Convertir un cambio en una modificación pagada
Registra un cambio de alcance mientras está reciente, valóralo como una modificación contrac…
Mida el período concepto por concepto, valórelo frente a los precios unitarios, amortice el anticipo y retenga el fondo de garantía, haga que el residente de obra autorice la estimación y emita el CFDI sobre la cifra autorizada.
7 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.
Record what was executed against each concepto for the period as a percentage of its contract quantity. The earned quantity follows from that percentage and the design quantity, and the earned amount from the same percentage and the position total, so one honest number per line produces the whole valuation.
Por que: An estimacion built from a single project percentage cannot be checked and therefore cannot be approved without a conversation. Measured line by line, the disagreement is about one concepto rather than about the whole month, and the rest of the money moves while that one is settled.
Read the valuation back against the bill and check the rates it used are the contract rates. Where a concepto has been measured past the quantity the contract carries, deal with it as a change to the position with an order behind it rather than as a larger figure on the same line.
Por que: A concepto extraordinario certified quietly is one the client can refuse at the final account, months after the work was built and paid for down the chain. Raising it as a change while it is small is the only version of that conversation where you are not asking to be paid for work already done.
Take the cumulative valuation, subtract what has already been certified, and apply fondo de garantia at the contract percentage. The figure that leaves this step is the one the CFDI is raised for, and the backup behind it is the measure that produced it. The anticipo is amortised on the same proportion the period earned, so an estimacion that measures more also repays more. Left to a fixed monthly figure it finishes the works still owing, and the last estimacion is the one that discovers it.
Por que: Interim payments are cumulative, so the month's money is a difference between two totals rather than a total of its own. Computing it from the cumulative figure is what stops a line being paid twice or dropped entirely when a period is re-measured.
Route the estimacion to the residente de obra, and to whoever the contract adds after them. Keep the approval date, because the CFDI follows the approval and the payment clock runs from there, so an approval that slips moves everything behind it.
Por que: Approval sitting in an inbox is the most common reason a payment is late, and it is invisible while it is happening because nobody has refused anything. A route with a date on each hop turns that into a question with an owner instead of a monthly complaint.
Raise the CFDI against the approved estimacion, carrying fondo de garantia and any deduction the contract provides for, and reference the estimacion on it. A stamped CFDI is corrected by cancelling it and issuing another, not by editing it, so the figure has to be right before it is stamped rather than after.
Por que: A demand for a figure nobody approved is one that will be returned, and the clock does not start on a returned document. Matching it to the estimacion also means the accounts and the valuation tell the same story at year end without anybody reconciling them by hand.
Open a clock over the CFDI starting from the authorisation of the estimacion, under the public works payment rules. Payment falls due 20 days later, and the clock records that date rather than leaving it to be worked out when somebody asks.
Por que: The single most expensive mistake in interim payment is starting the count on the wrong event, because every deadline behind it inherits the error and none of them look wrong. Anchoring on the authorisation of the estimacion once makes the whole chain checkable.
Put the approved figure next to the figure you asked for and carry the difference forward. What is unpaid, and how long it has been unpaid, belongs in the accounts as a number rather than in a conversation.
Por que: The gap between applied and certified is the health of the commercial relationship expressed as money, and it is only visible if somebody puts the two numbers side by side every period. Cumulatively it is also the single best predictor of a final account fight.
6 / 190 módulos de la plataforma
Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.
Normas que sigue
No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.
Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.
Registra un cambio de alcance mientras está reciente, valóralo como una modificación contrac…
Adjudica un paquete de trabajos a un subcontratista, formalízalo en un subcontrato con un cu…
Valora la obra ejecutada este periodo frente al contrato, presenta la solicitud con su docum…