ケース / コマーシャルと契約
コマーシャルと契約

月次の支払申請を評価し認証する

契約のschedule of values(出来高配分表)に照らして、現場が実際に完了した内容から1期分の支払申請を評価し、保留金を差し引き、別の担当者に認証させ、認証済み金額を経理に反映させ、法定の支払期限を設定する。

7ステップ22 分総合建設会社専門工事業者コストコンサルティング会社 / 積算事務所プロジェクト / 施工管理会社

仕組みをステップごとに

プラットフォーム全体で7ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

Set the schedule of values off the bill

契約

Open the contract and build its schedule of values from the bill's own items, carrying the code, the description, the unit, the quantity and the rate rather than a summarised version of them.

スクリーンショット、ステップ 1: Set the schedule of values off the bill (契約, 月次の支払申請を評価し認証する)
契約: Set the schedule of values off the bill

理由: Every month for the next two years is valued against this list. A schedule that summarises twelve bill items into one line saves an hour now and costs an argument every month afterwards, because nobody can show which part of the line was completed.

入力Signed contractCoded bill of quantities出力Schedule of values
2

Get the work accepted before you value it

検査

Record the period's inspections and note what was accepted and what was held back. Work that failed its inspection does not go into this month's valuation, and the inspection record is why.

スクリーンショット、ステップ 2: Get the work accepted before you value it (検査, 月次の支払申請を評価し認証する)
検査: Get the work accepted before you value it

理由: Acceptance is what a Chinese payment cycle is built on, and it decides what is allowed into this month's valuation at all. Claiming for work that has not passed is the fastest way to have the whole application sent back rather than the one line queried, and it is the inspection record that settles the argument about which it was.

入力Work completed in the period出力Work signed off as acceptedWork held back
3

Record the period's progress against the work

進捗

Record what was completed in the period as progress against the work items, so the percentages exist before anyone opens the application rather than being decided while filling it in.

スクリーンショット、ステップ 3: Record the period's progress against the work (進捗, 月次の支払申請を評価し認証する)
進捗: Record the period's progress against the work

理由: A percentage typed straight into a payment application is an opinion; the same percentage recorded against observed work is a measurement. The difference is invisible in the month you do it and decisive in the month somebody disputes it.

入力What the site reportedAccepted work出力Percent complete per item
4

Value the period rather than type it

契約

Open the period's application and populate the percent complete from the progress you just recorded. Each line gets this period's quantity, this period's value and the running total; the header keeps gross, retention held, previously settled and net due recomputing as you go.

スクリーンショット、ステップ 4: Value the period rather than type it (契約, 月次の支払申請を評価し認証する)
契約: Value the period rather than type it

理由: Retention is the deduction the application holds for you, and holding it in the same document as the valuation is what stops the two drifting apart. Anything else your contract deducts - advance payment recovery, owner-supplied material, site utilities, the wage account carve-out - is yours to apply, and you should agree those figures with the other side in the same conversation as the valuation, not after it.

入力Schedule of valuesRecorded progress出力Valued applicationGross, retention, prior, net due
5

Let a second person certify it

契約

Submit the application, then have it certified by somebody other than the person who prepared it. Certification is a separate action under a separate permission, and rejection back to the preparer is available while it is still submitted.

理由: The supervising engineer's signature on a Chinese payment is the moment the amount stops being a request and becomes a certified figure, and the structural part of that ritual is that a different person performs it, on the record, at a known time. One person preparing and approving their own application is the control failure auditors look for first.

入力Submitted application出力Certified amountWho certified, and when
6

Carry the certified amount into finance

財務

The certified amount lands in finance as a payable without being re-entered. Raise the invoice against it with the tax rate on each line, and keep the fapiao you issue to the buyer tied to the same record.

スクリーンショット、ステップ 6: Carry the certified amount into finance (財務, 月次の支払申請を評価し認証する)
財務: Carry the certified amount into finance

理由: In China the buyer generally cannot process the money until the fapiao is in hand, so the tax invoicing chain is part of the payment cycle rather than an accounting afterthought. Re-keying the certified figure into a separate ledger is where a transposed digit becomes a payment nobody can reconcile at year end.

入力Certified amount出力Payable in financeVAT carried per line
7

Put the statutory clock on the payment

支払クロック

Open a clock over the application, but check first that a statutory one reaches you at all. The two Chinese regimes turn on who is owed: both cover a sum owed to a small or medium-sized supplier, giving thirty calendar days when the buyer is a government organ or a public institution and sixty when it is a large enterprise. Where both sides are large enterprises no statutory period applies and the contract's own dates govern, so read the clock off the contract rather than expecting one to be computed. For a progress claim the period runs from the date both parties confirmed the settlement amount, so enter that date as the application date rather than the date you posted the paperwork.

理由: Chasing late money starts with knowing exactly when it became late, and the regulation counts calendar days from a date that is easy to lose. Where your contract agrees a different period, put the agreed final date on the application instead: a public-sector clock cannot be extended past sixty days, and a private-sector one has to be reasonable rather than merely written down.

入力The payment applicationDate the amount was confirmed出力Final date for paymentA late payment that is visible
モジュール

このプレイブックのモジュール

プラットフォーム 190 モジュール中 5 個

The market this case is written for

中国

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GB 50500
  • GB 50854

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

コマーシャルと契約の他のケース

コマーシャルと契約

Turn a change into a paid variation

Capture a scope change while it is fresh, price it as a contract variation on your agreed r…

3ステップ11 分開く
コマーシャルと契約

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3ステップ11 分開く
コマーシャルと契約

Payment application and reconciliation

Value the work put in place this period against the contract, raise the application with th…

3ステップ12 分開く