Případy / Rozpočtování a náklady
Rozpočtování a náklady

Rozebrat položku sazebníku na práci, materiál a mechanizaci

Rozeberte položku sazebníku na materiál, práci a mechanizaci, kterou skutečně spotřebovává, naceňte je vlastními sazbami, veďte zisk a režii jako viditelné procento, a uložte výsledek jako sestavu, kterou dokážete obhájit a znovu použít.

5 kroků20 minNákladové poradenství / rozpočtářstvíGenerální dodavatelSpecializovaný subdodavatelDeveloper / klient

Jak to funguje, krok za krokem

5 kroků napříč platformou - co na každém uděláte a proč na tom záleží.

1

Find the item and read what its rate is supposed to include

Databáze cen

Locate the nearest schedule item to the work in hand and read its description against the specification: the grade, the thickness, whether centering and shuttering are inside the item or billed separately, whether carriage is included.

Snímek obrazovky, krok 1: Find the item and read what its rate is supposed to include (Databáze cen, Rozebrat položku sazebníku na práci, materiál a mechanizaci)
Databáze cen: Find the item and read what its rate is supposed to include

Proč: Most rate arguments are really description arguments. Two people agree on the cost of concrete and disagree about whether the item was supposed to include the formwork, and no amount of analysis settles that. Reading the description first tells you whether you are analysing a rate or discovering a missing item.

VstupThe loaded schedule of ratesThe specification for the workVýstupThe item and what its rate covers
2

Open the unit into what it consumes

Výkonové normy

Expand one unit of the item into its constituents: the materials and their wastage allowance, the trade and helper hours to place them, and the plant hours the method needs. Adjust the assumed method where your site does it differently, and leave a note saying so.

Snímek obrazovky, krok 2: Open the unit into what it consumes (Výkonové normy, Rozebrat položku sazebníku na práci, materiál a mechanizaci)
Výkonové normy: Open the unit into what it consumes

Proč: This step is where an inherited norm meets a real site, and the mismatch is worth finding now. A norm that assumes machine mixing on a job doing hand mixing will be wrong in the labour line and right in the material line, and only an opened analysis shows you which half to trust.

VstupThe construction method assumedOne unit of finished workVýstupMaterial per unit, with wastageLabour and plant hours per unit
3

Price the hours at what labour costs you

Mzdové sazby

Build the labour rate per trade from the wage you pay plus what sits on top of it: the statutory contributions, the site allowances, the non-productive time you carry. Use the minimum wage notified for the state as a floor rather than as the answer.

Snímek obrazovky, krok 3: Price the hours at what labour costs you (Mzdové sazby, Rozebrat položku sazebníku na práci, materiál a mechanizaci)
Mzdové sazby: Price the hours at what labour costs you

Proč: Labour is where a schedule rate ages fastest and where a contractor's own figure is genuinely better information than a published one. It is also the constituent most often priced at the bare wage, which quietly removes the contribution and allowance cost from every item in the estimate at once.

VstupHours from the analysisThe wages you actually payVýstupAn all-in rate per trade
4

Save it as an assembly, with the percentage kept outside

Sestavy

Store the analysis as a named assembly so the next bill can use it, and keep the contractor's profit and overheads as a percentage on the direct cost rather than absorbing it into the constituent prices.

Snímek obrazovky, krok 4: Save it as an assembly, with the percentage kept outside (Sestavy, Rozebrat položku sazebníku na práci, materiál a mechanizaci)
Sestavy: Save it as an assembly, with the percentage kept outside

Proč: A tender is often accepted at a percentage above or below the estimated rates, and an assembly whose profit line is visible can be re-quoted at a different percentage in one move. One whose profit is spread through the material prices has to be rebuilt from the beginning, and usually is not.

VstupThe priced constituentsVýstupA reusable analysed rateProfit and overheads as their own line
5

Hold your rate against the published one

Průzkumník nákladů

Compare the analysed rate with the schedule rate for the same item and look at the constituents rather than the totals. Note which constituent carries the difference: material price, labour, plant, or the percentage on top.

Proč: A gap in the material line usually means the schedule is out of date and is an argument you can win with quotations. A gap in the labour line usually means the method differs and is an argument you win with the analysis. Knowing which one you have before the meeting decides how it goes.

VstupYour analysed rateThe published schedule rateVýstupWhere the two disagree, and why
Moduly

Moduly v tomto playbooku

5 / 190 modulů platformy

The market this case is written for

Indie

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Více v kategorii Rozpočtování a náklady

Rozpočtování a náklady

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 kroků12 minOtevřít
Rozpočtování a náklady

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 kroků11 minOtevřít