Analyser en satslistepris i arbeid, materiell og maskin

Åpne en satslistepost i materialet, arbeidet og maskinene den faktisk forbruker, prissett dem med dine egne satser, hold fortjeneste og påslag som en synlig prosent, og lagre resultatet som en montasje du kan forsvare og gjenbruke.

5 trinn20 minKostnadsrådgivning / kalkulasjonHovedentreprenørSpesialisert underentreprenørUtbygger / byggherre

Slik fungerer det, steg for steg

5 trinn gjennom plattformen - hva du gjør i hvert og hvorfor det betyr noe.

1

Find the item and read what its rate is supposed to include

Kostnadsdatabase

Locate the nearest schedule item to the work in hand and read its description against the specification: the grade, the thickness, whether centering and shuttering are inside the item or billed separately, whether carriage is included.

Skjermbilde, trinn 1: Find the item and read what its rate is supposed to include (Kostnadsdatabase, Analyser en satslistepris i arbeid, materiell og maskin)
Kostnadsdatabase: Find the item and read what its rate is supposed to include

Hvorfor: Most rate arguments are really description arguments. Two people agree on the cost of concrete and disagree about whether the item was supposed to include the formwork, and no amount of analysis settles that. Reading the description first tells you whether you are analysing a rate or discovering a missing item.

InndataThe loaded schedule of ratesThe specification for the workResultatThe item and what its rate covers
2

Open the unit into what it consumes

Produksjonsnormer

Expand one unit of the item into its constituents: the materials and their wastage allowance, the trade and helper hours to place them, and the plant hours the method needs. Adjust the assumed method where your site does it differently, and leave a note saying so.

Skjermbilde, trinn 2: Open the unit into what it consumes (Produksjonsnormer, Analyser en satslistepris i arbeid, materiell og maskin)
Produksjonsnormer: Open the unit into what it consumes

Hvorfor: This step is where an inherited norm meets a real site, and the mismatch is worth finding now. A norm that assumes machine mixing on a job doing hand mixing will be wrong in the labour line and right in the material line, and only an opened analysis shows you which half to trust.

InndataThe construction method assumedOne unit of finished workResultatMaterial per unit, with wastageLabour and plant hours per unit
3

Price the hours at what labour costs you

Timesatser

Build the labour rate per trade from the wage you pay plus what sits on top of it: the statutory contributions, the site allowances, the non-productive time you carry. Use the minimum wage notified for the state as a floor rather than as the answer.

Skjermbilde, trinn 3: Price the hours at what labour costs you (Timesatser, Analyser en satslistepris i arbeid, materiell og maskin)
Timesatser: Price the hours at what labour costs you

Hvorfor: Labour is where a schedule rate ages fastest and where a contractor's own figure is genuinely better information than a published one. It is also the constituent most often priced at the bare wage, which quietly removes the contribution and allowance cost from every item in the estimate at once.

InndataHours from the analysisThe wages you actually payResultatAn all-in rate per trade
4

Save it as an assembly, with the percentage kept outside

Sammensatte poster

Store the analysis as a named assembly so the next bill can use it, and keep the contractor's profit and overheads as a percentage on the direct cost rather than absorbing it into the constituent prices.

Skjermbilde, trinn 4: Save it as an assembly, with the percentage kept outside (Sammensatte poster, Analyser en satslistepris i arbeid, materiell og maskin)
Sammensatte poster: Save it as an assembly, with the percentage kept outside

Hvorfor: A tender is often accepted at a percentage above or below the estimated rates, and an assembly whose profit line is visible can be re-quoted at a different percentage in one move. One whose profit is spread through the material prices has to be rebuilt from the beginning, and usually is not.

InndataThe priced constituentsResultatA reusable analysed rateProfit and overheads as their own line
5

Hold your rate against the published one

Cost Explorer

Compare the analysed rate with the schedule rate for the same item and look at the constituents rather than the totals. Note which constituent carries the difference: material price, labour, plant, or the percentage on top.

Hvorfor: A gap in the material line usually means the schedule is out of date and is an argument you can win with quotations. A gap in the labour line usually means the method differs and is an argument you win with the analysis. Knowing which one you have before the meeting decides how it goes.

InndataYour analysed rateThe published schedule rateResultatWhere the two disagree, and why
Moduler

Moduler i denne playbooken

5 / 190 plattformmoduler

The market this case is written for

India

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Mer innen Kalkyle og kostnader

Kalkyle og kostnader

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 trinn12 minÅpne
Kalkyle og kostnader

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 trinn11 minÅpne