Produce an NRM1 order of cost estimate

فلور ایریا اور عمارت کی قسم کو اس کے نیچے ایک ایلیمنٹل تقسیم کے ساتھ order of cost estimate میں تبدیل کریں، رسک الاؤنسز کو اپنی الگ رقم کے طور پر رکھیں، اس تاریخ پر ری بیس کریں جس دن کام تعمیر ہوتا ہے، اور جب تک آپ کو یاد ہو بنیاد لکھ لیں۔

5 مراحل14 منٹکاسٹ کنسلٹنسی / QS فرمڈیولپر / کلائنٹجنرل کنٹریکٹر

یہ کیسے کام کرتا ہے، قدم بہ قدم

5 قدم پوری پلیٹ فارم میں - ہر قدم پر کیا کرنا ہے اور یہ کیوں اہم ہے۔

1

Size the building before you price it

تصوراتی اسٹیمیٹ

Enter the gross internal floor area, the building type, the quality level and the region. What comes back is a total with an elemental breakdown across substructure, superstructure, finishes, services and external works, and an accuracy band around it rather than one confident figure.

کیوں: NRM 1 calls the earliest estimate a floor area method estimate for a reason: the area and the building type are the only two things anybody knows properly at this point. Publishing the accuracy band beside the total is what stops a Stage 2 figure being read as a tender sum, which is how a project acquires a budget nobody ever agreed to.

اندر جاتا ہےClient briefGross internal floor areaباہر آتا ہےOrder of cost estimateAccuracy band on the total
2

Carry the risk allowances as their own money

الاؤنسز اور کنٹینجنسی

Open the register and put design development risk, construction risk and employer change risk in as separate allowances rather than folding one percentage into the rate. As the design firms up, draw against them and read what is left.

کیوں: NRM 1 treats risk as a cost plan item with a name and an owner, not as a cushion buried in a rate. Held separately it can be reported, spent and released deliberately. Buried in the rate it is invisible, and the first time anybody goes looking for it is the day it has already gone.

اندر جاتا ہےOrder of cost estimateRisk register entriesباہر آتا ہےRisk allowances heldContingency drawdown record
3

Rebase it to the date the money is spent

قیمت اشاریہ

Load a tender price index series of the kind the cost information services publish, set the base period the rates came from and the target period the works will be tendered and built in, and let the adjustment run. A location factor moves a national rate to the region the site is actually in.

کیوں: A rate taken from a price book or from a finished job is priced at the date that job was tendered, and repeating it unchanged for work three years out is a forecast nobody made on purpose. Rebasing turns the gap into a line the client can see, argue with and sign off, which is the whole point of showing inflation rather than absorbing it.

اندر جاتا ہےHistoric tender ratesTender price index seriesباہر آتا ہےRebased estimate totalTime and location adjustment
4

Write the basis down while you still remember it

اسٹیمیٹ کی بنیاد

Generate the basis of estimate and work through the inclusions, exclusions and assumptions it proposes. Say which drawings and which revision the estimate was built from, what sits outside it, and what the client has to decide before the next stage can firm it up.

کیوں: This estimate will be set against a tender in eighteen months by somebody who was not in the room. Without the basis that comparison is between two numbers and somebody is at fault; with it the comparison is between two scopes, and the difference stops being an accusation and becomes a list.

اندر جاتا ہےRebased estimate totalAssumptions and exclusionsباہر آتا ہےBasis of estimate documentExclusions on record
5

Issue it as a cost report the client can read

رپورٹس

Produce the cost report for the stage: the elemental summary, the risk allowances, the inflation line and the accuracy band, in one document that is dated and versioned so the next stage has something firm to be measured against.

کیوں: Reporting cost against the RIBA stage it belongs to is what lets a client watch cost move as design moves, instead of watching one number get replaced by another with no account of why. A stage report that carries its own basis is also the only version of the estimate anybody can safely quote six months later.

اندر جاتا ہےBasis of estimate documentElemental cost breakdownباہر آتا ہےStage cost reportBaseline for the next stage
ماڈیولز

اس سیناریو کے ماڈیولز

5 / 190 پلیٹ فارم ماڈیولز

The market this case is written for

سلطنت متحدہ

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • RICS NRM 1/2
  • JCT
  • CIS

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

تخمینہ سازی اور لاگت میں مزید

تخمینہ سازی اور لاگت

Check an estimate before you send it

Put a priced bill through the validation rules, clear every warning and error, then export…

3 مراحل8 منٹکھولیں
تخمینہ سازی اور لاگت

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 مراحل12 منٹکھولیں
تخمینہ سازی اور لاگت

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 مراحل11 منٹکھولیں