Decida qué planos son regulated designs, verifique que cada practitioner esté registrado para la clase de trabajo que declara, reúna los construction issued designs y sus compliance declarations, preséntelos antes de que empiece la obra, detecte el cambio de obra que crea un nuevo regulated design, y cierre con la declaration de la que depende el occupation certificate.
7 pasos a lo largo de la plataforma - qué hacer en cada uno y por qué importa.
Work through the design register and mark which documents are regulated designs, the ones covering building elements the regulation names, such as fire safety systems, waterproofing, and the internal and external load bearing components, together with the performance solutions that support them. Name the practitioner who will declare each one.
Por que: The list decides the whole workflow, and it is drawn once at the start when it is cheap. A document identified as regulated three months into construction needs a declaration from a practitioner who may not have been engaged on that basis, at a price nobody budgeted, for work that is already built.
Record each practitioner's registration, the classes of design work it authorises and its expiry, along with the professional indemnity cover the scheme requires. Check the registration against the class of the design they are being asked to declare, not simply that they hold one.
Por que: A declaration made by someone whose registration does not authorise that class of work is not a declaration, and the failure is invisible until it is checked. Registration also expires mid project, which turns a valid declaration into a problem on a date nobody was watching.
Run the regulated designs through the submittal register so each one arrives with its revision, its date and the practitioner who prepared it, and so a design still outstanding is visible as an outstanding item rather than as an absence nobody noticed.
Por que: What is lodged has to be the version that will actually be built from, and a register that tracks revisions is the only thing that keeps those two the same document. A declaration attached to a superseded revision is worse than none, because it reads as compliance while describing a building nobody is constructing.
Collect a design compliance declaration signed by the registered design practitioner for each regulated design. Where a principal design practitioner has been appointed, they make the principal compliance declaration that the designs are covered and the declarations were made by practitioners authorised to make them.
Por que: The declaration is a personal statement by a named practitioner and it carries personal consequences, which is why it is chased rather than given. Collecting them as they are signed, against a list drawn at the start, is the difference between a routine administrative task and a search for six people at the end of a job.
Lodge the construction issued regulated designs and their declarations through the state planning portal before building work commences, and keep the lodgement receipts against the submission record so the date can be shown rather than remembered.
Por que: The obligation is tied to the start of the work rather than to a milestone anybody celebrates, so the deadline arrives while the site is mobilising and everyone is busy with something else. Lodging late is not curable by lodging afterwards, because the record shows when the work started.
Route every change that touches a regulated design back through the same loop, a varied regulated design, a fresh declaration from a registered practitioner and a lodgement, before the varied work is built. Keep the link between the change and the design it varied.
Por que: This is the step the regime is most often failed on, and it fails quietly. Work built to a marked up sketch is work with no declared design behind it, and nothing on site looks wrong; the gap appears at the end, when the building is finished and the only remedies are expensive.
Check the close-out register holds every regulated design, every declaration and every lodgement receipt, then have the registered building practitioner make the building compliance declaration that the work complies with the designs as declared.
Por que: The compliance declarations have to be in place before an application for an occupation certificate can be made, which means a single missing declaration holds up handover for a finished building. Every day of that is carrying cost on a project that has stopped earning.
7 / 190 módulos de la plataforma
Todo en este caso sigue la forma en que la obra se mide, se valora y se paga en este mercado. Los documentos, el desglose de costes y las reglas de pago son los que se usan allí, no una versión genérica.
Normas que sigue
No tienes que configurar nada de eso a mano. La primera vez que abres la plataforma te pregunta en qué mercado trabajas. Elige este y ajusta el idioma de la interfaz, carga la base de costes correspondiente, registra la clasificación de costes y añade un proyecto de ejemplo que puedes abrir enseguida.
Las comprobaciones de este mercado también vienen con la plataforma. Actívalas una vez y un presupuesto al que le falte algo que el mercado espera queda señalado mientras trabajas en él, no después de presentar la oferta.
Inspeccione la obra frente a sus criterios de aceptación, registre una no conformidad en cua…
Informa a la cuadrilla de los peligros que realmente conlleva este turno, registra quién est…
Presenta al proyectista el producto que piensas comprar con su documentación técnica, consig…