Keep a court-proof Bautagebuch

Write the site day while it happens - weather from an independent source, crews, progress, obstructions and visitors - book the hours the same day, then close and sign the diary so it is sealed evidence instead of something written up weeks later.

6 кадам11 мүнБашкы подрядчыАдистешкен субподрядчыДолбоор / курулуш менеджмент компаниясы

Бул кантип иштейт, кадам-кадам менен

6 кадам платформа боюнча - ар бир кадамда эмне кылуу керек жана ал эмне үчүн маанилүү.

1

Open the day and pull the weather

Күндөлүк журнал

Open today's Bautagebuch and fetch the weather for the project location from the Open-Meteo service rather than typing it from memory. Record the crews and subcontractors on site, the headcount, the visitors and deliveries, and what each area actually got done.

Эмне үчүн: Weather fetched from an independent service on the day it happened is a fact. Weather remembered in December is an assertion, and the other side gets to test it. Frost days, rain days and the crews who stood in them are what an extension of time is later built from, and they only count if they were written while they were still true.

КиретWeather for the site locationCrews and subcontractorsVisitors and deliveriesЧыгатBautagebuch for the dayCrews, visitors and progress logged
2

Log the Behinderung at the hour it starts

Күндөлүк журнал

The moment the work is obstructed - the shaft is not handed over, the design answer is missing, the ready-mix does not arrive - log it on the diary as its own entry: the clock time it began, what exactly is blocked, which crews are standing in it and who on the client side was told.

Эмне үчүн: A Behinderung recorded as hold-ups in week 34 is worth nothing. The hour it started, the gang that stood in it and the name of the person you told are what turn a complaint into a claim somebody can price. Write it while the crane is still standing, not when the month is being closed.

КиретObstruction on siteClock time it beganCrews standing idleЧыгатTimed Behinderung entryBasis for the notice
3

Serve the Behinderungsanzeige

Кат-кабарлар

Raise the Behinderungsanzeige to the Auftraggeber as an outgoing notice in the correspondence register, quoting the diary entry and its date, and set a response deadline so the answer - or the silence - lands on the same thread.

Эмне үчүн: The diary entry is your evidence, but it is not the notice. VOB/B expects the Auftraggeber to be told in writing without delay, and the claim for time or money most often refused is the one that was never announced. Served from the register it carries its own timestamp and its own thread, so nobody has to search a mailbox two years later.

КиретBehinderung diary entryContract and partiesЧыгатServed BehinderungsanzeigeDated notice thread
4

Book the hours before anyone leaves site

Талаа убактысы

Book the hours every person and every machine put in today against the right cost code, and flag the standing time caused by the Behinderung as daywork. The day recorder works offline, so the Vorarbeiter books from the site instead of from the office.

Эмне үчүн: MiLoG paragraph 17 gives seven days for the working-hours record to exist and requires it to be kept for at least two years. Booked on the day you are inside that window without anyone writing up the week from memory on a Friday evening, and the standing hours get priced while it is still obvious who stood where and for how long.

КиретCrews and plant on siteCost codesStanding time from the BehinderungЧыгатHours booked on the dayStanding time as daywork
5

Attach the photos, close and sign the day

Күндөлүк журнал

Attach the day's photos to the entries they belong to, close the diary and sign it. Signing freezes the contents behind a SHA-256 hash, and the PDF export is the copy you hand to the client or the lawyer.

Эмне үчүн: A diary that can still be edited invites the one question that decides everything: when was this really written? A signed day answers it before it is asked, because the hash proves the text has not moved since the evening it was written. It is also the moment the Bauleiter stops carrying the week home.

КиретPhotos taken todayThe day entriesЧыгатSigned and sealed diary dayPDF for the project file
6

Two years on, assemble the evidence

Дааларга далилдер

When the dispute finally arrives, open the claims evidence view for the delay or the change in question. It gathers the diary days, the notices, the booked hours and the photos from those dates into one pack and scores how well the record actually carries the point.

Эмне үчүн: This is where the daily discipline gets paid. Every entry was made on the day it describes, so the pack is a contemporaneous record and not a reconstruction, and the score shows you which days are thin while there is still time to say so yourself.

КиретSigned diary daysServed noticesBooked hours and photosЧыгатEvidence packProvability score
Модулдар

Ушул сценарийдин модулдары

Платформанын 184 модулунун 4

Обьект жана талаа бөлүмүндө дагы

Обьект жана талаа

Сайттын күнүн иштетүү

Күндү туура жабыңыз: күндөлүктү жазыңыз, эмгек жана техника сааттарын брондоңуз, сүрөттөрдү…

4 кадам9 мүнАчуу
Обьект жана талаа

RFIге жооп берүү

Иш жүзүндөгү суроону катталган суроо-талапка айлантыңыз, аны жоопту ээсине багыттаңыз жана ж…

3 кадам9 мүнАчуу