תרחישים / מסחרי וחוזים
מסחרי וחוזים

סגירת תקופה בתהליך וקבלת חתימה עליה

תמחרו את הכמויות שהושלמו ואינן שנויות במחלוקת לתקופה אחת כולל השינויים שאושרו בה, הקפיאו את כתב הכמויות כגרסה בעלת שם, כתבו את ההצהרה המאושרת, וקבלו את חתימות שני הצדדים על הרישום.

5 שלבים18 דק׳קבלן ראשייזם / לקוחייעוץ עלויות / כמויותמשרד ניהול פרויקטים / בנייה

איך זה עובד, שלב אחר שלב

5 שלבים לאורך הפלטפורמה - מה עושים בכל שלב ולמה זה חשוב.

1

Price only what is complete and undisputed

כתב כמויות

Work the bill for the period: price the quantities that are complete, add the changes that were accepted inside it, and deliberately leave out anything still in dispute. Note what you left out and why.

למה: The point of settling in process is to take the settled part off the table permanently, and one contested item is enough to keep a whole period open. Confirming ninety percent now and carrying ten percent forward is worth far more than agreeing everything eventually.

נכנסQuantities completed in the periodChanges accepted in the periodיוצאValue of the periodDisputed items left out
2

Take a named version at the close of the period

כתב כמויות

Save a version of the bill at the moment the period closes and name it for the period, so the state you are about to have signed can be retrieved exactly as it was.

למה: The bill carries on moving after this, and that is correct. What the named version buys you is the ability to answer, in a year, which numbers the signatures were given against - without asking anybody to remember, and without freezing a document the project still needs to work on.

נכנסThe period pricedיוצאNamed version of the billThe exact numbers, retrievable
3

Write the statement the two parties will sign

מסמכים

File the period statement in the project documents: the span it covers, the confirmed quantities and value, the changes included, the items deliberately excluded, and the name of the bill version it was taken from.

למה: A signature is only as good as the document under it. A statement that names its own span and its own exclusions cannot later be read as covering more or less than it did, which is the single most common way an in-process settlement stops holding.

נכנסThe named versionWhat was left outיוצאConfirmed period statement
4

Get both signatures against the same document

חתימות אלקטרוניות

Open a signing session over the statement, name the signatory on each side, and let each of them sign. Every signature is recorded against that document reference with the time it was given.

למה: Two signatures on one document is the whole mechanism. Two separate approvals in two separate systems is what produces the classic dispute where each side is certain it agreed to something slightly different, and neither can show what.

נכנסThe period statementBoth parties' signatoriesיוצאSigning session on the recordWho signed, and when
5

Keep the settled periods together for the final account

דוחות

Report the settled periods as a running set: what has been confirmed and signed to date, and what is still carried forward as open. Bring that set to the final account as your starting position.

למה: A final account assembled from documents both parties already signed is a short meeting about the open items. A final account started from the whole bill invites a review of everything, including the parts that were settled fairly two years ago and that nobody now remembers agreeing.

נכנסSigned period statementsיוצאRunning settled positionWhat is still open
מודולים

המודולים בתרחיש הזה

4 מתוך 190 מודולי הפלטפורמה

The market this case is written for

סין

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GB 50500
  • GB 50854

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

עוד ב-מסחרי וחוזים

מסחרי וחוזים

Turn a change into a paid variation

Capture a scope change while it is fresh, price it as a contract variation on your agreed r…

3 שלבים11 דק׳פתיחה
מסחרי וחוזים

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 שלבים11 דק׳פתיחה
מסחרי וחוזים

Payment application and reconciliation

Value the work put in place this period against the contract, raise the application with th…

3 שלבים12 דק׳פתיחה