Build a Preisspiegel and award

Send one work package to several Nachunternehmer, level what comes back onto the same scope, read the Preisspiegel side by side, and award on the Wertung instead of on the smallest number.

7 خطوة13 دقيقةمقاول عاممكتب إدارة المشاريع / الإنشاءاستشارات التكاليف / قياس الكميات

كيف يعمل، خطوة بخطوة

7 خطوات عبر المنصة - ما تفعله في كل منها ولماذا يهم.

1

Cut the package out of the LV

المناقصات

Create the tender package straight from the LV: pick the positions that make up the one Gewerk you are buying, name the scope, and set the dates the work has to run to. The package starts as a draft you can still change.

لماذا: Every NU has to price the same positions with the same quantities. A package cut from the LV is what makes that true; three hand-made spreadsheet extracts are what makes a Preisspiegel impossible two weeks later.

المدخلاتPriced LVTrade to buyالمخرجاتDraft VergabepaketPositions to be priced
2

Pick the Nachunternehmer you will ask

المقاولون من الباطن

Work through the NU register and shortlist the firms for this Gewerk: the right trade, capacity free in your window, references you can actually call, and a valid Freistellungsbescheinigung on file.

لماذا: Asking everybody wastes their time and yours, and asking the wrong firm costs more than that. A missing Freistellungsbescheinigung becomes a Bauabzugsteuer deduction you have to handle, and MiLoG leaves you answerable for the wages your NU pays. That belongs in the shortlist, not in the week of the award.

المدخلاتNU registerTrade and regionPrequalification recordsالمخرجاتShortlist for the AnfrageChecked credentials
3

Send one Anfrage to all of them

المناقصات

Issue the package to the whole shortlist at once, with the same position list, the same dates and the same terms. Answer what comes back as an addendum that reaches every bidder, then let the package collect the Angebote as they arrive.

لماذا: The moment one NU prices a scope the others never saw, the comparison is dead and no amount of leveling brings it back. Issuing once and clarifying to everyone at once is what keeps all the columns answering the same question.

المدخلاتDraft VergabepaketNU shortlistالمخرجاتIssued AnfrageAddenda on recordReturned Angebote
4

Level the offers to one scope

المناقصات

Open the leveling matrix and work down it line by line: the positions an NU left unpriced, the ones excluded in the Anschreiben, the Bedarfspositionen each firm handled differently, and the arithmetic where unit price times quantity does not give the total they wrote. Put the Nachlass and the Skonto where they belong, and price the gaps in at your own rate.

لماذا: This is the work the spreadsheet never does. Until the missing positions are priced back in, the lowest column belongs to whoever read the LV least carefully, and you meet the difference again as a Nachtrag once the trade is on site.

المدخلاتReturned AngebotePackage positionsالمخرجاتLeveled offersGaps and exclusions flagged
5

Read the Preisspiegel side by side

المناقصات

Set the leveled offers out as a Preisspiegel, NU by column and position by row, then read down the rows rather than across the bottom line: where one firm sits far under everybody on a single position, where the spread is tight, where somebody stands alone at the top. Weigh the recommendation the package offers and the warning it raises when a low offer sits well below the median.

لماذا: A bottom line tells you what a firm will charge. The rows tell you whether they understood the job. A position priced at a third of everyone else is not a discount, it is a misreading that turns up later as a Nachtrag with your name on it.

المدخلاتLeveled offersBudget from the LVالمخرجاتPreisspiegelOutliers per position
6

Award on the Wertung and raise the order

المشتريات

Award on the whole Wertung and not on the smallest number: the leveled price, capacity for your dates, the references, the credentials you checked. The award writes the agreed rates back to the LV, gives you the award letter for the winner and the rejection notice for the rest, and drafts the order in Procurement. Open it there and check it carries the leveled scope rather than the raw Angebot.

لماذا: The award is a decision; the order is the commitment. If the order goes out on the original Angebot, every gap you just priced in comes straight back as a Nachtrag and you paid for the leveling work twice.

المدخلاتPreisspiegelWertung criteriaChecked credentialsالمخرجاتAwarded NUOrder on the leveled scopeAward and rejection letters
7

Put the reasoning on record

التقارير

File the Vergabevermerk: the Preisspiegel as it stood on the day, the adjustments you made and what each one was for, the criteria you weighed, and the reason the package went where it went.

لماذا: Six months on, nobody asks what you paid. They ask why the more expensive NU got the work. One short document written on the day answers a partner, an auditor or a losing bidder without anyone having to remember.

المدخلاتPreisspiegel at awardLeveling adjustmentsAward decisionالمخرجاتVergabevermerkAuditable award trail
الوحدات

وحدات هذا الدليل

4 / 184 من وحدات المنصة

المزيد في المناقصات والمشتريات

المناقصات والمشتريات

إجراء مناقصة من BOQ

اطرح جدول كميات مسعّراً في السوق: حزّمه، وادعُ مقاولي الباطن، وسوِّ عروضهم، وأرسِ على الفائز…

5 خطوة12 دقيقةفتح
المناقصات والمشتريات

توريد المواد من BOQ

اشترِ الكميات التي سعّرتها بالفعل: أنشئ طلب شراء من الجدول، وضع الأمر لدى مورّد، وسجّل استلا…

4 خطوة10 دقيقةفتح
المناقصات والمشتريات

مقارنة العطاءات والترسية

خذ مجلد عطاءات مُعادة لا تتطابق تماماً، وأرجعها إلى النطاق نفسه، وسلّم العميل قرار ترسية يصم…

3 خطوة12 دقيقةفتح