케이스 / 계획 및 관리
계획 및 관리

Hijri력과 그레고리력을 함께 써서 계약 운영하기

일요일부터 목요일까지의 근무주와 변동 공휴일을 설정하고, 계약이 작성된 달력 기준으로 계약기간을 기록하고, 라마단 단축근무를 계획하고, Hijri력으로 표기된 모든 만료일을 등록하고, 양측이 확인할 수 있는 날짜를 근거로 지연을 정산한다.

7단계14 분종합건설사PM/CM 업체시행사 / 발주처전문건설사

작동 방식, 단계별로

플랫폼 전반에 걸친 7단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Set the working week the site actually keeps

4D 일정

Set the project calendar to the Saudi working week, Sunday through Thursday with Friday and Saturday as the weekend, and record the normal working day at the Labour Law maximum of eight hours, or forty eight hours in the week, whichever standard the contract of employment adopts.

이유: A programme built on a Monday to Friday default is wrong twice a week, every week, and the error compounds silently into every float calculation and every completion date the programme produces. It also puts planned work on Fridays, which is the day it will not happen, so the first progress report reads as a delay that never occurred.

입력Project and its countryWorking hours agreed결과Work calendar setSunday to Thursday week
2

Put the holidays that move next to the ones that do not

고급 일정

Load the public holidays for the programme years ahead. Founding Day on 22 February and National Day on 23 September are fixed Gregorian dates. Eid al-Fitr and Eid al-Adha are Hijri and shift about eleven days earlier each Gregorian year, and the exact days off are confirmed close to the time, so plan the window and confirm the days rather than the other way round.

이유: A concrete pour or a shutdown planned into an Eid week is not a scheduling inconvenience, it is a crew that is not in the country. Because the Eids move, a programme copied from a job that ran two years earlier puts them in the wrong place, and the mistake is invisible until the week arrives.

입력Work calendarProgramme year결과Fixed national daysMoving Eid periods
3

Record the period in the calendar the contract uses

계약

Read the contract for how the period of performance is expressed, in Hijri months, in Gregorian months or in days, note which it is on the contract record, and compute the completion date from the commencement date on that basis. Show the same date in the other calendar beside it, marked as the conversion rather than as the term.

이유: This is where the disputes come from. Eighteen Hijri months and eighteen Gregorian months are more than a fortnight apart, and on a contract with liquidated damages a fortnight is a number. Naming the calendar the contract chose, once, means the completion date is computed rather than negotiated, and the conversion stays visible as a convenience for the reader instead of quietly becoming the obligation.

입력Signed contractCommencement date결과Contract calendar namedCompletion date in both
4

Plan Ramadan at the hours the law allows

리소스 및 인력

Set the crews to the Ramadan working day and replan the month's output on it. Article 98 of the Labour Law reduces actual working hours during Ramadan for Muslim workers to six a day, or thirty six a week, against the normal eight and forty eight, and most sites apply the reduced day to everyone rather than run two rotas.

이유: A quarter of the working hours disappears for a month, and it is a statutory reduction rather than a productivity dip, so it belongs in the plan rather than in the excuses. A programme that carries eight hour days through Ramadan is not optimistic, it is arithmetically impossible, and the recovery plan written in the following month is paying for a decision made a year earlier.

입력Crews and shiftsRamadan window결과Reduced hours appliedOutput replanned
5

Register every expiry with the calendar it is written in

마감일

Put the guarantees, the insurances, the classification and commercial registration certificates, the municipal permits and the residence permits of the staff on one register, each with its expiry and a note saying whether that expiry was written in Hijri or in Gregorian, and set the reminder far enough ahead to renew rather than to react.

이유: Almost every instrument on that list has teeth and none of them warn you. A residence permit that lapses stops a man working, a lapsed guarantee can cost the contract, and a bank guarantee written for twelve Hijri months expires eleven days before the anniversary somebody has in their diary. The register is not paperwork, it is the only place the two calendars are reconciled once instead of forty times.

입력Guarantees, licences, permitsResidence and permit dates결과One expiry registerCalendar noted on each
6

Measure a delay against the calendar that was agreed

클레임 증거

When an extension of time is claimed, count the delay in working days on the project calendar, with the weekends, the national days and the Eid closures the calendar already holds, and attach the diary entries and correspondence that show what happened on each of them.

이유: A claim counted in calendar days and answered in working days is two parties disagreeing about arithmetic while believing they disagree about the facts. Counting on the calendar both signed up to removes that argument entirely and leaves the real one, which is whether the event was the employer's risk.

입력Site records and diariesAgreed work calendar결과Delay measured in working daysEvidence pack
7

Report dates the client reads the same way you do

보고서

Publish the period report with the contract completion date, the forecast completion and the remaining float, each shown in the calendar the contract uses, and the conversion given alongside where the audience needs it.

이유: A monthly report is where a date error gets ratified. Print the completion date in one calendar for a year and both parties stop checking it, and the correction, when it comes, arrives with a claim attached. Showing the contract calendar first and the conversion second keeps the obligation and the convenience clearly apart.

입력Progress this periodContract and programme dates결과Report both sides can readForecast completion
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 7

The market this case is written for

사우디아라비아

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • Saudi Building Code
  • Government Tenders and Procurement Law

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

계획 및 관리 카테고리의 더 보기

계획 및 관리

프로젝트 설정 및 인도

프로젝트를 최초 설정부터 최종 인도까지 처리한다. 프로젝트를 생성하고, 공사비를 산정하며, 공정을 계획하고, 현장에서 진척을 관리한 후 깔끔하게 마무리한다. 전체 생…

5단계20 분열기
계획 및 관리

베이스라인 구축 및 진척 추적

공정표를 계획하고, 비교 기준이 될 베이스라인을 확정하고, 현장의 실제 진척을 반영한 뒤 편차를 확인하여 지연을 조기에 발견합니다.

4단계12 분열기
계획 및 관리

실적 가치 분석 및 예측

현장이 계획과 예산 대비 실제로 어디에 있는지 파악합니다. 공정표를 최신화하고, CPI와 SPI를 확인한 뒤, 준공 예상 비용과 예상 완료일에 신뢰할 수 있는 값을…

3단계13 분열기