案例 / 商务与合同
商务与合同

批准 estimación 并以 CFDI 形式开票

按每个 concepto 计量本期完成量,按 precios unitarios 计价,摊销 anticipo 并扣留 fondo de garantía,由 residente de obra 批准 estimación,再据此开具 CFDI。

7 个步骤12 分钟总承包商专业分包商开发商/业主

运作方式,逐步说明

贯穿平台的 7 个步骤 - 每一步做什么,以及为什么重要。

1

Measure the period concepto by concepto

进度

Record what was executed against each concepto for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

原因: An estimacion built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one concepto rather than about the whole month, and the rest of the money moves while that one is settled.

输入Catalogo de conceptosWork executed this period成果Percent complete per conceptoVolumenes for the period
2

Value it at the contract rates

工程量清单

Read the valuation back against the bill and check the rates it used are the contract rates. Where a concepto has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

原因: A concepto extraordinario certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.

输入Volumenes for the periodPrecios unitarios成果Estimacion for the periodConceptos extraordinarios flagged
3

Apply fondo de garantia and previous payments

财务

Take the cumulative valuation, subtract what has already been certified, and apply fondo de garantia at the contract percentage. The figure that leaves this step is the one the CFDI is raised for, and the backup behind it is the measure that produced it. The anticipo is amortised on the same proportion the period earned, so an estimacion that measures more also repays more. Left to a fixed monthly figure it finishes the works still owing, and the last estimacion is the one that discovers it.

原因: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured.

输入Cumulative estimacionAnticipo outstandingPrevious payments成果Amortizacion del anticipoNet due for the period
4

Get it approved by the people who have to approve it

审批路线

Route the estimacion to the residente de obra, and to whoever the contract adds after them. Keep the approval date, because the CFDI follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it.

原因: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.

输入Estimacion for the periodResidente de obra named for authorisation成果Authorised estimacionAuthorisation date on record
5

Issue the CFDI against the approved figure

财务

Raise the CFDI against the approved estimacion, carrying fondo de garantia and any deduction the contract provides for, and reference the estimacion on it. A stamped CFDI is corrected by cancelling it and issuing another, not by editing it, so the figure has to be right before it is stamped rather than after.

原因: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the estimacion also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

输入Authorised estimacionRetenciones and deductions成果CFDI issued and stampedAmount carried into the accounts
6

Open the payment clock on the right day

付款时钟

Open a clock over the CFDI starting from the authorisation of the estimacion, under the public works payment rules. Payment falls due 20 days later, and the clock records that date rather than leaving it to be worked out when somebody asks.

原因: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the authorisation of the estimacion once makes the whole chain checkable.

输入CFDI and its dateAuthorisation date成果Open payment clockDue date computed
7

Reconcile what was certified against what was asked

事件对账

Put the approved figure next to the figure you asked for and carry the difference forward. What is unpaid, and how long it has been unpaid, belongs in the accounts as a number rather than in a conversation.

原因: The gap between applied and certified is the health of the commercial relationship expressed as money, and it is only visible if somebody puts the two numbers side by side every period. Cumulatively it is also the single best predictor of a final account fight.

输入Amount invoicedAmount authorised成果Difference carried forwardOutstanding by age
模块

此方案使用的模块

190 个平台模块中的 6

The market this case is written for

墨西哥

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

更多 商务与合同 案例

商务与合同

把变更转化为已付款的变更单

在范围变更还新鲜时就记录下来,依据你已约定的单价将其作为合同变更报价,并在下一期进度付款申请中计入,使额外工作能够获得补偿,而不是被悄悄吸收。

3 个步骤11 分钟打开
商务与合同

管理分包工程

将某工种分包给分包商,以带付款计划表和保留金条款的分包合同确定下来,再按实际完成的工作逐期支付款项。

3 个步骤11 分钟打开
商务与合同

付款申请与对账

按合同对本期已完成工作进行估值,附上依据提出申请,并将已核证的金额与账户实际到账的金额进行对账。

3 个步骤12 分钟打开