Одобрете estimacion и я фактурирайте като CFDI

Остойностете периода concepto по concepto, оценете го спрямо precios unitarios, амортизирайте anticipo и задръжте fondo de garantia, оставете residente de obra да одобри estimacion и издайте CFDI спрямо одобрената сума.

7 стъпки12 минГлавен изпълнителСпециализиран подизпълнителИнвеститор / възложител

Как работи, стъпка по стъпка

7 стъпки през платформата - какво правите на всяка и защо е важно.

1

Measure the period concepto by concepto

Напредък

Record what was executed against each concepto for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

Екранна снимка, стъпка 1: Measure the period concepto by concepto (Напредък, Одобрете estimacion и я фактурирайте като CFDI)
Напредък: Measure the period concepto by concepto

Защо: An estimacion built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one concepto rather than about the whole month, and the rest of the money moves while that one is settled.

ВходCatalogo de conceptosWork executed this periodРезултатPercent complete per conceptoVolumenes for the period
2

Value it at the contract rates

Количествена сметка

Read the valuation back against the bill and check the rates it used are the contract rates. Where a concepto has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

Екранна снимка, стъпка 2: Value it at the contract rates (Количествена сметка, Одобрете estimacion и я фактурирайте като CFDI)
Количествена сметка: Value it at the contract rates

Защо: A concepto extraordinario certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.

ВходVolumenes for the periodPrecios unitariosРезултатEstimacion for the periodConceptos extraordinarios flagged
3

Apply fondo de garantia and previous payments

Финанси

Take the cumulative valuation, subtract what has already been certified, and apply fondo de garantia at the contract percentage. The figure that leaves this step is the one the CFDI is raised for, and the backup behind it is the measure that produced it. The anticipo is amortised on the same proportion the period earned, so an estimacion that measures more also repays more. Left to a fixed monthly figure it finishes the works still owing, and the last estimacion is the one that discovers it.

Екранна снимка, стъпка 3: Apply fondo de garantia and previous payments (Финанси, Одобрете estimacion и я фактурирайте като CFDI)
Финанси: Apply fondo de garantia and previous payments

Защо: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured.

ВходCumulative estimacionAnticipo outstandingPrevious paymentsРезултатAmortizacion del anticipoNet due for the period
4

Get it approved by the people who have to approve it

Маршрути за одобрение

Route the estimacion to the residente de obra, and to whoever the contract adds after them. Keep the approval date, because the CFDI follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it.

Екранна снимка, стъпка 4: Get it approved by the people who have to approve it (Маршрути за одобрение, Одобрете estimacion и я фактурирайте като CFDI)
Маршрути за одобрение: Get it approved by the people who have to approve it

Защо: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.

ВходEstimacion for the periodResidente de obra named for authorisationРезултатAuthorised estimacionAuthorisation date on record
5

Issue the CFDI against the approved figure

Финанси

Raise the CFDI against the approved estimacion, carrying fondo de garantia and any deduction the contract provides for, and reference the estimacion on it. A stamped CFDI is corrected by cancelling it and issuing another, not by editing it, so the figure has to be right before it is stamped rather than after.

Екранна снимка, стъпка 5: Issue the CFDI against the approved figure (Финанси, Одобрете estimacion и я фактурирайте като CFDI)
Финанси: Issue the CFDI against the approved figure

Защо: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the estimacion also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

ВходAuthorised estimacionRetenciones and deductionsРезултатCFDI issued and stampedAmount carried into the accounts
6

Open the payment clock on the right day

Часовник за плащане

Open a clock over the CFDI starting from the authorisation of the estimacion, under the public works payment rules. Payment falls due 20 days later, and the clock records that date rather than leaving it to be worked out when somebody asks.

Защо: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the authorisation of the estimacion once makes the whole chain checkable.

ВходCFDI and its dateAuthorisation dateРезултатOpen payment clockDue date computed
7

Reconcile what was certified against what was asked

Съгласуване на събития

Put the approved figure next to the figure you asked for and carry the difference forward. What is unpaid, and how long it has been unpaid, belongs in the accounts as a number rather than in a conversation.

Защо: The gap between applied and certified is the health of the commercial relationship expressed as money, and it is only visible if somebody puts the two numbers side by side every period. Cumulatively it is also the single best predictor of a final account fight.

ВходAmount invoicedAmount authorisedРезултатDifference carried forwardOutstanding by age
Модули

Модули в този наръчник

6 / 190 модула на платформата

The market this case is written for

Мексико

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.