ケース / 引き渡しとライフサイクル
引き渡しとライフサイクル

COBie施設データを引き渡す

資産台帳をFMシステムが実際に取り込めるCOBie UK 2.4形式のワークブックに変換する。各シートの元になる項目を埋め、出力時に露呈する不備を修正し、ワークブックを作成して竣工書類一式とともに発行する。

4ステップ9 分総合建設会社オーナー / 運営者 (FM)BIM / デジタルコンサルティング会社

仕組みをステップごとに

プラットフォーム全体で4ステップ - 各ステップで何をするか、そしてなぜ重要か。

1

Complete the register the workbook is built from

Assets

Work through the tracked assets and fill the fields COBie reads: make, model and serial, the operational status and warranty date, the storey the item sits on and the parent system it belongs to.

スクリーンショット、ステップ 1: Complete the register the workbook is built from (Assets, COBie施設データを引き渡す)
Assets: Complete the register the workbook is built from

理由: The workbook is a projection of the register, not a document you write separately, so the sheets are only as complete as the rows behind them. A blank storey does not leave one empty cell, it removes a whole Floor row the receiving system was expecting to hang the asset on.

入力Tracked assetsCanonical model data出力Complete asset registerAssets under a parent system
2

Check the gaps the export will expose

Assets

Before you export, read the register the way the workbook will: search and filter down to the assets with no serial, no warranty date and no parent system, and either fix them or put them back to whoever installed the plant.

理由: The export falls back to n/a rather than failing, so a workbook full of holes still downloads cleanly and still looks finished. Nobody finds out until the operator tries to raise a work order against a pump with no serial and no system, by which time the fitters have long gone.

入力Complete asset registerOperator data requirements出力List of thin recordsFixes back to the delivery team
3

Build the COBie 2.4 workbook

Assets

Export the register as a COBie UK 2.4 workbook. It arrives as one spreadsheet with seven sheets, Contact, Facility, Floor, Space, Type, Component and System, each projected straight from the canonical model and the asset data sitting on it.

理由: A workbook generated from the model matches the building; a workbook typed into a template matches whatever the typist had in front of them that week. Exporting per model as each one is signed off also keeps the register current, instead of leaving the whole job to the fortnight before handover.

入力Checked asset registerModel to export出力COBie 2.4 workbookSeven populated sheets
4

Issue it to the operator

完了

Bind the workbook into the close-out package alongside the as-built drawings, the O and M manuals and the warranties, and issue the lot as one structured set with its manifest.

スクリーンショット、ステップ 4: Issue it to the operator (完了, COBie施設データを引き渡す)
完了: Issue it to the operator

理由: A COBie file arriving on its own gets loaded by nobody, because the FM team cannot tell which state of the building it describes. Wrapped in the close-out package, dated and listed on the manifest, it is a deliverable the operator can accept, import and be held to.

入力COBie 2.4 workbookClose-out checklist出力Issued handover packageOperator acceptance
モジュール

このプレイブックのモジュール

プラットフォーム 190 モジュール中 2 個

The market this case is written for

イギリス

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • RICS NRM 1/2
  • JCT
  • CIS

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

引き渡しとライフサイクルの他のケース

引き渡しとライフサイクル

Hand over and close out

Finish the job cleanly: work the punch list to zero, confirm every inspection passed and no…

5ステップ14 分開く
引き渡しとライフサイクル

As-built and O and M handover

Pull the as-built record together, prove the quality file has no gaps, then issue an operat…

3ステップ12 分開く
引き渡しとライフサイクル

Run a handover acceptance inspection

Walk the finished works with the client, record what passes and what does not against the a…

3ステップ11 分開く