Fatturare uno stato di avanzamento a partire dal libretto delle misure

Misura il lavoro prima che venga coperto, fai controllare e firmare il rilievo in cantiere, trasforma le quantità aggiornate in uno stato di avanzamento rispetto al precedente, e avvia i termini di pagamento previsti dal contratto.

5 passaggi22 minImpresa generaleSubappaltatore specializzatoStudio di gestione progetti / cantieriSviluppatore / committente

Come funziona, passo dopo passo

5 passi attraverso la piattaforma - cosa fare a ciascuno e perché conta.

1

Record the measurement while the work can still be seen

Computo metrico

Measure the executed work item by item, on the standard method, and enter the up-to-date quantity beside the quantity carried from the previous bill. Take the measurements for excavation, reinforcement, concealed services and anything about to be covered before that happens, and note the date each was taken.

Schermata, passaggio 1: Record the measurement while the work can still be seen (Computo metrico, Fatturare uno stato di avanzamento a partire dal libretto delle misure)
Computo metrico: Record the measurement while the work can still be seen

Perché: Covered work cannot be re-measured, only argued about. A measurement written on the day, against a dated entry, is worth more than any later reconstruction, and it is what makes the difference between a quantity that is checked and a quantity that is conceded or refused.

In entrataWork done since the last billQuantities paid last timeIn uscitaUp-to-date quantity per itemHidden work recorded before covering
2

Bill only what has passed its inspection

Ispezioni

Check the measured quantities against the inspection records for the same work and hold back anything whose check is outstanding or failed, listing it so it can be picked up in the next bill rather than lost.

Schermata, passaggio 2: Bill only what has passed its inspection (Ispezioni, Fatturare uno stato di avanzamento a partire dal libretto delle misure)
Ispezioni: Bill only what has passed its inspection

Perché: Measured and accepted are different states, and a bill that treats them as one is returned by the engineer with everything in it queried, including the parts that were fine. Separating them costs one column and saves a cycle.

In entrataThe measured workThe inspection and test planIn uscitaWork that passed its checksWork held back from the bill
3

Turn the record into a bill that shows its own working

Finanza

Build the bill from the up-to-date quantities at contract rates, show what the previous bill paid, and carry the recoveries: the instalment of any mobilisation advance, the retention deducted this period, and anything paid earlier against materials brought to site and now built in.

Schermata, passaggio 3: Turn the record into a bill that shows its own working (Finanza, Fatturare uno stato di avanzamento a partire dal libretto delle misure)
Finanza: Turn the record into a bill that shows its own working

Perché: Recoveries against advances are the part most often missed, and missing them twice turns into a payment the department claws back from a later bill without warning. Putting them on the face of the bill keeps both sides looking at the same running position.

In entrataUp-to-date and previous quantitiesThe contract ratesIn uscitaThe running account billAdvances and retention recovered
4

Get the record signed by the people who checked it

Firme elettroniche

Route the measurement record and the bill for signature by the contractor's representative and the engineer who checked the work, and keep the signed version with the bill it belongs to.

Schermata, passaggio 4: Get the record signed by the people who checked it (Firme elettroniche, Fatturare uno stato di avanzamento a partire dal libretto delle misure)
Firme elettroniche: Get the record signed by the people who checked it

Perché: A signed measurement closes an item for good. An unsigned one stays open, travels forward through every later bill, and is reopened at final settlement when nobody remembers the work, which is the single most common reason an Indian final bill takes longer to agree than the job took to build.

In entrataThe bill and its measurementsIn uscitaA record signed by both sides
5

Start the clock the contract sets and watch it

Orologio di pagamento

Record the submission date and the period the contract allows for certification and for payment, and let the module show what is running and what is late.

Perché: Interest on delayed payment, where the contract provides for it, runs from a date that has to be proved. Tracking the date on every bill turns a claim you would rather not make into one you could make, which is usually enough for the conversation to go differently.

In entrataThe date the bill was submittedIn uscitaWhen the payment falls dueWhat has gone past its date
Moduli

Moduli di questo playbook

5 / 190 moduli della piattaforma

The market this case is written for

India

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Altro in Cantiere e campo

Cantiere e campo

Run the site day

Close the day out properly: record the diary, book the labour and plant hours, upload the p…