Run the site day
Close the day out properly: record the diary, book the labour and plant hours, upload the p…
Tulis hari kerja lapangan saat itu juga terjadi - cuaca dari sumber independen, kru, progres, hambatan dan tamu - bukukan jam kerja pada hari yang sama, lalu tutup dan tandatangani buku harian itu sehingga ia menjadi bukti tersegel, bukan sesuatu yang ditulis ulang berminggu-minggu kemudian.
6 langkah di seluruh platform - apa yang Anda lakukan di setiap langkah dan mengapa itu penting.
Open today's Bautagebuch and fetch the weather for the project location from the Open-Meteo service rather than typing it from memory. Record the crews and subcontractors on site, the headcount, the visitors and deliveries, and what each area actually got done.
Mengapa: Weather fetched from an independent service on the day it happened is a fact. Weather remembered in December is an assertion, and the other side gets to test it. Frost days, rain days and the crews who stood in them are what an extension of time is later built from, and they only count if they were written while they were still true.
The moment the work is obstructed - the shaft is not handed over, the design answer is missing, the ready-mix does not arrive - log it on the diary as its own entry: the clock time it began, what exactly is blocked, which crews are standing in it and who on the client side was told.

Mengapa: A Behinderung recorded as hold-ups in week 34 is worth nothing. The hour it started, the gang that stood in it and the name of the person you told are what turn a complaint into a claim somebody can price. Write it while the crane is still standing, not when the month is being closed.
Raise the Behinderungsanzeige to the Auftraggeber as an outgoing notice in the correspondence register, quoting the diary entry and its date, and set a response deadline so the answer - or the silence - lands on the same thread.

Mengapa: The diary entry is your evidence, but it is not the notice. VOB/B expects the Auftraggeber to be told in writing without delay, and the claim for time or money most often refused is the one that was never announced. Served from the register it carries its own timestamp and its own thread, so nobody has to search a mailbox two years later.
Book the hours every person and every machine put in today against the right cost code, and flag the standing time caused by the Behinderung as daywork. The day recorder works offline, so the Vorarbeiter books from the site instead of from the office.

Mengapa: MiLoG paragraph 17 gives seven days for the working-hours record to exist and requires it to be kept for at least two years. Booked on the day you are inside that window without anyone writing up the week from memory on a Friday evening, and the standing hours get priced while it is still obvious who stood where and for how long.
Attach the day's photos to the entries they belong to, close the diary and sign it. Signing freezes the contents behind a SHA-256 hash, and the PDF export is the copy you hand to the client or the lawyer.
Mengapa: A diary that can still be edited invites the one question that decides everything: when was this really written? A signed day answers it before it is asked, because the hash proves the text has not moved since the evening it was written. It is also the moment the Bauleiter stops carrying the week home.
When the dispute finally arrives, open the claims evidence view for the delay or the change in question. It gathers the diary days, the notices, the booked hours and the photos from those dates into one pack and scores how well the record actually carries the point.

Mengapa: This is where the daily discipline gets paid. Every entry was made on the day it describes, so the pack is a contemporaneous record and not a reconstruction, and the score shows you which days are thin while there is still time to say so yourself.
4 / 190 modul platform
Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.
Standards it follows
You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.
Close the day out properly: record the diary, book the labour and plant hours, upload the p…
Turn a question from the working face into a tracked request, drive it to the party who own…
Turn instructed extra work into a claim that gets paid: record the labour, plant and materi…