the Eid closures the calendar already holds, and attach the diary entries and correspondence that show what happened on each of them.

Por que: A claim counted in calendar days and answered in working days is two parties disagreeing about arithmetic while believing they disagree about the facts. Counting on the calendar both signed up to removes that argument entirely and leaves the real one, which is whether the event was the employer's risk.

EntradaSite records and diariesAgreed work calendarResultadoDelay measured in working daysEvidence pack
7

Report dates the client reads the same way you do

Informes

Publish the period report with the contract completion date, the forecast completion and the remaining float, each shown in the calendar the contract uses, and the conversion given alongside where the audience needs it.

Por que: A monthly report is where a date error gets ratified. Print the completion date in one calendar for a year and both parties stop checking it, and the correction, when it comes, arrives with a claim attached. Showing the contract calendar first and the conversion second keeps the obligation and the convenience clearly apart.

EntradaProgress this periodContract and programme datesResultadoReport both sides can readForecast completion
Módulos

Módulos de este playbook

7 / 190 módulos de la plataforma

El mercado para el que está escrito este caso

Arabia Saudí

Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.

Normas que sigue

  • Saudi Building Code
  • Government Tenders and Procurement Law

No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.

Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.