케이스 / 입찰 및 조달
입찰 및 조달

정부 입찰을 예정가격과 대조하여 평가하기

입찰의 기준이 되는 예정가격을 확정하고, 모든 응찰자에게 동일한 내역서를 발급하고, 응찰서를 접수·개찰하고, 비율뿐 아니라 예정가격과 항목별로 대조해 검토하며, 낙찰 사유를 기록으로 남깁니다.

5단계24 분시행사 / 발주처PM/CM 업체원가 컨설팅 / 적산 업체종합건설사

작동 방식, 단계별로

플랫폼 전반에 걸친 5단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Fix the estimated cost the tender is called on

견적 근거

Record the estimated cost as issued, the schedule and edition behind it, the price level, and what it excludes. Freeze it before the notice goes out, so later comparison is against the figure bidders actually saw.

이유: An estimate that keeps moving after issue cannot be compared with anything. Fixing it is what makes the percentage above or below meaningful, and it is the first thing an audit of the award asks to see.

입력The priced estimateThe sanctioned amount결과The estimated cost, fixed and dated
2

Issue one bill, one set of conditions, one clock

입찰

Publish the tender on the frozen bill, stating the tender form, whether rates are quoted item by item or as a single percentage, the earnest money required, the eligibility conditions and the closing date. Issue every clarification to every bidder.

이유: The comparison at the end is only valid if the offers answer the same question. A clarification sent to one bidder, or a bill quietly corrected after issue, breaks that and is the most common ground on which an award is challenged.

입력The tender billConditions and eligibility결과One bill issued to everyoneDates and the earnest money required
3

Receive the offers and settle eligibility before price

입찰 관리

Log every offer with its time of receipt, check the earnest money and the eligibility documents, and settle who is technically qualified before any financial offer is read.

이유: Two-stage opening exists so that eligibility cannot be decided by knowing the price. Recording the technical decision with its date, before the financial opening, is what makes that separation demonstrable rather than merely intended.

입력Sealed offers결과A register of who bid and whenWho cleared the technical stage
4

Compare at the item, not only at the percentage

Cost Explorer

Put the offers beside the estimated rates and look for items that are far below the estimate on early work and far above on late work, and for rates that no analysis supports. Query those with the bidder and record the answer.

이유: Front loading is legal, invisible in a total, and expensive. So is a rate so far below the estimate that the item cannot be built for it, because that work is either not done or comes back as a claim. Both are visible only when the bill is compared line by line against a fixed reference.

입력Qualified offers on the same billThe estimated rates결과Item by item spread against the estimateThe items worth querying
5

Award on the record, with the security in place

계약

Set the contract up on the accepted rates, carry the percentage above or below onto it, and record the performance security, the defect liability period and the price variation position agreed at award.

이유: Everything the job argues about later, valuation, extras, escalation, release of security, is decided against what the contract says at this moment. Writing it down here is cheap; reconstructing it from the tender file two years later is not.

입력The recommendation and its reasons결과A contract on the accepted ratesPerformance security recorded
모듈

이 플레이북의 모듈

플랫폼 190개 모듈 중 5

The market this case is written for

인도

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • CPWD DSR
  • IS 456
  • RERA

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

입찰 및 조달 카테고리의 더 보기

입찰 및 조달

Run a tender from a BOQ

Take a priced bill of quantities out to market: package it, invite the subcontractors, leve…

5단계12 분열기
입찰 및 조달

Procure materials from the BOQ

Buy the quantities you already priced: raise a requisition off the bill, place the order wi…

4단계10 분열기
입찰 및 조달

Compare bids and award

Take a folder of returned tenders that never quite match, strip them back to the same scope…

3단계12 분열기