Submeta regulated designs ao abrigo do Design and Building Practitioners Act

Decida que desenhos são regulated designs, verifique se cada practitioner está registado para a classe de trabalho que declara, recolha os construction issued designs e as suas declarações de conformidade, submeta-os antes de a obra começar, apanhe a alteração em obra que cria um novo regulated design e feche com a declaração de que depende o occupation certificate.

7 etapas18 minEmpreiteiro geralGabinete de projeto / engenhariaPromotor / clienteGabinete de gestão de projetos / obras

Como funciona, passo a passo

7 passos ao longo da plataforma - o que fazer em cada um e por que importa.

1

Decide which designs are regulated designs

Revisão da Autoridade

Work through the design register and mark which documents are regulated designs, the ones covering building elements the regulation names, such as fire safety systems, waterproofing, and the internal and external load bearing components, together with the performance solutions that support them. Name the practitioner who will declare each one.

Por quê: The list decides the whole workflow, and it is drawn once at the start when it is cheap. A document identified as regulated three months into construction needs a declaration from a practitioner who may not have been engaged on that basis, at a price nobody budgeted, for work that is already built.

EntradaDesign documents for the jobBuilding class and work typeResultadoList of regulated designsPractitioner responsible for each
2

Check the registration covers the class being declared

Habilitações

Record each practitioner's registration, the classes of design work it authorises and its expiry, along with the professional indemnity cover the scheme requires. Check the registration against the class of the design they are being asked to declare, not simply that they hold one.

Por quê: A declaration made by someone whose registration does not authorise that class of work is not a declaration, and the failure is invisible until it is checked. Registration also expires mid project, which turns a valid declaration into a problem on a date nobody was watching.

EntradaDesign team engagedClasses of design workResultadoRegistration checked per classExpiry and insurance dates watched
3

Collect the construction issued designs and their revisions

Submissões

Run the regulated designs through the submittal register so each one arrives with its revision, its date and the practitioner who prepared it, and so a design still outstanding is visible as an outstanding item rather than as an absence nobody noticed.

Por quê: What is lodged has to be the version that will actually be built from, and a register that tracks revisions is the only thing that keeps those two the same document. A declaration attached to a superseded revision is worse than none, because it reads as compliance while describing a building nobody is constructing.

EntradaConstruction issued drawingsList of regulated designsResultadoDesigns collected with revisionsMissing designs visible
4

Get a declaration for every regulated design

Assinaturas Eletrónicas

Collect a design compliance declaration signed by the registered design practitioner for each regulated design. Where a principal design practitioner has been appointed, they make the principal compliance declaration that the designs are covered and the declarations were made by practitioners authorised to make them.

Por quê: The declaration is a personal statement by a named practitioner and it carries personal consequences, which is why it is chased rather than given. Collecting them as they are signed, against a list drawn at the start, is the difference between a routine administrative task and a search for six people at the end of a job.

EntradaDesigns collected with revisionsRegistration checked per classResultadoDesign compliance declarationsPrincipal declaration where appointed
5

Lodge them before the work they cover starts

Submissões à Autoridade

Lodge the construction issued regulated designs and their declarations through the state planning portal before building work commences, and keep the lodgement receipts against the submission record so the date can be shown rather than remembered.

Por quê: The obligation is tied to the start of the work rather than to a milestone anybody celebrates, so the deadline arrives while the site is mobilising and everyone is busy with something else. Lodging late is not curable by lodging afterwards, because the record shows when the work started.

EntradaDesigns and declarationsPlanned start on siteResultadoLodged before work startsLodgement receipts on file
6

Treat a change on site as a new regulated design

Gestão da qualidade

Route every change that touches a regulated design back through the same loop, a varied regulated design, a fresh declaration from a registered practitioner and a lodgement, before the varied work is built. Keep the link between the change and the design it varied.

Por quê: This is the step the regime is most often failed on, and it fails quietly. Work built to a marked up sketch is work with no declared design behind it, and nothing on site looks wrong; the gap appears at the end, when the building is finished and the only remedies are expensive.

EntradaDesign change on siteWhat was lodged beforeResultadoVaried design declared againWhat was built matches what was declared
7

Close it out before the occupation certificate is applied for

Encerramento

Check the close-out register holds every regulated design, every declaration and every lodgement receipt, then have the registered building practitioner make the building compliance declaration that the work complies with the designs as declared.

Por quê: The compliance declarations have to be in place before an application for an occupation certificate can be made, which means a single missing declaration holds up handover for a finished building. Every day of that is carrying cost on a project that has stopped earning.

EntradaAll declarations lodgedBuilding work completeResultadoBuilding compliance declarationReady to apply for occupation
Módulos

Módulos deste playbook

7 / 190 módulos da plataforma

O mercado para o qual este caso foi escrito

Austrália

Tudo neste caso segue a forma como a obra é medida, orçada e paga neste mercado. Os documentos, a decomposição de custos e as regras de pagamento são os que se usam lá, não uma versão genérica.

Normas que ele segue

  • AS 4000
  • Security of Payment Act

Você não precisa configurar nada disso na mão. Na primeira vez que abre a plataforma, ela pergunta em que mercado você trabalha. Escolha este e ela ajusta o idioma da interface, carrega a base de custos correspondente, registra a classificação de custos e adiciona um projeto de exemplo que você pode abrir na hora.

As verificações deste mercado também vêm com a plataforma. Ative uma vez e um orçamento ao qual falte algo que o mercado espera é sinalizado enquanto você trabalha nele, e não depois que a proposta já saiu.

Mais em Qualidade e segurança