ケース / 積算とコスト
積算とコスト

単価表の単価を労務・材料・機械費に分解する

単価表の項目を実際に消費する材料・労務・機械に分解し、自社の単価で価格を付け、利益と諸経費を目に見える割合として残し、その結果を防御でき再利用できる歩掛りとして保存する。

5ステップ20 分コストコンサルティング会社 / 積算事務所総合建設会社専門工事業者デベロッパー / 発注者

仕組みをステップごとに

プラットフォーム全体で5ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

Find the item and read what its rate is supposed to include

単価データベース

Locate the nearest schedule item to the work in hand and read its description against the specification: the grade, the thickness, whether centering and shuttering are inside the item or billed separately, whether carriage is included.

理由: Most rate arguments are really description arguments. Two people agree on the cost of concrete and disagree about whether the item was supposed to include the formwork, and no amount of analysis settles that. Reading the description first tells you whether you are analysing a rate or discovering a missing item.

入力The loaded schedule of ratesThe specification for the work出力The item and what its rate covers
2

Open the unit into what it consumes

歩掛

Expand one unit of the item into its constituents: the materials and their wastage allowance, the trade and helper hours to place them, and the plant hours the method needs. Adjust the assumed method where your site does it differently, and leave a note saying so.

理由: This step is where an inherited norm meets a real site, and the mismatch is worth finding now. A norm that assumes machine mixing on a job doing hand mixing will be wrong in the labour line and right in the material line, and only an opened analysis shows you which half to trust.

入力The construction method assumedOne unit of finished work出力Material per unit, with wastageLabour and plant hours per unit
3

Price the hours at what labour costs you

労務単価

Build the labour rate per trade from the wage you pay plus what sits on top of it: the statutory contributions, the site allowances, the non-productive time you carry. Use the minimum wage notified for the state as a floor rather than as the answer.

理由: Labour is where a schedule rate ages fastest and where a contractor's own figure is genuinely better information than a published one. It is also the constituent most often priced at the bare wage, which quietly removes the contribution and allowance cost from every item in the estimate at once.

入力Hours from the analysisThe wages you actually pay出力An all-in rate per trade
4

Save it as an assembly, with the percentage kept outside

複合単価

Store the analysis as a named assembly so the next bill can use it, and keep the contractor's profit and overheads as a percentage on the direct cost rather than absorbing it into the constituent prices.

理由: A tender is often accepted at a percentage above or below the estimated rates, and an assembly whose profit line is visible can be re-quoted at a different percentage in one move. One whose profit is spread through the material prices has to be rebuilt from the beginning, and usually is not.

入力The priced constituents出力A reusable analysed rateProfit and overheads as their own line
5

Hold your rate against the published one

Cost Explorer

Compare the analysed rate with the schedule rate for the same item and look at the constituents rather than the totals. Note which constituent carries the difference: material price, labour, plant, or the percentage on top.

理由: A gap in the material line usually means the schedule is out of date and is an argument you can win with quotations. A gap in the labour line usually means the method differs and is an argument you win with the analysis. Knowing which one you have before the meeting decides how it goes.

入力Your analysed rateThe published schedule rate出力Where the two disagree, and why
モジュール

このプレイブックのモジュール

プラットフォーム 190 モジュール中 5

The market this case is written for

インド

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

積算とコストの他のケース

積算とコスト

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4ステップ12 分開く
積算とコスト

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3ステップ11 分開く