تسعير مناقصة على جدول الأسعار الذي يحكمها

حدّد جدول الأسعار الذي كُتب العقد على أساسه، حمّله كقاعدة تكلفة، سعّر الجدول منه، وتأكد أن كل بند يحمل مرجع بند الجدول الذي أُخذ منه قبل أن يغادر التقدير مكتبك.

5 خطوة22 دقيقةاستشارات التكاليف / قياس الكمياتمقاول عاممطوّر / عميلمكتب إدارة المشاريع / الإنشاء

كيف يعمل، خطوة بخطوة

5 خطوات عبر المنصة - ما تفعله في كل منها ولماذا يهم.

1

Settle which schedule the contract is written against

العقود

Read the tender conditions and record, against the contract, which schedule of rates governs it, which edition, and what price level it is stated at. Central government work names CPWD DSR; state work names the state PWD schedule; a private client may name neither and leave you on market rates.

لماذا: This is the one decision every later number depends on, and it is the one most often taken by assumption. Writing it down where the contract lives means the next person to open the estimate can see which document it was built from, instead of inferring it from the shape of the rates.

المدخلاتTender documentsWho is paying for the workالمخرجاتThe governing schedule, namedIts edition and price level
2

Load that schedule as a cost base, not as a column you typed

قاعدة بيانات التكاليف

Bring the schedule into the cost database through the ordinary import surface and check it landed with its item numbers, descriptions, units and rates intact. No commercial schedule ships with the product, so this is your own copy or your own cost history, loaded once and reused.

لماذا: A schedule loaded as data can be searched, versioned and re-priced next year. A schedule transcribed into a spreadsheet column becomes a set of numbers with no provenance the moment the person who typed them moves on, and every query about a rate turns into an archaeology exercise.

المدخلاتYour copy of the scheduleالمخرجاتCost base loaded and searchablePriced in INR
3

Price the bill and carry the item reference with the rate

جدول الكميات

Work down the bill sub-head by sub-head, from earthwork to external services, pulling each rate off the loaded schedule and keeping its item number on the line. Where no schedule item fits, price it as a non-schedule item and say so on the line rather than bending a neighbouring item to cover it.

لماذا: Non-schedule items are normal and are checked differently, by rate analysis rather than by lookup. Marking them at the point of pricing is what lets the department check the rest quickly and concentrate on the few that need argument, instead of treating the whole bill as unverified.

المدخلاتThe tender bill of quantitiesThe loaded scheduleالمخرجاتA priced billSchedule item on every line
4

Run the check that finds a rate with nothing behind it

التحقق

Validate the priced bill and read the findings. The India pack ships a rule that asks every priced line for its schedule item reference, so the lines you meant to mark as non-schedule and the lines you simply forgot both come back in one list.

لماذا: The difference between a deliberate non-schedule item and a forgotten reference is invisible in a printed bill and obvious in a validation run. Finding it here costs a few minutes; finding it after the tender is opened costs a technical query you answer under a clock.

المدخلاتThe priced billالمخرجاتLines with no item referenceA bill that passes before it is sent
5

Write down the basis while you still remember it

أساس التقدير

Record the schedule and edition used, the price level and base date, the lead and lift assumptions, which items are non-schedule and how they were analysed, and what the estimate excludes.

لماذا: An estimate on a public job is read months later by somebody who was not in the room, often during a query about a single item. The basis is what turns that from a defence of your memory into a reading of the file.

المدخلاتWhat you assumed and whyالمخرجاتA written basis of estimate
الوحدات

وحدات هذا الدليل

5 / 190 من وحدات المنصة

The market this case is written for

الهند

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

المزيد في التقدير والتكلفة

التقدير والتكلفة

Check an estimate before you send it

Put a priced bill through the validation rules, clear every warning and error, then export…

3 خطوة8 دقيقةفتح
التقدير والتكلفة

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 خطوة12 دقيقةفتح
التقدير والتكلفة

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 خطوة11 دقيقةفتح