Produce an NRM1 order of cost estimate

Omdan et etageareal og en bygningstype til et order of cost estimate med en elementopdeling under det, hold risikotillæggene som deres egne penge, rebasér til den dato, arbejdet bygges, og skriv grundlaget ned, mens du stadig husker det.

5 trin14 minOmkostnings- / mængderådgivningUdvikler / bygherreHovedentreprenør

Sådan fungerer det, trin for trin

5 trin gennem platformen - hvad du gør i hvert, og hvorfor det betyder noget.

1

Size the building before you price it

Konceptuelt overslag

Enter the gross internal floor area, the building type, the quality level and the region. What comes back is a total with an elemental breakdown across substructure, superstructure, finishes, services and external works, and an accuracy band around it rather than one confident figure.

Hvorfor: NRM 1 calls the earliest estimate a floor area method estimate for a reason: the area and the building type are the only two things anybody knows properly at this point. Publishing the accuracy band beside the total is what stops a Stage 2 figure being read as a tender sum, which is how a project acquires a budget nobody ever agreed to.

InputClient briefGross internal floor areaResultatOrder of cost estimateAccuracy band on the total
2

Carry the risk allowances as their own money

Afsætninger og reserver

Open the register and put design development risk, construction risk and employer change risk in as separate allowances rather than folding one percentage into the rate. As the design firms up, draw against them and read what is left.

Hvorfor: NRM 1 treats risk as a cost plan item with a name and an owner, not as a cushion buried in a rate. Held separately it can be reported, spent and released deliberately. Buried in the rate it is invisible, and the first time anybody goes looking for it is the day it has already gone.

InputOrder of cost estimateRisk register entriesResultatRisk allowances heldContingency drawdown record
3

Rebase it to the date the money is spent

Prisindeks

Load a tender price index series of the kind the cost information services publish, set the base period the rates came from and the target period the works will be tendered and built in, and let the adjustment run. A location factor moves a national rate to the region the site is actually in.

Hvorfor: A rate taken from a price book or from a finished job is priced at the date that job was tendered, and repeating it unchanged for work three years out is a forecast nobody made on purpose. Rebasing turns the gap into a line the client can see, argue with and sign off, which is the whole point of showing inflation rather than absorbing it.

InputHistoric tender ratesTender price index seriesResultatRebased estimate totalTime and location adjustment
4

Write the basis down while you still remember it

Overslagsgrundlag

Generate the basis of estimate and work through the inclusions, exclusions and assumptions it proposes. Say which drawings and which revision the estimate was built from, what sits outside it, and what the client has to decide before the next stage can firm it up.

Hvorfor: This estimate will be set against a tender in eighteen months by somebody who was not in the room. Without the basis that comparison is between two numbers and somebody is at fault; with it the comparison is between two scopes, and the difference stops being an accusation and becomes a list.

InputRebased estimate totalAssumptions and exclusionsResultatBasis of estimate documentExclusions on record
5

Issue it as a cost report the client can read

Rapporter

Produce the cost report for the stage: the elemental summary, the risk allowances, the inflation line and the accuracy band, in one document that is dated and versioned so the next stage has something firm to be measured against.

Hvorfor: Reporting cost against the RIBA stage it belongs to is what lets a client watch cost move as design moves, instead of watching one number get replaced by another with no account of why. A stage report that carries its own basis is also the only version of the estimate anybody can safely quote six months later.

InputBasis of estimate documentElemental cost breakdownResultatStage cost reportBaseline for the next stage
Moduler

Moduler i denne playbook

5 / 190 platformmoduler

The market this case is written for

Storbritannien

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • RICS NRM 1/2
  • JCT
  • CIS

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Mere inden for Kalkulation og omkostninger

Kalkulation og omkostninger

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 trin12 minÅbn
Kalkulation og omkostninger

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 trin11 minÅbn