תרחישים / אתר ושטח
אתר ושטח

הפקת חשבון ביניים מתוך פנקס המדידות

מדדו את העבודה לפני שהיא מתכסה, קבלו את הרישום מאושר וחתום באתר, הפכו את הכמויות המעודכנות לחשבון ביניים מול קודמו, והפעילו את שעון התשלום שהחוזה קובע.

5 שלבים22 דק׳קבלן ראשיקבלן משנה מתמחהמשרד ניהול פרויקטים / בנייהיזם / לקוח

איך זה עובד, שלב אחר שלב

5 שלבים לאורך הפלטפורמה - מה עושים בכל שלב ולמה זה חשוב.

1

Record the measurement while the work can still be seen

כימות כמויות

Measure the executed work item by item, on the standard method, and enter the up-to-date quantity beside the quantity carried from the previous bill. Take the measurements for excavation, reinforcement, concealed services and anything about to be covered before that happens, and note the date each was taken.

למה: Covered work cannot be re-measured, only argued about. A measurement written on the day, against a dated entry, is worth more than any later reconstruction, and it is what makes the difference between a quantity that is checked and a quantity that is conceded or refused.

נכנסWork done since the last billQuantities paid last timeיוצאUp-to-date quantity per itemHidden work recorded before covering
2

Bill only what has passed its inspection

בדיקות

Check the measured quantities against the inspection records for the same work and hold back anything whose check is outstanding or failed, listing it so it can be picked up in the next bill rather than lost.

למה: Measured and accepted are different states, and a bill that treats them as one is returned by the engineer with everything in it queried, including the parts that were fine. Separating them costs one column and saves a cycle.

נכנסThe measured workThe inspection and test planיוצאWork that passed its checksWork held back from the bill
3

Turn the record into a bill that shows its own working

כספים

Build the bill from the up-to-date quantities at contract rates, show what the previous bill paid, and carry the recoveries: the instalment of any mobilisation advance, the retention deducted this period, and anything paid earlier against materials brought to site and now built in.

למה: Recoveries against advances are the part most often missed, and missing them twice turns into a payment the department claws back from a later bill without warning. Putting them on the face of the bill keeps both sides looking at the same running position.

נכנסUp-to-date and previous quantitiesThe contract ratesיוצאThe running account billAdvances and retention recovered
4

Get the record signed by the people who checked it

חתימות אלקטרוניות

Route the measurement record and the bill for signature by the contractor's representative and the engineer who checked the work, and keep the signed version with the bill it belongs to.

למה: A signed measurement closes an item for good. An unsigned one stays open, travels forward through every later bill, and is reopened at final settlement when nobody remembers the work, which is the single most common reason an Indian final bill takes longer to agree than the job took to build.

נכנסThe bill and its measurementsיוצאA record signed by both sides
5

Start the clock the contract sets and watch it

שעון תשלום

Record the submission date and the period the contract allows for certification and for payment, and let the module show what is running and what is late.

למה: Interest on delayed payment, where the contract provides for it, runs from a date that has to be proved. Tracking the date on every bill turns a claim you would rather not make into one you could make, which is usually enough for the conversation to go differently.

נכנסThe date the bill was submittedיוצאWhen the payment falls dueWhat has gone past its date
מודולים

המודולים בתרחיש הזה

5 מתוך 190 מודולי הפלטפורמה

The market this case is written for

הודו

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

עוד ב-אתר ושטח

אתר ושטח

Run the site day

Close the day out properly: record the diary, book the labour and plant hours, upload the p…

4 שלבים9 דק׳פתיחה
אתר ושטח

Answer an RFI

Turn a question from the working face into a tracked request, drive it to the party who own…

3 שלבים9 דק׳פתיחה