Soll-Ist kontroll töötaval objektil

Loe Deckungsbeitrag'i, kuni objekt veel töötab: sea Soll kalkulatsioonist, broneeri edenemine ja tegelik kulu igal perioodil, sobita kulu väärtusega, ning lase teenitud väärtusel öelda, kuhu töö jõuab.

7 sammu14 minPeatöövõtjaErialaalltöövõtjaProjekti- / ehitusjuhtimisbüroo

Kuidas see töötab, samm-sammult

7 sammu läbi platvormi - mida teete igas ja miks see loeb.

1

Set the Soll from the calculation

5D kulumudel

Generate the cost budget from the priced bill, then work down the budget lines category by category so the Soll carries the money your calculation carried, split the way site will actually spend it.

Ekraanipilt, samm 1: Set the Soll from the calculation (5D kulumudel, Soll-Ist kontroll töötaval objektil)
5D kulumudel: Set the Soll from the calculation

Miks: A Soll is only worth comparing against when it comes from the calculation the job was priced on. A budget keyed in from memory turns every later variance into an argument about the budget instead of a decision about the work.

SisendPriced bill of quantitiesCost categoriesVäljundSoll budget linesBudget at completion
2

Freeze the baseline

Teenitud väärtus

Create the baseline from that budget with its budget at completion, run the check, and approve it. From here the Soll is fixed and dated, and every later measurement is read against it.

Miks: A budget nobody froze quietly swallows a Nachtrag, and the margin never moves - which is exactly how a job reads as healthy until the end. A dated, approved Soll makes added scope show up as a change you can see, price and defend.

SisendSoll budget linesBudget at completionVäljundApproved baselineDated Soll
3

Record what is built at the cut-off

Edenemine

On the cut-off date record the percent complete against the bill positions from the site measurement, then read the earned quantity and the quantity variance the entries produce.

Ekraanipilt, samm 3: Record what is built at the cut-off (Edenemine, Soll-Ist kontroll töötaval objektil)
Edenemine: Record what is built at the cut-off

Miks: Built work is the one figure nobody can invoice their way around. Recording it position by position, on a date everyone holds to, is what keeps the value side of the reconciliation from turning into a feeling.

SisendSite measurementBill positionsPeriod cut-offVäljundPercent complete per positionEarned quantityQuantity variance
4

Turn the progress into a Leistungsmeldung

Lepingud

Raise the progress claim for the period and populate it from the progress you just recorded, then walk it from submitted through approved to certified so the period ends with a value both sides stand behind.

Ekraanipilt, samm 4: Turn the progress into a Leistungsmeldung (Lepingud, Soll-Ist kontroll töötaval objektil)
Lepingud: Turn the progress into a Leistungsmeldung

Miks: The Leistungsmeldung is what turns built work into money you are allowed to count. Filling it from recorded progress rather than from a spreadsheet keeps the value in the reconciliation tied to something that was measured on site.

SisendRecorded progressContract and retention termsVäljundLeistungsmeldung for the periodCertified value to date
5

Book the Ist and the Obligo

Finants

Book the cost that landed in the same period - subcontractor and supplier invoices, labour, plant - and bring in the orders placed but not yet invoiced so the Obligo sits alongside the Ist.

Ekraanipilt, samm 5: Book the Ist and the Obligo (Finants, Soll-Ist kontroll töötaval objektil)
Finants: Book the Ist and the Obligo

Miks: Cost you have ordered but not yet been billed for is the part of the overrun that has already happened and cannot be seen yet. Leave it out and the margin looks fine for exactly as long as the post takes to arrive.

SisendSubcontractor and supplier invoicesLabour and plant recordsOrders placedVäljundIst cost to dateObligo
6

Read the Deckungsbeitrag

Kulu-väärtuse võrdlus

Open the month, set the value to date against the cost to date per cost head with the accruals in, and read the margin to date and the forecast margin. Finalise the month once the figures are agreed.

Ekraanipilt, samm 6: Read the Deckungsbeitrag (Kulu-väärtuse võrdlus, Soll-Ist kontroll töötaval objektil)
Kulu-väärtuse võrdlus: Read the Deckungsbeitrag

Miks: One margin figure tells you there is a problem; a margin per cost head tells you which trade caused it. Finalising the month puts an agreed number on the record, so next month's movement is a comparison rather than a fresh opinion.

SisendCertified value to dateIst cost and ObligoSoll budget linesVäljundDeckungsbeitrag to dateForecast marginFinalised month
7

Forecast where the job lands

Teenitud väärtus

Record the measurement for the cut-off - earned value, actual cost, planned value - and work out the forecast. Read the cost and schedule indices, the outturn against budget, and pick up any alert that has tripped its threshold.

Ekraanipilt, samm 7: Forecast where the job lands (Teenitud väärtus, Soll-Ist kontroll töötaval objektil)
Teenitud väärtus: Forecast where the job lands

Miks: An index under one is a forecast, not a report card: it says where the job ends up if nothing changes. Read in month three that is a plan to fix the trade that is losing. Read at the Schlussrechnung it is only the loss you already took.

SisendApproved baselineEarned value and actual costCut-off dateVäljundCost and schedule indicesOutturn against budgetThreshold alert
Moodulid

Selle tegevusjuhendi moodulid

6 / 190 platvormi moodulit

The market this case is written for

Saksamaa

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • DIN 276
  • GAEB XML
  • VOB/B

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Rohkem valdkonnas Äritegevus ja lepingud

Äritegevus ja lepingud

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 sammu11 minAva