ارجاع اختلاف پرداخت به adjudication

مشخص کنید چه چیزی اطلاع داده شده و چه چیزی نه، سوابق همزمان را در یک بسته که هر دو طرف بتوانند بازتولید کنند گردآوری کنید، اخطار را جایی که قرارداد می‌گوید ابلاغ کنید، ارجاع را با هر آنچه همراه آن است ثبت کنید، و تصمیم را به کار بازگردانید.

5 مرحله15 دقیقهپیمانکار عمومیپیمانکار جزء تخصصیمشاوره هزینه / QS

چگونه کار می‌کند، گام به گام

5 گام در سراسر پلتفرم - کاری که در هر گام انجام می‌دهید و چرا اهمیت دارد.

1

Establish what was notified and what was not

ساعت پرداخت

Read the clock for the application in dispute: the dates, the notices actually served, the ones that were missed or served out of time, and the sum the module derives as notified. Take the derivation as it is printed rather than paraphrasing it into a sentence.

چرا: Most British payment disputes are decided on the sequence rather than on the valuation. Whether a payment notice was served, whether a pay less notice stated its basis and whether either was in time will usually settle the sum before anybody looks at the work, so this is the cheapest thing to get right and the most expensive to get wrong.

ورودیPayment application and noticesStatutory datesخروجیNotified sum, with its derivationNotices missed or out of time
2

Assemble one pack both sides can reproduce

شواهد ادعا

Build the evidence pack from the source records: the notices, the correspondence, the RFIs, the approvals, the variation records and any delay analysis. The ordering is deterministic and the pack carries a content digest, so feeding the same records in a different order produces the same bundle.

تصویر صفحه، گام 2: Assemble one pack both sides can reproduce (شواهد ادعا, ارجاع اختلاف پرداخت به adjudication)
شواهد ادعا: Assemble one pack both sides can reproduce

چرا: An adjudicator reads a great deal of paper in a short time, and an ordered pack is read differently from a folder of attachments. A digest also means the other side cannot end up holding a slightly different bundle from the one the adjudicator has, which is a dispute nobody needs inside a dispute.

ورودیNotices, letters and RFIsDiary and progress recordsخروجیEvidence packSources in a fixed order
3

Serve the notice where the contract says to serve it

مکاتبات

Issue the notice of adjudication through the correspondence register: to the right party, at the address the contract gives for service, stating the nature of the dispute, what is claimed and the redress sought. The register keeps the date and the method of service with it.

تصویر صفحه، گام 3: Serve the notice where the contract says to serve it (مکاتبات, ارجاع اختلاف پرداخت به adjudication)
مکاتبات: Serve the notice where the contract says to serve it

چرا: Service is where an otherwise good referral dies. A notice sent to the wrong entity inside a group, or to an email address the contract does not recognise, can be challenged on jurisdiction before anybody looks at the merits, and the seven days to the referral do not pause while that gets sorted out.

ورودیEvidence packContract service provisionsخروجیNotice of adjudication servedDate and method of service on record
4

File the referral and everything that follows it

اسناد

Put the referral and its annexes into the project files as one versioned, dated set alongside the notice. The response, the reply and the decision go into the same place as they arrive rather than into whoever happened to receive them.

تصویر صفحه، گام 4: File the referral and everything that follows it (اسناد, ارجاع اختلاف پرداخت به adjudication)
اسناد: File the referral and everything that follows it

چرا: An adjudication produces a lot of documents in twenty eight days, across several people, usually while the job is still running. Keeping them in the project rather than in one mailbox is what lets the next stage, whether that is enforcement, a second adjudication or a settlement, start from the record instead of from a reconstruction.

ورودیReferral document and annexesNotice of adjudication servedخروجیOne filed set of the disputeResponses filed as they arrive
5

Put the decision back into the job

گزارش‌ها

Record the decision and what it changed: the sum payable, the date it is payable by, and any effect on the programme. An adjudicator's decision binds the parties until the dispute is finally determined, so it is the number the job works to from that day.

تصویر صفحه، گام 5: Put the decision back into the job (گزارش‌ها, ارجاع اختلاف پرداخت به adjudication)
گزارش‌ها: Put the decision back into the job

چرا: The commonest failure after an adjudication is that the decision stays with the commercial team while the valuations carry on exactly as before. Reporting the outcome into the project is what makes the decision operate, and it also leaves the next job an honest record of what a dispute of this kind cost in time and attention.

ورودیDecision and its dateSum payableخروجیOutcome reported to the projectValuations follow the decision
ماژول‌ها

ماژول‌های این سناریو

5 / 190 ماژول پلتفرم

The market this case is written for

بریتانیا

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • RICS NRM 1/2
  • JCT
  • CIS

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

بیشتر در بازرگانی و قراردادها

بازرگانی و قراردادها

Turn a change into a paid variation

Capture a scope change while it is fresh, price it as a contract variation on your agreed r…

3 مرحله11 دقیقهباز کردن
بازرگانی و قراردادها

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 مرحله11 دقیقهباز کردن
بازرگانی و قراردادها

Payment application and reconciliation

Value the work put in place this period against the contract, raise the application with th…

3 مرحله12 دقیقهباز کردن