Gjør aktivaregisteret om til COBie UK 2.4-arbeidsboken et FM-system faktisk kan importere: fyll ut feltene arkene bygges fra, rett det eksporten ville avdekket, produser arbeidsboken og utsted den med sluttdokumentasjonen.

4 trinn9 minHovedentreprenørEier / driftsansvarlig (FM)BIM- / digital rådgivning

Slik fungerer det, steg for steg

4 trinn gjennom plattformen - hva du gjør i hvert og hvorfor det betyr noe.

1

Complete the register the workbook is built from

Assets

Work through the tracked assets and fill the fields COBie reads: make, model and serial, the operational status and warranty date, the storey the item sits on and the parent system it belongs to.

Skjermbilde, trinn 1: Complete the register the workbook is built from (Assets, Overlever en COBie-eksport for drift)
Assets: Complete the register the workbook is built from

Hvorfor: The workbook is a projection of the register, not a document you write separately, so the sheets are only as complete as the rows behind them. A blank storey does not leave one empty cell, it removes a whole Floor row the receiving system was expecting to hang the asset on.

InndataTracked assetsCanonical model dataResultatComplete asset registerAssets under a parent system
2

Check the gaps the export will expose

Assets

Before you export, read the register the way the workbook will: search and filter down to the assets with no serial, no warranty date and no parent system, and either fix them or put them back to whoever installed the plant.

Hvorfor: The export falls back to n/a rather than failing, so a workbook full of holes still downloads cleanly and still looks finished. Nobody finds out until the operator tries to raise a work order against a pump with no serial and no system, by which time the fitters have long gone.

InndataComplete asset registerOperator data requirementsResultatList of thin recordsFixes back to the delivery team
3

Build the COBie 2.4 workbook

Assets

Export the register as a COBie UK 2.4 workbook. It arrives as one spreadsheet with seven sheets, Contact, Facility, Floor, Space, Type, Component and System, each projected straight from the canonical model and the asset data sitting on it.

Hvorfor: A workbook generated from the model matches the building; a workbook typed into a template matches whatever the typist had in front of them that week. Exporting per model as each one is signed off also keeps the register current, instead of leaving the whole job to the fortnight before handover.

InndataChecked asset registerModel to exportResultatCOBie 2.4 workbookSeven populated sheets
4

Issue it to the operator

Avslutning

Bind the workbook into the close-out package alongside the as-built drawings, the O and M manuals and the warranties, and issue the lot as one structured set with its manifest.

Skjermbilde, trinn 4: Issue it to the operator (Avslutning, Overlever en COBie-eksport for drift)
Avslutning: Issue it to the operator

Hvorfor: A COBie file arriving on its own gets loaded by nobody, because the FM team cannot tell which state of the building it describes. Wrapped in the close-out package, dated and listed on the manifest, it is a deliverable the operator can accept, import and be held to.

InndataCOBie 2.4 workbookClose-out checklistResultatIssued handover packageOperator acceptance
Moduler

Moduler i denne playbooken

2 / 190 plattformmoduler

The market this case is written for

Storbritannia

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • RICS NRM 1/2
  • JCT
  • CIS

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Mer innen Overlevering og livssyklus

Overlevering og livssyklus

Hand over and close out

Finish the job cleanly: work the punch list to zero, confirm every inspection passed and no…

5 trinn14 minÅpne
Overlevering og livssyklus

As-built and O and M handover

Pull the as-built record together, prove the quality file has no gaps, then issue an operat…

3 trinn12 minÅpne