케이스 / 상업 및 계약
상업 및 계약

Run the VOB/B payment clock

Register the contract, raise each Abschlagsrechnung against it, open a payment clock over the invoice and let the module count the days paragraph 16 VOB/B gives the client, so an overdue payment is a dated record rather than a feeling.

7단계12 분종합건설사전문건설사원가 컨설팅 / 적산 업체

작동 방식, 단계별로

플랫폼 전반에 걸친 7단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Register the contract

계약

Create the contract for the job with its type, its priced schedule of values and its retention percentage, so the sums you will invoice against are on record before the first Abschlagsrechnung leaves the office.

이유: A payment deadline only bites when both sides agree what was ordered. A contract carrying the priced schedule turns a challenged invoice into an arithmetic question instead of an argument about scope.

입력Signed BauvertragPriced schedule of values결과Registered contractRetention terms on record
2

Raise the Abschlagsrechnung

계약

On the progress claims tab, value the work done in the period against the schedule of values and raise it as the interim invoice, with the period it covers, the retention deducted and the net sum you are asking for.

이유: The clock is counted against this document, so it has to state the work, the period and the sum before it goes out. A statement the client can check is what sets the period running; one they cannot check comes back as a query, and a query costs you the days it takes to answer.

입력Registered contractWork measured this period결과AbschlagsrechnungNet sum applied for
3

Open a clock over the invoice

Payment Clock

Open a clock and pick the German regime for interim payments under paragraph 16 VOB/B. Enter the date the client received the statement as the application date, then the sum applied for and the currency.

이유: The period runs from receipt, not from the day you printed the invoice. Entering the posting date moves every deadline in your own favour and leaves you holding a date you cannot prove on the one occasion it has to be proved.

입력AbschlagsrechnungDate the client received itSum applied for결과Open payment clockStatutory regime on record
4

Read the dates the module computed

Payment Clock

Open the clock detail. The sum payable leads, the due date and the final date for payment sit under it, and the derivation spells out each date against the provision it came from. On a VOB/B clock the two notice rows stay empty.

이유: They stay empty because VOB/B sets no payment notice and no pay-less notice, so there is nothing to serve and nothing to chase, only the money and the date it stops being on time. A derivation you can read out loud is what turns a phone call about a late payment into a quotable line.

입력Open payment clockChosen regime결과Due dateFinal date for paymentDerivation you can quote
5

Watch the clock count each deadline

Payment Clock

Come back to the list as the month runs. It says how many clocks the project carries and how many are past their final date, badges the overdue ones, and fills the breach register underneath. Open an overdue one and the findings name the sum outstanding, the days it has run past the final date and the rate the statutory interest runs at.

이유: Reading a clock is what writes its register, so a quiet register on a project nobody opens is telling you about the reading and not about the payments. The interest is due as of right and starts running the moment the date passes, without having to be claimed separately, so the only thing standing between you and it is a record that says when.

입력Open clocks on the projectFinal dates for payment결과Overdue invoices flaggedBreach register rows
6

See what the delay is costing you

재무

Open the receivable side of Finance: the invoice raised from the certified claim, its due date, and the total the project is carrying overdue. It sits in the same cash picture as the money you have already spent doing the work it pays for.

이유: This is what an untracked payment deadline actually is - your own working capital lent to the client at no charge, for as long as nobody counts it. Seeing the overdue total beside the budget turns a vague chase into a decision about which invoice gets escalated first.

입력Certified progress claimOverdue clocks결과Receivable on the booksOverdue total in the cash picture
7

Escalate with the record assembled

문서

Write the Nachfrist letter and file it with the invoice and the clock reading it quotes: the date of receipt, the final date for payment, the days late and the sum outstanding. The module runs no grace period of its own, so that date is one you set and mind by hand.

이유: By the time a payment is worth escalating, the facts are months old and spread across three inboxes. A letter whose every date came off a record you kept as you went is the one that moves the client's accounts department, and it is the same file anyone advising you later asks for first.

입력Clock readingAbschlagsrechnung결과Nachfrist letter on fileEscalation record
모듈

이 플레이북의 모듈

플랫폼 184개 모듈 중 4

상업 및 계약 카테고리의 더 보기

상업 및 계약

변경사항을 유상 변경계약으로 전환

신선할 때 범위 변경을 기록하고, 합의된 단가로 계약 변경계약으로 산정한 뒤 다음 기성청구에 포함시켜, 추가 작업을 조용히 흡수하지 않고 회수합니다.

3단계11 분열기
상업 및 계약

협력업체 패키지 운영

협력업체에 공종 패키지를 발주하고, 기성 내역서와 유보금 조건을 포함한 하도급 계약으로 전환한 뒤, 실제 완료된 작업에 대해 기성 청구별로 지급합니다.

3단계11 분열기
상업 및 계약

기성 청구 및 대사

계약서 대비 해당 기간 시공된 물량을 평가하고, 근거 자료와 함께 기성 청구를 제출하며, 승인된 금액을 실제 입금액과 대조 확인한다.

3단계12 분열기