Mål opp i metrisk og kjøp i imperial

Mål tegningene i metrisk, hold mengden metrisk overalt der den lagres og eksporteres, og bær det imperiale produktnavnet trelasthandelen faktisk vil selge deg, på samme rad, uten å la det ene skrive over det andre.

5 trinn15 minHovedentreprenørSpesialisert underentreprenørKostnadsrådgivning / kalkulasjon

Slik fungerer det, steg for steg

5 trinn gjennom plattformen - hva du gjør i hvert og hvorfor det betyr noe.

1

Measure off the drawings in metric

PDF-målinger

Set the scale from a known dimension on the sheet and measure lengths, areas and volumes in metric, taking each value from the drawing itself rather than from a figure somebody has already converted.

Hvorfor: The drawings are metric, the model is metric and the specification is metric. Measuring in one system and converting at every step adds a rounding at every step, and roundings compound worst in the quantities that matter most, which are always the biggest ones.

InndataDrawing set at a known scaleScope to be measuredResultatMetric lengths, areas and volumesMeasurements tied to the sheet
2

Store the quantity metric and leave it that way

Mengdeberegning

Keep the measured quantity in its metric unit as the stored value, and treat an imperial reading of it as a view of that number rather than as a replacement for it.

Skjermbilde, trinn 2: Store the quantity metric and leave it that way (Mengdeberegning, Mål opp i metrisk og kjøp i imperial)
Mengdeberegning: Store the quantity metric and leave it that way

Hvorfor: There is only a right answer for one stored number. Storing a converted figure and converting it back is how a quantity acquires a rounding it never had, and nobody catches it, because both versions look entirely reasonable.

InndataMeasurements from the drawingsResultatMetric quantities stored onceA display that does not edit
3

Carry the product name the yard will sell you

Mengdefortegnelse

Write the nominal product name on the item beside the metric quantity: a 2x4 with its dressed size of 38 by 89 mm stated from the standard, a 4x8 sheet with 1219.2 by 2438.4 mm stated and 1220 by 2440 as the conventional designation. Take each stated size from the standard or the arithmetic that produced it, never from the name.

Skjermbilde, trinn 3: Carry the product name the yard will sell you (Mengdefortegnelse, Mål opp i metrisk og kjøp i imperial)
Mengdefortegnelse: Carry the product name the yard will sell you

Hvorfor: The quantity is what you measured and the name is what you order, and they are two different facts about the same row. A bill carrying only the metric size has to be translated at the counter by whoever answers the phone, and a bill carrying only the name cannot be checked back against the drawings at all.

InndataMetric quantitiesProduct names as they are boughtResultatRows carrying both factsDressed sizes stated, not derived
4

Check that nothing was converted twice

Validering

Validate the bill before it goes out, looking for the two failures this scope produces: a quantity whose unit no longer matches the way it was measured, and a stated size that has been recomputed from the nominal name instead of taken from the standard.

Skjermbilde, trinn 4: Check that nothing was converted twice (Validering, Mål opp i metrisk og kjøp i imperial)
Validering: Check that nothing was converted twice

Hvorfor: Both failures produce numbers that look right, which is exactly why a read-through does not catch them. A member sized at 50.8 mm where the standard says 38 mm passes every eye in the room and is wrong by a third, and it is wrong in the direction that costs money on site rather than in the estimate.

InndataThe priced billNominal names and stated sizesResultatUnit mismatches caughtSizes verified against the standard
5

Issue each reader the units they need

Rapporter

Export the bill with the metric quantities intact for the client and the consultant, and produce the material order carrying the nominal names for the supplier, both from the same rows.

Skjermbilde, trinn 5: Issue each reader the units they need (Rapporter, Mål opp i metrisk og kjøp i imperial)
Rapporter: Issue each reader the units they need

Hvorfor: Two readers need two different things from one set of rows, and neither should be handed a converted version of the other's. Exports staying metric is also what keeps the bill comparable against the drawings it was measured from, which is the only check anybody can run on it later.

InndataBill rows carrying both factsResultatMetric bill for the clientMaterial order in nominal sizes
Moduler

Moduler i denne playbooken

5 / 190 plattformmoduler

The market this case is written for

Canada

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CCDC
  • CSA
  • NBC 2020

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Mer innen Kalkyle og kostnader

Kalkyle og kostnader

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 trinn12 minÅpne
Kalkyle og kostnader

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 trinn11 minÅpne