Registrar el proyecto bajo RERA y presentar el informe trimestral

Decide si el proyecto necesita registro, regístralo con una fecha de terminación que puedas defender, cotiza el área útil en todas partes, y lleva el avance físico y financiero en una forma de la que se pueda armar el informe trimestral sin sobresaltos.

5 pasos22 minDesarrollador / clienteGestora de proyectos / construcciónConsultoría de costos / QSPropietario / operador (FM)

Cómo funciona, paso a paso

5 pasos a lo largo de la plataforma - qué haces en cada uno y por qué importa.

1

Settle what counts as the project before you register it

Desarrollo inmobiliario

Set the scheme up with its land area, unit count and phasing, and check it against the registration threshold the state authority applies. Decide which phases are registered separately and which are one project, and record why.

Por que: Phasing decides the completion dates you will be held to, and it is easier to argue before registration than after. A phase registered inside a larger project inherits that project's date even when its own work is shorter, and nothing later undoes that.

EntradaThe scheme and its phasingThe state authority's thresholdResultadoWhether registration is requiredWhat is registered as one project
2

Register with a completion date the programme supports

Envíos a Autoridad

Lodge the registration with the state authority and keep the submission, the approvals it relied on and the certificate itself against the project. Record the declared completion date where the programme can be read against it.

Por que: The declared date is the most expensive sentence in the application, because delay past it is compensated to buyers on everything they have paid. A date taken from the sales plan rather than from the programme is a liability accepted at the moment of registration, in writing, in public.

EntradaSanctioned plans and approvalsThe programme behind the dateResultadoRegistration on file with its numberThe declared completion date
3

Measure carpet area and use it everywhere

Cubicación

Measure each unit to the definition the Act uses, the net usable floor area within the walls, and make that figure the one the agreement, the marketing material and the internal cost per unit all run on.

Por que: Two area bases in one organisation is not a documentation problem, it is a pricing problem. Cost per unit computed on one basis and price per unit quoted on the other is wrong by whatever the loading factor is, quietly, on every unit in the scheme.

EntradaUnit drawingsResultadoCarpet area per unitOne area basis everywhere
4

Keep physical and financial progress on the same spine

Avance

Record progress element by element, foundation, structure, external walls, internal finishes, services, external development, and keep the money committed and spent against those same elements rather than against a separate cost code.

Por que: The quarterly return asks for physical and financial progress side by side, and the two are read against each other by anyone looking for trouble. Recording them on one structure makes that comparison an output; recording them separately makes it a quarterly reconciliation exercise, done in a hurry, under a deadline.

EntradaWork done on siteMoney spent and receivedResultadoPhysical progress by elementFinancial progress against it
5

Produce the quarterly return, and read it as a warning

Informes

Generate the quarter's report from the progress records, with the status of each approval and the photographs for the period, file it with the authority, and compare the trend against the declared completion date.

Por que: Four returns show a trend the fourth quarter cannot hide. A developer who reads them as an early warning has a year to act on a slipping date; one who treats them as filing finds out at handover, when the only remaining options cost money to buyers.

EntradaThe quarter's progress and approvalsResultadoThe quarterly return, produced not assembledEarly warning on the declared date
Módulos

Módulos de este playbook

5 / 190 módulos de la plataforma

The market this case is written for

India

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.