Een COBie-gebouwexport opleveren

Zet het assetregister om in het COBie UK 2.4-werkboek dat een FM-systeem daadwerkelijk kan importeren: vul de velden waarop de bladen zijn gebouwd, herstel wat de export zou blootleggen, produceer het werkboek en lever het op met het opleverdossier.

4 stappen9 minHoofdaannemerEigenaar / beheerder (FM)BIM- / digitaliseringsadvies

Zo werkt het, stap voor stap

4 stappen door het platform - wat je bij elke stap doet en waarom het ertoe doet.

1

Complete the register the workbook is built from

Assets

Work through the tracked assets and fill the fields COBie reads: make, model and serial, the operational status and warranty date, the storey the item sits on and the parent system it belongs to.

Schermafbeelding, stap 1: Complete the register the workbook is built from (Assets, Een COBie-gebouwexport opleveren)
Assets: Complete the register the workbook is built from

Waarom: The workbook is a projection of the register, not a document you write separately, so the sheets are only as complete as the rows behind them. A blank storey does not leave one empty cell, it removes a whole Floor row the receiving system was expecting to hang the asset on.

InvoerTracked assetsCanonical model dataResultaatComplete asset registerAssets under a parent system
2

Check the gaps the export will expose

Assets

Before you export, read the register the way the workbook will: search and filter down to the assets with no serial, no warranty date and no parent system, and either fix them or put them back to whoever installed the plant.

Waarom: The export falls back to n/a rather than failing, so a workbook full of holes still downloads cleanly and still looks finished. Nobody finds out until the operator tries to raise a work order against a pump with no serial and no system, by which time the fitters have long gone.

InvoerComplete asset registerOperator data requirementsResultaatList of thin recordsFixes back to the delivery team
3

Build the COBie 2.4 workbook

Assets

Export the register as a COBie UK 2.4 workbook. It arrives as one spreadsheet with seven sheets, Contact, Facility, Floor, Space, Type, Component and System, each projected straight from the canonical model and the asset data sitting on it.

Waarom: A workbook generated from the model matches the building; a workbook typed into a template matches whatever the typist had in front of them that week. Exporting per model as each one is signed off also keeps the register current, instead of leaving the whole job to the fortnight before handover.

InvoerChecked asset registerModel to exportResultaatCOBie 2.4 workbookSeven populated sheets
4

Issue it to the operator

Afsluiting

Bind the workbook into the close-out package alongside the as-built drawings, the O and M manuals and the warranties, and issue the lot as one structured set with its manifest.

Schermafbeelding, stap 4: Issue it to the operator (Afsluiting, Een COBie-gebouwexport opleveren)
Afsluiting: Issue it to the operator

Waarom: A COBie file arriving on its own gets loaded by nobody, because the FM team cannot tell which state of the building it describes. Wrapped in the close-out package, dated and listed on the manifest, it is a deliverable the operator can accept, import and be held to.

InvoerCOBie 2.4 workbookClose-out checklistResultaatIssued handover packageOperator acceptance
Modules

Modules in dit playbook

2 / 190 platformmodules

The market this case is written for

Verenigd Koninkrijk

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • RICS NRM 1/2
  • JCT
  • CIS

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Meer in Oplevering & levenscyclus

Oplevering & levenscyclus

Hand over and close out

Finish the job cleanly: work the punch list to zero, confirm every inspection passed and no…

5 stappen14 minOpenen
Oplevering & levenscyclus

As-built and O and M handover

Pull the as-built record together, prove the quality file has no gaps, then issue an operat…