Keep a court-proof Bautagebuch

Write the site day while it happens - weather from an independent source, crews, progress, obstructions and visitors - book the hours the same day, then close and sign the diary so it is sealed evidence instead of something written up weeks later.

6 שלבים11 דק׳קבלן ראשיקבלן משנה מתמחהמשרד ניהול פרויקטים / בנייה

איך זה עובד, שלב אחר שלב

6 שלבים לאורך הפלטפורמה - מה עושים בכל שלב ולמה זה חשוב.

1

Open the day and pull the weather

יומן יומי

Open today's Bautagebuch and fetch the weather for the project location from the Open-Meteo service rather than typing it from memory. Record the crews and subcontractors on site, the headcount, the visitors and deliveries, and what each area actually got done.

למה: Weather fetched from an independent service on the day it happened is a fact. Weather remembered in December is an assertion, and the other side gets to test it. Frost days, rain days and the crews who stood in them are what an extension of time is later built from, and they only count if they were written while they were still true.

נכנסWeather for the site locationCrews and subcontractorsVisitors and deliveriesיוצאBautagebuch for the dayCrews, visitors and progress logged
2

Log the Behinderung at the hour it starts

יומן יומי

The moment the work is obstructed - the shaft is not handed over, the design answer is missing, the ready-mix does not arrive - log it on the diary as its own entry: the clock time it began, what exactly is blocked, which crews are standing in it and who on the client side was told.

למה: A Behinderung recorded as hold-ups in week 34 is worth nothing. The hour it started, the gang that stood in it and the name of the person you told are what turn a complaint into a claim somebody can price. Write it while the crane is still standing, not when the month is being closed.

נכנסObstruction on siteClock time it beganCrews standing idleיוצאTimed Behinderung entryBasis for the notice
3

Serve the Behinderungsanzeige

התכתבות

Raise the Behinderungsanzeige to the Auftraggeber as an outgoing notice in the correspondence register, quoting the diary entry and its date, and set a response deadline so the answer - or the silence - lands on the same thread.

למה: The diary entry is your evidence, but it is not the notice. VOB/B expects the Auftraggeber to be told in writing without delay, and the claim for time or money most often refused is the one that was never announced. Served from the register it carries its own timestamp and its own thread, so nobody has to search a mailbox two years later.

נכנסBehinderung diary entryContract and partiesיוצאServed BehinderungsanzeigeDated notice thread
4

Book the hours before anyone leaves site

זמן שטח

Book the hours every person and every machine put in today against the right cost code, and flag the standing time caused by the Behinderung as daywork. The day recorder works offline, so the Vorarbeiter books from the site instead of from the office.

למה: MiLoG paragraph 17 gives seven days for the working-hours record to exist and requires it to be kept for at least two years. Booked on the day you are inside that window without anyone writing up the week from memory on a Friday evening, and the standing hours get priced while it is still obvious who stood where and for how long.

נכנסCrews and plant on siteCost codesStanding time from the BehinderungיוצאHours booked on the dayStanding time as daywork
5

Attach the photos, close and sign the day

יומן יומי

Attach the day's photos to the entries they belong to, close the diary and sign it. Signing freezes the contents behind a SHA-256 hash, and the PDF export is the copy you hand to the client or the lawyer.

למה: A diary that can still be edited invites the one question that decides everything: when was this really written? A signed day answers it before it is asked, because the hash proves the text has not moved since the evening it was written. It is also the moment the Bauleiter stops carrying the week home.

נכנסPhotos taken todayThe day entriesיוצאSigned and sealed diary dayPDF for the project file
6

Two years on, assemble the evidence

ראיות תביעה

When the dispute finally arrives, open the claims evidence view for the delay or the change in question. It gathers the diary days, the notices, the booked hours and the photos from those dates into one pack and scores how well the record actually carries the point.

למה: This is where the daily discipline gets paid. Every entry was made on the day it describes, so the pack is a contemporaneous record and not a reconstruction, and the score shows you which days are thin while there is still time to say so yourself.

נכנסSigned diary daysServed noticesBooked hours and photosיוצאEvidence packProvability score
מודולים

המודולים בתרחיש הזה

4 מתוך 184 מודולי הפלטפורמה

עוד ב-אתר ושטח

אתר ושטח

ניהול יום העבודה באתר

סגרו את היום כראוי: תעדו את היומן, רשמו את שעות כוח האדם והציוד, העלו את התצלומים ותעדו תצפי…

4 שלבים9 דק׳פתיחה
אתר ושטח

מענה לבקשת מידע

הפכו שאלה מפני העבודה לבקשת מידע במעקב, הובילו אותה לגורם האחראי על התשובה, ותייקו את המענה…

3 שלבים9 דק׳פתיחה
אתר ושטח

תיעוד יומעבודה וזמן וחומרים

הפכו עבודה נוספת שהוזמנה לתביעה שמשולמת: תעדו את העבודה, הציוד והחומרים תוך כדי התרחשות, קבל…

3 שלבים9 דק׳פתיחה