Cases / Byggeplads og felt
Byggeplads og felt

Før en retssikker Bautagebuch

Skriv byggepladsdagen, mens den sker - vejr fra en uafhængig kilde, mandskab, fremdrift, forhindringer og besøgende - bogfør timerne samme dag, og luk og underskriv journalen, så den er forseglet bevis frem for noget skrevet sammen uger senere.

6 trin11 minHovedentreprenørFagentreprenørProjekt- / byggeledelsesfirma

Sådan fungerer det, trin for trin

6 trin gennem platformen - hvad du gør i hvert, og hvorfor det betyder noget.

1

Open the day and pull the weather

Byggedagbog

Open today's Bautagebuch and fetch the weather for the project location from the Open-Meteo service rather than typing it from memory. Record the crews and subcontractors on site, the headcount, the visitors and deliveries, and what each area actually got done.

Hvorfor: Weather fetched from an independent service on the day it happened is a fact. Weather remembered in December is an assertion, and the other side gets to test it. Frost days, rain days and the crews who stood in them are what an extension of time is later built from, and they only count if they were written while they were still true.

InputWeather for the site locationCrews and subcontractorsVisitors and deliveriesResultatBautagebuch for the dayCrews, visitors and progress logged
2

Log the Behinderung at the hour it starts

Byggedagbog

The moment the work is obstructed - the shaft is not handed over, the design answer is missing, the ready-mix does not arrive - log it on the diary as its own entry: the clock time it began, what exactly is blocked, which crews are standing in it and who on the client side was told.

Skærmbillede, trin 2: Log the Behinderung at the hour it starts (Byggedagbog, Før en retssikker Bautagebuch)
Byggedagbog: Log the Behinderung at the hour it starts

Hvorfor: A Behinderung recorded as hold-ups in week 34 is worth nothing. The hour it started, the gang that stood in it and the name of the person you told are what turn a complaint into a claim somebody can price. Write it while the crane is still standing, not when the month is being closed.

InputObstruction on siteClock time it beganCrews standing idleResultatTimed Behinderung entryBasis for the notice
3

Serve the Behinderungsanzeige

Korrespondance

Raise the Behinderungsanzeige to the Auftraggeber as an outgoing notice in the correspondence register, quoting the diary entry and its date, and set a response deadline so the answer - or the silence - lands on the same thread.

Skærmbillede, trin 3: Serve the Behinderungsanzeige (Korrespondance, Før en retssikker Bautagebuch)
Korrespondance: Serve the Behinderungsanzeige

Hvorfor: The diary entry is your evidence, but it is not the notice. VOB/B expects the Auftraggeber to be told in writing without delay, and the claim for time or money most often refused is the one that was never announced. Served from the register it carries its own timestamp and its own thread, so nobody has to search a mailbox two years later.

InputBehinderung diary entryContract and partiesResultatServed BehinderungsanzeigeDated notice thread
4

Book the hours before anyone leaves site

Felttid

Book the hours every person and every machine put in today against the right cost code, and flag the standing time caused by the Behinderung as daywork. The day recorder works offline, so the Vorarbeiter books from the site instead of from the office.

Skærmbillede, trin 4: Book the hours before anyone leaves site (Felttid, Før en retssikker Bautagebuch)
Felttid: Book the hours before anyone leaves site

Hvorfor: MiLoG paragraph 17 gives seven days for the working-hours record to exist and requires it to be kept for at least two years. Booked on the day you are inside that window without anyone writing up the week from memory on a Friday evening, and the standing hours get priced while it is still obvious who stood where and for how long.

InputCrews and plant on siteCost codesStanding time from the BehinderungResultatHours booked on the dayStanding time as daywork
5

Attach the photos, close and sign the day

Byggedagbog

Attach the day's photos to the entries they belong to, close the diary and sign it. Signing freezes the contents behind a SHA-256 hash, and the PDF export is the copy you hand to the client or the lawyer.

Hvorfor: A diary that can still be edited invites the one question that decides everything: when was this really written? A signed day answers it before it is asked, because the hash proves the text has not moved since the evening it was written. It is also the moment the Bauleiter stops carrying the week home.

InputPhotos taken todayThe day entriesResultatSigned and sealed diary dayPDF for the project file
6

Two years on, assemble the evidence

Kravbeviser

When the dispute finally arrives, open the claims evidence view for the delay or the change in question. It gathers the diary days, the notices, the booked hours and the photos from those dates into one pack and scores how well the record actually carries the point.

Skærmbillede, trin 6: Two years on, assemble the evidence (Kravbeviser, Før en retssikker Bautagebuch)
Kravbeviser: Two years on, assemble the evidence

Hvorfor: This is where the daily discipline gets paid. Every entry was made on the day it describes, so the pack is a contemporaneous record and not a reconstruction, and the score shows you which days are thin while there is still time to say so yourself.

InputSigned diary daysServed noticesBooked hours and photosResultatEvidence packProvability score
Moduler

Moduler i denne playbook

4 / 190 platformmoduler

The market this case is written for

Tyskland

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • DIN 276
  • GAEB XML
  • VOB/B

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Mere inden for Byggeplads og felt

Byggeplads og felt

Run the site day

Close the day out properly: record the diary, book the labour and plant hours, upload the p…

4 trin9 minÅbn
Byggeplads og felt

Answer an RFI

Turn a question from the working face into a tracked request, drive it to the party who own…

3 trin9 minÅbn