केस / आकलन और लागत
आकलन और लागत

बिल जांचे जाने लायक बनाने के लिए IS 1200 के अनुसार मापें

मात्राएं ड्रॉइंग से उसी तरह लें जैसे भारतीय माप पद्धति बताती है, इकाइयों को मीट्रिक और मान्यता-प्राप्त रखें, और ऐसा माप जारी करें जिसे दूसरा पक्ष कुल पर विवाद करने के बजाय लाइन-दर-लाइन दोबारा बना सके।

5 चरण18 मिनटविशेषज्ञ उपठेकेदारमुख्य ठेकेदारलागत परामर्श / QS फर्म

यह कैसे काम करता है, चरण दर चरण

प्लेटफ़ॉर्म भर में 5 चरण - हर एक में आप क्या करते हैं और यह क्यों मायने रखता है।

1

Take the dimensions off the drawing, on the drawing

PDF माप

Calibrate the sheet against a stated dimension, then measure lengths, areas and counts directly on it, keeping each measurement attached to the place it was taken from. Work in metres and millimetres throughout.

क्यों: A measurement that lives on the drawing can be re-opened and re-checked at the exact spot it came from. A measurement that lives only in a spreadsheet cell has to be re-taken from scratch by anyone who doubts it, which is how a query about one wall becomes a re-measure of a floor.

इनपुटDrawings for the workA known scale or a dimension to set itपरिणामMeasurements on the drawingEach figure traceable to where it was taken
2

Turn dimensions into quantities the standard way

मात्रा निकालना

Build the quantity register trade by trade, applying the deduction and inclusion rules the method of measurement sets for each: openings in masonry and plaster, the treatment of the working space in excavation, how reinforcement is measured against how it is placed. Keep the deduction on the register rather than folded into a net figure.

क्यों: The deductions are where two honest takeoffs separate, so they are exactly what a checker wants to see. A register that shows gross, deduction and net can be agreed in one pass; one that shows only net invites a full re-measure to find out why it is short.

इनपुटRaw dimensions from the drawingपरिणामQuantities on the standard methodDeductions applied and visible
3

Post the quantities onto the bill items they belong to

मात्रा विवरण

Move the measured quantities onto the bill, matching each to the item whose description covers the work actually measured, and splitting a measurement across two items rather than stretching one description to cover both.

क्यों: An item description and a method of measurement are a pair: the description says what the rate includes and the method says how the quantity was arrived at. Posting a quantity under a description that does not cover it breaks the pair quietly, and the error surfaces at valuation as a rate that seems wrong.

इनपुटThe quantity registerपरिणामBill items with their quantities
4

Check the units before anybody prices them

सत्यापन

Validate the bill and read what comes back about units. The India pack ships a rule that asks for a unit the method of measurement recognises, and metric only, so an imperial leftover or an invented unit is reported rather than priced.

क्यों: A wrong unit does not look wrong. It looks like a rate that is out by a factor, and it is usually blamed on the rate. Catching it as a unit finding names the actual defect and fixes one line instead of re-arguing a trade.

इनपुटThe measured billपरिणामUnits the method does not recognise
5

Issue the measurement in a form the other side can re-do

रिपोर्ट

Produce the measurement sheet showing item, dimensions, deductions, unit and quantity, and send that rather than a single total per trade.

क्यों: Agreement is reached at the line that differs, and only a sheet that shows lines has one. Sending a total asks the other party to trust you, which on a running account nobody does twice.

इनपुटThe checked measurementपरिणामA measurement sheet the other side can reproduce
मॉड्यूल

इस प्लेबुक के मॉड्यूल

प्लेटफ़ॉर्म के 190 में से 5 मॉड्यूल

The market this case is written for

भारत

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

आकलन और लागत में और देखें

आकलन और लागत

Check an estimate before you send it

Put a priced bill through the validation rules, clear every warning and error, then export…

3 चरण8 मिनटखोलें
आकलन और लागत

Estimate from a cost database

Pull priced items from a real cost database, build the bill from them, bundle recurring bui…

4 चरण12 मिनटखोलें
आकलन और लागत

Set contingency from cost risk

Turn a single-point estimate into a range, run a Monte Carlo over the genuinely uncertain l…

3 चरण11 मिनटखोलें