Report a DIN 276 cost plan to the client

Build the cost plan on the DIN 276 cost groups, code every position to its Kostengruppe, read the variance group by group and issue it to the client in the structure their auditor expects.

7ステップ13 分コストコンサルティング会社 / 積算事務所総合建設会社デベロッパー / 発注者

仕組みをステップごとに

プラットフォーム全体で7ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

Set the early cost frame

概算見積

Open the conceptual estimate and put down the first cost frame: gross floor area, quality level and region give a cost per square metre, and the total comes back split across the elemental categories rather than as one number.

理由: The client approves a figure long before there is a bill to price. Holding that early frame in the project is what lets the later, finer plan be read against something instead of arriving as a fresh number nobody recognises.

入力Gross floor areaQuality level and region出力Early cost frameElemental split
2

Code every position to a Kostengruppe

内訳書

Work down the bill and give each position its DIN 276 code in the classification column: 300 for the Baukonstruktionen, 400 for the Technische Anlagen, 500 for the Aussenanlagen, down to the three-digit group where the work really sits.

理由: The cost group is what turns a flat list of positions into a plan that can be read by group. A position left uncoded is money that shows up under no heading at all when the client asks what a group contains.

入力Priced positionsDIN 276 cost groups出力Coded positionsCost group on every line
3

Build the plan by cost group

5Dコストモデル

Generate the cost spine from the bill. Each coded position lands on a control account for its cost group, so the plan appears as a tree of Kostengruppen with the totals rolled up from the positions underneath and every line still reachable.

理由: This is the elemental plan itself, and it is generated from the coded positions rather than typed next to them. That is what stops a group total and the detail behind it from drifting apart as the design moves on.

入力Coded billClassification standard出力Control account per groupRolled-up group totals
4

Check that nothing is unclassified

検証

Run validation across the bill and look for positions carrying no cost group at all and for codes that sit outside the group the work belongs to, then go back to the line and correct them.

理由: A single uncoded position makes a group total wrong while the grand total still adds up, so the error survives every check that looks only at the bottom line. Finding it now is cheaper than explaining it in a review.

入力Cost planClassification rules出力Validation reportUncoded lines flagged
5

Read the variance group by group

5Dコストモデル

Go through the spine one cost group at a time and read the estimate against the budget recorded for it, so you can name which Kostengruppe carries the movement and how much of it, before you open the drill-down on the group that moved most.

理由: The budget question is almost never about the total, it is about which group moved and why. Having the answer per group turns a defensive meeting into a short one.

入力Group totalsRecorded budget出力Variance per groupThe groups that moved
6

Write down what the plan assumes

見積根拠

Record the basis behind the numbers: which design state the plan was built on, what each cost group includes and excludes, and which figures are still an allowance rather than a priced quantity.

理由: A cost plan is only defensible with its assumptions attached. Written down while you build it, they answer a challenge months later; reconstructed after the challenge, the same sentences read as an excuse.

入力Cost planDesign state出力Basis of estimateInclusions and exclusions
7

Issue the plan to the client

レポート

Export the plan grouped by Kostengruppe, with the group totals, the variance against the budget and the basis alongside them, in the structure the client and their auditor already read.

理由: A client who receives the plan in the structure they work in every day can approve it. One who has to re-sort a flat total into cost groups first will send it back, and the next meeting is about the format instead of the money.

入力Validated cost planBasis of estimate出力Cost plan by groupClient-ready budget
モジュール

このプレイブックのモジュール

プラットフォーム 184 モジュール中 6

積算とコストの他のケース

積算とコスト

送付前に見積を確認する

積算済みの内訳書を検証ルールにかけ、すべての警告とエラーを解消し、そのまま顧客に渡せるきれいなレポートを出力する。

3ステップ8 分開く
積算とコスト

コストデータベースから見積を作成する

実在のコストデータベースから積算項目を取り出して内訳書を組み立て、繰り返し使う積み上げをアセンブリにまとめ、入札額を確定する前にチェックを実行します。

4ステップ12 分開く
積算とコスト

コストリスクから予備費を設定する

単一値の見積を幅のある値に変え、本当に不確実性のある項目についてモンテカルロシミュレーションを実行し、P50からP90の分布を読み取り、行ごとに根拠を示せる予備費を設定します。

3ステップ11 分開く