Chase every overdue date in one place

Pull every due date the platform tracks into a single register, see what is genuinely late rather than what feels late, let the sweep tell the owners, and turn the worst one into a task somebody owns.

3 kroków9 minGeneralny wykonawcaBiuro zarządzania projektem / budowąDeweloper / klient

Jak to działa, krok po kroku

3 kroków w całej platformie - co robisz na każdym z nich i dlaczego to ważne.

1

See what is actually late

Terminy

Open the deadline register and switch it to overdue. It gathers the dates each module already tracks, correspondence response deadlines, corrective actions off non-conformance reports, open punch items, and groups them by module with the days late on each, so you read one list instead of opening three.

Dlaczego: A project rarely slips in one obvious place. It slips a few days here and a week there, in registers nobody reads together, and by the time it is visible in the programme the reasons are two months old. One list turns a vague feeling that things are drifting into a count you can do something about this morning.

WejścieDue dates across modulesOverdue filterWynikOne overdue registerDays late on each item
2

Let the sweep tell the owners

Terminy

The overdue sweep runs across the same register and pushes a reminder to whoever owns each late item. Once an item has sat past the grace window it escalates to the project managers, once and only once, and the register shows you what it moved.

Dlaczego: Very little slips because somebody decided to ignore it. It slips because nobody told them it was theirs. Escalating on a grace window rather than on day one is what keeps the escalation worth reading, because a manager copied into everything reads none of it.

WejścieOverdue itemsOwners and managersWynikOwners toldEscalations past the grace window
3

Turn the worst one into a tracked action

Zadania

Take the item sitting at the top of the overdue list and raise a task against it with a named owner and a date you actually believe. Work it until the underlying record closes, at which point the entry drops out of the register on its own.

Dlaczego: A reminder tells somebody a date has passed. It does not tell them what to do next, and the ones that have gone badly overdue are usually the ones where that is not obvious. The register only shortens when the source record closes, so the task has to point at the real work rather than at the reminder about it.

WejścieThe worst overdue itemA named ownerWynikTask with an owner and a dateRegister entry cleared
Moduły

Moduły w tym playbooku

TerminyZadania

2 / 184 modułów platformy

Więcej w kategorii Budowa i teren

Budowa i teren

Zamknij dzień budowy

Zamknij dzień budowy prawidłowo: wpisz dziennik, zaksięguj godziny roboczej i sprzętu, wgraj…

4 kroków9 minOtwórz
Budowa i teren

Odpowiedz na zapytanie RFI

Zamień pytanie z frontu robót w śledzone zapytanie, przekaż je stronie odpowiedzialnej za od…

3 kroków9 minOtwórz