케이스 / 상업 및 계약
상업 및 계약

estimación을 승인하고 CFDI로 청구하기

concepto별로 기간을 실측하고, precios unitarios에 대조해 가격을 매기고, anticipo를 상각하고 fondo de garantía를 유보하고, residente de obra가 estimación을 승인하게 하고, 승인된 금액에 대해 CFDI를 발행한다.

7단계12 분종합건설사전문건설사시행사 / 발주처

작동 방식, 단계별로

플랫폼 전반에 걸친 7단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Measure the period concepto by concepto

진척

Record what was executed against each concepto for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

이유: An estimacion built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one concepto rather than about the whole month, and the rest of the money moves while that one is settled.

입력Catalogo de conceptosWork executed this period결과Percent complete per conceptoVolumenes for the period
2

Value it at the contract rates

내역서

Read the valuation back against the bill and check the rates it used are the contract rates. Where a concepto has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

이유: A concepto extraordinario certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.

입력Volumenes for the periodPrecios unitarios결과Estimacion for the periodConceptos extraordinarios flagged
3

Apply fondo de garantia and previous payments

재무

Take the cumulative valuation, subtract what has already been certified, and apply fondo de garantia at the contract percentage. The figure that leaves this step is the one the CFDI is raised for, and the backup behind it is the measure that produced it. The anticipo is amortised on the same proportion the period earned, so an estimacion that measures more also repays more. Left to a fixed monthly figure it finishes the works still owing, and the last estimacion is the one that discovers it.

이유: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured.

입력Cumulative estimacionAnticipo outstandingPrevious payments결과Amortizacion del anticipoNet due for the period
4

Get it approved by the people who have to approve it

승인 경로

Route the estimacion to the residente de obra, and to whoever the contract adds after them. Keep the approval date, because the CFDI follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it.

이유: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.

입력Estimacion for the periodResidente de obra named for authorisation결과Authorised estimacionAuthorisation date on record
5

Issue the CFDI against the approved figure

재무

Raise the CFDI against the approved estimacion, carrying fondo de garantia and any deduction the contract provides for, and reference the estimacion on it. A stamped CFDI is corrected by cancelling it and issuing another, not by editing it, so the figure has to be right before it is stamped rather than after.

이유: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the estimacion also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

입력Authorised estimacionRetenciones and deductions결과CFDI issued and stampedAmount carried into the accounts
6

Open the payment clock on the right day

지급 시계

Open a clock over the CFDI starting from the authorisation of the estimacion, under the public works payment rules. Payment falls due 20 days later, and the clock records that date rather than leaving it to be worked out when somebody asks.

이유: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the authorisation of the estimacion once makes the whole chain checkable.

입력CFDI and its dateAuthorisation date결과Open payment clockDue date computed
7

Reconcile what was certified against what was asked

사건 대사

Put the approved figure next to the figure you asked for and carry the difference forward. What is unpaid, and how long it has been unpaid, belongs in the accounts as a number rather than in a conversation.

이유: The gap between applied and certified is the health of the commercial relationship expressed as money, and it is only visible if somebody puts the two numbers side by side every period. Cumulatively it is also the single best predictor of a final account fight.

입력Amount invoicedAmount authorised결과Difference carried forwardOutstanding by age
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 6

The market this case is written for

멕시코

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

상업 및 계약 카테고리의 더 보기

상업 및 계약

변경사항을 유상 변경계약으로 전환

신선할 때 범위 변경을 기록하고, 합의된 단가로 계약 변경계약으로 산정한 뒤 다음 기성청구에 포함시켜, 추가 작업을 조용히 흡수하지 않고 회수합니다.

3단계11 분열기
상업 및 계약

협력업체 패키지 운영

협력업체에 공종 패키지를 발주하고, 기성 내역서와 유보금 조건을 포함한 하도급 계약으로 전환한 뒤, 실제 완료된 작업에 대해 기성 청구별로 지급합니다.

3단계11 분열기
상업 및 계약

기성 청구 및 대사

계약서 대비 해당 기간 시공된 물량을 평가하고, 근거 자료와 함께 기성 청구를 제출하며, 승인된 금액을 실제 입금액과 대조 확인한다.

3단계12 분열기