سناریوها / بازرگانی و قراردادها
بازرگانی و قراردادها

تسویه یک دوره در حین کار و گرفتن امضا

مقادیر تکمیل‌شده و بی‌اختلاف یک دوره را همراه با تغییرات پذیرفته‌شده در آن قیمت‌گذاری کنید، صورت مقادیر را به‌صورت یک نسخه نام‌گذاری‌شده منجمد کنید، بیانیه تأییدشده را بنویسید، و امضای هر دو طرف را روی سابقه بگیرید.

5 مرحله18 دقیقهپیمانکار عمومیسازنده / کارفرمامشاوره هزینه / QSدفتر مدیریت پروژه / ساخت

چگونه کار می‌کند، گام به گام

5 گام در سراسر پلتفرم - کاری که در هر گام انجام می‌دهید و چرا اهمیت دارد.

1

Price only what is complete and undisputed

صورت مقادیر (BOQ)

Work the bill for the period: price the quantities that are complete, add the changes that were accepted inside it, and deliberately leave out anything still in dispute. Note what you left out and why.

چرا: The point of settling in process is to take the settled part off the table permanently, and one contested item is enough to keep a whole period open. Confirming ninety percent now and carrying ten percent forward is worth far more than agreeing everything eventually.

ورودیQuantities completed in the periodChanges accepted in the periodخروجیValue of the periodDisputed items left out
2

Take a named version at the close of the period

صورت مقادیر (BOQ)

Save a version of the bill at the moment the period closes and name it for the period, so the state you are about to have signed can be retrieved exactly as it was.

چرا: The bill carries on moving after this, and that is correct. What the named version buys you is the ability to answer, in a year, which numbers the signatures were given against - without asking anybody to remember, and without freezing a document the project still needs to work on.

ورودیThe period pricedخروجیNamed version of the billThe exact numbers, retrievable
3

Write the statement the two parties will sign

اسناد

File the period statement in the project documents: the span it covers, the confirmed quantities and value, the changes included, the items deliberately excluded, and the name of the bill version it was taken from.

چرا: A signature is only as good as the document under it. A statement that names its own span and its own exclusions cannot later be read as covering more or less than it did, which is the single most common way an in-process settlement stops holding.

ورودیThe named versionWhat was left outخروجیConfirmed period statement
4

Get both signatures against the same document

امضای الکترونیک

Open a signing session over the statement, name the signatory on each side, and let each of them sign. Every signature is recorded against that document reference with the time it was given.

چرا: Two signatures on one document is the whole mechanism. Two separate approvals in two separate systems is what produces the classic dispute where each side is certain it agreed to something slightly different, and neither can show what.

ورودیThe period statementBoth parties' signatoriesخروجیSigning session on the recordWho signed, and when
5

Keep the settled periods together for the final account

گزارش‌ها

Report the settled periods as a running set: what has been confirmed and signed to date, and what is still carried forward as open. Bring that set to the final account as your starting position.

چرا: A final account assembled from documents both parties already signed is a short meeting about the open items. A final account started from the whole bill invites a review of everything, including the parts that were settled fairly two years ago and that nobody now remembers agreeing.

ورودیSigned period statementsخروجیRunning settled positionWhat is still open
ماژول‌ها

ماژول‌های این سناریو

4 / 190 ماژول پلتفرم

The market this case is written for

چین

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GB 50500
  • GB 50854

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

بیشتر در بازرگانی و قراردادها

بازرگانی و قراردادها

Turn a change into a paid variation

Capture a scope change while it is fresh, price it as a contract variation on your agreed r…

3 مرحله11 دقیقهباز کردن
بازرگانی و قراردادها

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 مرحله11 دقیقهباز کردن
بازرگانی و قراردادها

Payment application and reconciliation

Value the work put in place this period against the contract, raise the application with th…

3 مرحله12 دقیقهباز کردن