Turn a change into a paid variation
Capture a scope change while it is fresh, price it as a contract variation on your agreed r…
Hinnoittele kauden työ, käynnistä lain määräämä kello, kirjaa jokainen ilmoitus sen toimittamisen mukaan, lue, mikä ilmoitettu summa todella on, ja tarkista pidätys sellaisena kuin se on pidätetty, ei sellaisena kuin se muistetaan.
5 vaihetta läpi alustan - mitä teet kussakin ja miksi sillä on merkitystä.
Raise the interim valuation as a progress claim against the contract: the gross value of work properly executed, materials on site where the contract allows them, less retention and less what was certified previously.

Miksi: The application is the document the whole clock is measured from, so its date and its content matter more than how it looks. A valuation assembled from the contract lines rather than typed in as a single figure is also the only version that can be checked line by line when somebody disputes it three weeks later.
Open a payment clock over the application under the United Kingdom regime. The due date, the payment notice deadline, the pay less deadline and the final date for payment are computed from the Act and the Scheme, counting days the way the statute counts them rather than the way a calendar app would.
Miksi: Nobody argues about a payment timetable until the week it matters, and by then the dates are being reconstructed from a mailbox. Computing them the day the application goes in means the argument that follows is about the valuation, which is a proper argument, rather than about which Tuesday something fell due.
Record the payment notice when it arrives, with the sum notified and the basis on which it was calculated. Record a pay less notice the same way, with the ground for withholding stated, and record it even when it was served late, because that is the fact which decides the sum.
Miksi: A pay less notice that states no basis of calculation is not a valid pay less notice, and one served inside the seven days before the final date is out of time. Recording what actually happened, rather than what should have happened, is what turns the sum payable into a matter of record instead of a matter of opinion.
Read what the clock says is payable and read the derivation beside it. Where a valid payment notice was served in time the notified sum is the notified amount. Where the payer served nothing, the sum applied for is the notified sum, and the payee may serve its own default payment notice under section 110B, which pushes the final date out by the days the payer was late.
Miksi: This is the part that surprises people. A missed payment notice does not shave a little off the payer's position, it hands the payee the full sum applied for, and the only escape left is a valid pay less notice served in time. Reading the derivation rather than assuming it is the difference between a payment and an adjudication you were always going to lose.
Open the retention ledger and read what has been scheduled, held and released against each counterparty, on this application and cumulatively. The figures come off the contracts rather than out of a spreadsheet one person keeps.

Miksi: Retention accumulates quietly on every valuation and is the money nobody chases until the job is over. A ledger that shows the held total per counterparty makes the half you owe and the half you are owed two separate questions, and both of them have an answer ready before anybody asks.
3 / 190 alustan moduulia
Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.
Standards it follows
You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.
The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.
Capture a scope change while it is fresh, price it as a contract variation on your agreed r…
Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…
Value the work put in place this period against the contract, raise the application with th…