אישור ה-estimacion והפקתה כ-CFDI

מדדו את התקופה concepto אחר concepto, תמחרו אותה מול precios unitarios, הפחיתו את ה-anticipo ושמרו את ה-fondo de garantia, בקשו מה-residente de obra לאשר את ה-estimacion והוציאו CFDI מול הנתון המאושר.

7 שלבים12 דק׳קבלן ראשיקבלן משנה מתמחהיזם / לקוח

איך זה עובד, שלב אחר שלב

7 שלבים לאורך הפלטפורמה - מה עושים בכל שלב ולמה זה חשוב.

1

Measure the period concepto by concepto

התקדמות

Record what was executed against each concepto for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.

למה: An estimacion built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one concepto rather than about the whole month, and the rest of the money moves while that one is settled.

נכנסCatalogo de conceptosWork executed this periodיוצאPercent complete per conceptoVolumenes for the period
2

Value it at the contract rates

כתב כמויות

Read the valuation back against the bill and check the rates it used are the contract rates. Where a concepto has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.

למה: A concepto extraordinario certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.

נכנסVolumenes for the periodPrecios unitariosיוצאEstimacion for the periodConceptos extraordinarios flagged
3

Apply fondo de garantia and previous payments

כספים

Take the cumulative valuation, subtract what has already been certified, and apply fondo de garantia at the contract percentage. The figure that leaves this step is the one the CFDI is raised for, and the backup behind it is the measure that produced it. The anticipo is amortised on the same proportion the period earned, so an estimacion that measures more also repays more. Left to a fixed monthly figure it finishes the works still owing, and the last estimacion is the one that discovers it.

למה: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured.

נכנסCumulative estimacionAnticipo outstandingPrevious paymentsיוצאAmortizacion del anticipoNet due for the period
4

Get it approved by the people who have to approve it

מסלולי אישור

Route the estimacion to the residente de obra, and to whoever the contract adds after them. Keep the approval date, because the CFDI follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it.

למה: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.

נכנסEstimacion for the periodResidente de obra named for authorisationיוצאAuthorised estimacionAuthorisation date on record
5

Issue the CFDI against the approved figure

כספים

Raise the CFDI against the approved estimacion, carrying fondo de garantia and any deduction the contract provides for, and reference the estimacion on it. A stamped CFDI is corrected by cancelling it and issuing another, not by editing it, so the figure has to be right before it is stamped rather than after.

למה: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the estimacion also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.

נכנסAuthorised estimacionRetenciones and deductionsיוצאCFDI issued and stampedAmount carried into the accounts
6

Open the payment clock on the right day

שעון תשלום

Open a clock over the CFDI starting from the authorisation of the estimacion, under the public works payment rules. Payment falls due 20 days later, and the clock records that date rather than leaving it to be worked out when somebody asks.

למה: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the authorisation of the estimacion once makes the whole chain checkable.

נכנסCFDI and its dateAuthorisation dateיוצאOpen payment clockDue date computed
7

Reconcile what was certified against what was asked

התאמת אירועים

Put the approved figure next to the figure you asked for and carry the difference forward. What is unpaid, and how long it has been unpaid, belongs in the accounts as a number rather than in a conversation.

למה: The gap between applied and certified is the health of the commercial relationship expressed as money, and it is only visible if somebody puts the two numbers side by side every period. Cumulatively it is also the single best predictor of a final account fight.

נכנסAmount invoicedAmount authorisedיוצאDifference carried forwardOutstanding by age
מודולים

המודולים בתרחיש הזה

6 מתוך 190 מודולי הפלטפורמה

The market this case is written for

מקסיקו

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CFDI 4.0
  • Ley de Obras Publicas

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

עוד ב-מסחרי וחוזים

מסחרי וחוזים

הפיכת שינוי לשינוי חוזי משולם

תעדו שינוי היקף בעוד הוא טרי, תמחרו אותו כשינוי חוזי לפי התעריפים המוסכמים שלכם, וחייבו אותו…

3 שלבים11 דק׳פתיחה
מסחרי וחוזים

ניהול חבילת קבלן משנה

העניקו חבילת עבודה לקבלן משנה, הציבו אותה על חוזה משנה עם לוח ערכים וניכוי עיכבון, ואז שלמו…

3 שלבים11 דק׳פתיחה
מסחרי וחוזים

בקשת תשלום והתאמה

העריכו את העבודה שבוצעה בתקופה זו מול החוזה, העלו את הבקשה עם הראיות מאחוריה, והתאימו את מה…

3 שלבים12 דק׳פתיחה