Keep a court-proof Bautagebuch

Write the site day while it happens - weather from an independent source, crews, progress, obstructions and visitors - book the hours the same day, then close and sign the diary so it is sealed evidence instead of something written up weeks later.

6단계11 분종합건설사전문건설사PM/CM 업체

작동 방식, 단계별로

플랫폼 전반에 걸친 6단계 - 각 단계에서 무엇을 하는지, 그리고 왜 중요한지.

1

Open the day and pull the weather

현장 일지

Open today's Bautagebuch and fetch the weather for the project location from the Open-Meteo service rather than typing it from memory. Record the crews and subcontractors on site, the headcount, the visitors and deliveries, and what each area actually got done.

이유: Weather fetched from an independent service on the day it happened is a fact. Weather remembered in December is an assertion, and the other side gets to test it. Frost days, rain days and the crews who stood in them are what an extension of time is later built from, and they only count if they were written while they were still true.

입력Weather for the site locationCrews and subcontractorsVisitors and deliveries결과Bautagebuch for the dayCrews, visitors and progress logged
2

Log the Behinderung at the hour it starts

현장 일지

The moment the work is obstructed - the shaft is not handed over, the design answer is missing, the ready-mix does not arrive - log it on the diary as its own entry: the clock time it began, what exactly is blocked, which crews are standing in it and who on the client side was told.

이유: A Behinderung recorded as hold-ups in week 34 is worth nothing. The hour it started, the gang that stood in it and the name of the person you told are what turn a complaint into a claim somebody can price. Write it while the crane is still standing, not when the month is being closed.

입력Obstruction on siteClock time it beganCrews standing idle결과Timed Behinderung entryBasis for the notice
3

Serve the Behinderungsanzeige

서신

Raise the Behinderungsanzeige to the Auftraggeber as an outgoing notice in the correspondence register, quoting the diary entry and its date, and set a response deadline so the answer - or the silence - lands on the same thread.

이유: The diary entry is your evidence, but it is not the notice. VOB/B expects the Auftraggeber to be told in writing without delay, and the claim for time or money most often refused is the one that was never announced. Served from the register it carries its own timestamp and its own thread, so nobody has to search a mailbox two years later.

입력Behinderung diary entryContract and parties결과Served BehinderungsanzeigeDated notice thread
4

Book the hours before anyone leaves site

현장 시간

Book the hours every person and every machine put in today against the right cost code, and flag the standing time caused by the Behinderung as daywork. The day recorder works offline, so the Vorarbeiter books from the site instead of from the office.

이유: MiLoG paragraph 17 gives seven days for the working-hours record to exist and requires it to be kept for at least two years. Booked on the day you are inside that window without anyone writing up the week from memory on a Friday evening, and the standing hours get priced while it is still obvious who stood where and for how long.

입력Crews and plant on siteCost codesStanding time from the Behinderung결과Hours booked on the dayStanding time as daywork
5

Attach the photos, close and sign the day

현장 일지

Attach the day's photos to the entries they belong to, close the diary and sign it. Signing freezes the contents behind a SHA-256 hash, and the PDF export is the copy you hand to the client or the lawyer.

이유: A diary that can still be edited invites the one question that decides everything: when was this really written? A signed day answers it before it is asked, because the hash proves the text has not moved since the evening it was written. It is also the moment the Bauleiter stops carrying the week home.

입력Photos taken todayThe day entries결과Signed and sealed diary dayPDF for the project file
6

Two years on, assemble the evidence

클레임 증거

When the dispute finally arrives, open the claims evidence view for the delay or the change in question. It gathers the diary days, the notices, the booked hours and the photos from those dates into one pack and scores how well the record actually carries the point.

이유: This is where the daily discipline gets paid. Every entry was made on the day it describes, so the pack is a contemporaneous record and not a reconstruction, and the score shows you which days are thin while there is still time to say so yourself.

입력Signed diary daysServed noticesBooked hours and photos결과Evidence packProvability score
모듈

이 플레이북의 모듈

플랫폼 184개 모듈 중 4

현장 및 작업 카테고리의 더 보기

현장 및 작업

현장 일일 업무 진행

하루를 제대로 마무리합니다. 작업일지를 기록하고, 노무 및 장비 시간을 등록하고, 사진을 업로드하고, 안전 관찰 사항을 기록하여 그날의 기록이 나중에 근거로 활용될…

4단계9 분열기
현장 및 작업

RFI 답변하기

현장에서 나온 질문을 추적 가능한 요청으로 전환하고, 답변 책임자에게 전달하여, 회신 내용을 기록으로 남깁니다.

3단계9 분열기
현장 및 작업

실비정산(데이워크) 및 시간자재 기록

지시된 추가 작업을 지급받는 클레임으로 전환합니다: 발생 즉시 노무, 장비, 자재를 기록하고, 당일 시트에 서명을 받은 뒤 계약에 따라 제출합니다.

3단계9 분열기