Scenariji / Komercijala i ugovori
Komercijala i ugovori

Odobrite estimación i fakturirajte je kao CFDI

Izmjerite razdoblje concepto po concepto, formirajte vrijednost prema precios unitarios, amortizirajte anticipo i zadržite fondo de garantía, neka residente de obra odobri estimación i izdajte CFDI na odobreni iznos.

7 koraka12 minGlavni izvođačSpecijalizirani podizvođačInvestitor / naručitelj

Kako funkcionira, korak po korak

7 koraka kroz platformu - što radite u svakom i zašto je važno.

1

Measure the period concepto by concepto

Napredak

Record what was executed against each concepto for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

Snimka zaslona, korak 1: Measure the period concepto by concepto (Napredak, Odobrite estimación i fakturirajte je kao CFDI)
Napredak: Measure the period concepto by concepto

Zašto: An estimacion built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one concepto rather than about the whole month, and the rest of the money moves while that one is settled.

UlazCatalogo de conceptosWork executed this periodRezultatPercent complete per conceptoVolumenes for the period
2

Value it at the contract rates

Troškovnik

Read the valuation back against the bill and check the rates it used are the contract rates. Where a concepto has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

Snimka zaslona, korak 2: Value it at the contract rates (Troškovnik, Odobrite estimación i fakturirajte je kao CFDI)
Troškovnik: Value it at the contract rates

Zašto: A concepto extraordinario certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.

UlazVolumenes for the periodPrecios unitariosRezultatEstimacion for the periodConceptos extraordinarios flagged
3

Apply fondo de garantia and previous payments

Financije

Take the cumulative valuation, subtract what has already been certified, and apply fondo de garantia at the contract percentage. The figure that leaves this step is the one the CFDI is raised for, and the backup behind it is the measure that produced it. The anticipo is amortised on the same proportion the period earned, so an estimacion that measures more also repays more. Left to a fixed monthly figure it finishes the works still owing, and the last estimacion is the one that discovers it.

Snimka zaslona, korak 3: Apply fondo de garantia and previous payments (Financije, Odobrite estimación i fakturirajte je kao CFDI)
Financije: Apply fondo de garantia and previous payments

Zašto: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured.

UlazCumulative estimacionAnticipo outstandingPrevious paymentsRezultatAmortizacion del anticipoNet due for the period
4

Get it approved by the people who have to approve it

Rute odobravanja

Route the estimacion to the residente de obra, and to whoever the contract adds after them. Keep the approval date, because the CFDI follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it.

Snimka zaslona, korak 4: Get it approved by the people who have to approve it (Rute odobravanja, Odobrite estimación i fakturirajte je kao CFDI)
Rute odobravanja: Get it approved by the people who have to approve it

Zašto: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.

UlazEstimacion for the periodResidente de obra named for authorisationRezultatAuthorised estimacionAuthorisation date on record
5

Issue the CFDI against the approved figure

Financije

Raise the CFDI against the approved estimacion, carrying fondo de garantia and any deduction the contract provides for, and reference the estimacion on it. A stamped CFDI is corrected by cancelling it and issuing another, not by editing it, so the figure has to be right before it is stamped rather than after.

Snimka zaslona, korak 5: Issue the CFDI against the approved figure (Financije, Odobrite estimación i fakturirajte je kao CFDI)
Financije: Issue the CFDI against the approved figure

Zašto: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the estimacion also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

UlazAuthorised estimacionRetenciones and deductionsRezultatCFDI issued and stampedAmount carried into the accounts
6

Open the payment clock on the right day

Sat plaćanja

Open a clock over the CFDI starting from the authorisation of the estimacion, under the public works payment rules. Payment falls due 20 days later, and the clock records that date rather than leaving it to be worked out when somebody asks.

Zašto: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the authorisation of the estimacion once makes the whole chain checkable.

UlazCFDI and its dateAuthorisation dateRezultatOpen payment clockDue date computed
7

Reconcile what was certified against what was asked

Usklađivanje događaja

Put the approved figure next to the figure you asked for and carry the difference forward. What is unpaid, and how long it has been unpaid, belongs in the accounts as a number rather than in a conversation.

Zašto: The gap between applied and certified is the health of the commercial relationship expressed as money, and it is only visible if somebody puts the two numbers side by side every period. Cumulatively it is also the single best predictor of a final account fight.

UlazAmount invoicedAmount authorisedRezultatDifference carried forwardOutstanding by age
Moduli

Moduli u ovom playbooku

6 / 190 modula platforme

The market this case is written for

Meksiko

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Više u kategoriji Komercijala i ugovori

Komercijala i ugovori

Vodite podizvođački paket

Dodijelite paket radova podizvođaču, sklopite podugovor s tabelarnim pregledom vrijednosti i…

3 koraka11 minOtvori
Komercijala i ugovori

Zahtjev za plaćanje i usklađivanje

Vrednujte radove izvedene u ovom razdoblju u odnosu na ugovor, podnesite zahtjev za plaćanje…

3 koraka12 minOtvori