Valorizzare una gara sul prezzario che la governa

Stabilisci quale prezzario regge il contratto, caricalo come base dei costi, valorizza il computo a partire da esso, e dimostra che ogni riga porta la voce del prezzario da cui deriva prima che la stima lasci la tua scrivania.

5 passaggi22 minConsulenza costi / QSImpresa generaleSviluppatore / committenteStudio di gestione progetti / cantieri

Come funziona, passo dopo passo

5 passi attraverso la piattaforma - cosa fare a ciascuno e perché conta.

1

Settle which schedule the contract is written against

Contratti

Read the tender conditions and record, against the contract, which schedule of rates governs it, which edition, and what price level it is stated at. Central government work names CPWD DSR; state work names the state PWD schedule; a private client may name neither and leave you on market rates.

Schermata, passaggio 1: Settle which schedule the contract is written against (Contratti, Valorizzare una gara sul prezzario che la governa)
Contratti: Settle which schedule the contract is written against

Perché: This is the one decision every later number depends on, and it is the one most often taken by assumption. Writing it down where the contract lives means the next person to open the estimate can see which document it was built from, instead of inferring it from the shape of the rates.

In entrataTender documentsWho is paying for the workIn uscitaThe governing schedule, namedIts edition and price level
2

Load that schedule as a cost base, not as a column you typed

Database dei costi

Bring the schedule into the cost database through the ordinary import surface and check it landed with its item numbers, descriptions, units and rates intact. No commercial schedule ships with the product, so this is your own copy or your own cost history, loaded once and reused.

Schermata, passaggio 2: Load that schedule as a cost base, not as a column you typed (Database dei costi, Valorizzare una gara sul prezzario che la governa)
Database dei costi: Load that schedule as a cost base, not as a column you typed

Perché: A schedule loaded as data can be searched, versioned and re-priced next year. A schedule transcribed into a spreadsheet column becomes a set of numbers with no provenance the moment the person who typed them moves on, and every query about a rate turns into an archaeology exercise.

In entrataYour copy of the scheduleIn uscitaCost base loaded and searchablePriced in INR
3

Price the bill and carry the item reference with the rate

Computo metrico estimativo

Work down the bill sub-head by sub-head, from earthwork to external services, pulling each rate off the loaded schedule and keeping its item number on the line. Where no schedule item fits, price it as a non-schedule item and say so on the line rather than bending a neighbouring item to cover it.

Schermata, passaggio 3: Price the bill and carry the item reference with the rate (Computo metrico estimativo, Valorizzare una gara sul prezzario che la governa)
Computo metrico estimativo: Price the bill and carry the item reference with the rate

Perché: Non-schedule items are normal and are checked differently, by rate analysis rather than by lookup. Marking them at the point of pricing is what lets the department check the rest quickly and concentrate on the few that need argument, instead of treating the whole bill as unverified.

In entrataThe tender bill of quantitiesThe loaded scheduleIn uscitaA priced billSchedule item on every line
4

Run the check that finds a rate with nothing behind it

Validazione

Validate the priced bill and read the findings. The India pack ships a rule that asks every priced line for its schedule item reference, so the lines you meant to mark as non-schedule and the lines you simply forgot both come back in one list.

Schermata, passaggio 4: Run the check that finds a rate with nothing behind it (Validazione, Valorizzare una gara sul prezzario che la governa)
Validazione: Run the check that finds a rate with nothing behind it

Perché: The difference between a deliberate non-schedule item and a forgotten reference is invisible in a printed bill and obvious in a validation run. Finding it here costs a few minutes; finding it after the tender is opened costs a technical query you answer under a clock.

In entrataThe priced billIn uscitaLines with no item referenceA bill that passes before it is sent
5

Write down the basis while you still remember it

Base della stima

Record the schedule and edition used, the price level and base date, the lead and lift assumptions, which items are non-schedule and how they were analysed, and what the estimate excludes.

Perché: An estimate on a public job is read months later by somebody who was not in the room, often during a query about a single item. The basis is what turns that from a defence of your memory into a reading of the file.

In entrataWhat you assumed and whyIn uscitaA written basis of estimate
Moduli

Moduli di questo playbook

5 / 190 moduli della piattaforma

The market this case is written for

India

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Altro in Stima e costi

Stima e costi

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 passaggi12 minApri
Stima e costi

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 passaggi11 minApri