Wyślij kosztorys do Hiszpanii w formacie FIEBDC-3

Wyeksportuj wyceniony kosztorys do FIEBDC-3, formatu budżetowego, w którym wymienia się dane rynek hiszpański i latynoamerykański, tak by otworzył się jako prawdziwy presupuesto w desktopowym narzędziu kosztorysowym i wrócił przez twój własny czytnik bez zmian.

4 kroków11 minDoradztwo kosztowe / kosztorysowanieGeneralny wykonawcaPodwykonawca specjalistyczny

Jak to działa, krok po kroku

4 kroków w całej platformie - co robisz na każdym z nich i dlaczego to ważne.

1

Get the bill ready to travel

BOQ

Check the bill has the shape BC3 expects before you export anything: a chapter for each section, an item for each position, and a code, a unit, a quantity and a unit rate on every line. Long descriptions travel too, so read the ones you would rather a client did not see.

Zrzut ekranu, krok 1: Get the bill ready to travel (BOQ, Wyślij kosztorys do Hiszpanii w formacie FIEBDC-3)
BOQ: Get the bill ready to travel

Dlaczego: BC3 carries a hierarchy, so a bill with orphaned positions or two items sharing a code arrives at the other end as a budget nobody can navigate. Sorting the tree out here takes minutes. Sorting it out after someone has started pricing in their own software is no longer your decision to make.

WejściePriced billChapter structureWynikClean chapter and item treeEvery position coded
2

Export to FIEBDC-3

BOQ

Export the bill to FIEBDC-3. The file carries the chapters and items with their codes, units, quantities, unit rates and long texts, which is what a Spanish desktop estimating tool needs to open it as a working budget instead of a list of numbers.

Zrzut ekranu, krok 2: Export to FIEBDC-3 (BOQ, Wyślij kosztorys do Hiszpanii w formacie FIEBDC-3)
BOQ: Export to FIEBDC-3

Dlaczego: BC3 is what that market actually exchanges budgets in, and for Spanish public work it is not optional. Sending a spreadsheet instead means somebody at the other end retypes your bill, and a retyped bill of four hundred positions always loses a few.

WejścieStructured priced billFIEBDC-3 exportWynikBC3 budget fileHierarchy, rates and texts
3

Check the charset in the header

BOQ

Open the file and read the charset the header declares. It is written Windows-1252 by default, which is what the desktop tools in that market expect, and it switches to UTF-8 only when a character in your texts cannot be represented. Either way the header states which one was used.

Dlaczego: A mis-declared charset is the classic BC3 failure. The file opens, the numbers are all correct, and every accented character in the descriptions comes out as rubbish. It gets spotted late, usually by the client reading your descriptions, and it makes an otherwise careful submission look sloppy.

WejścieBC3 filePosition textsWynikCharset named in the headerText that survives the trip
4

Prove the round trip

BOQ

Read the file you have just written straight back in through the BC3 importer and compare it against what you exported. Codes, chapters, quantities, units, rates and long texts should all come back the same.

Dlaczego: An export nobody has ever read back is a guess. Putting it through your own reader takes a minute and is the difference between believing the file is sound and knowing it, which matters most on the submission where you do not get a second go.

WejścieExported BC3 fileBC3 importerWynikRe-imported billConfirmed match
Moduły

Moduły w tym playbooku

Bill of Quantities

1 / 190 modułów platformy

The market this case is written for

Hiszpania

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • FIEBDC-3 (BC3)
  • LCSP

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

Więcej w kategorii Sprawy handlowe i kontrakty

Sprawy handlowe i kontrakty

Turn a change into a paid variation

Capture a scope change while it is fresh, price it as a contract variation on your agreed r…

3 kroków11 minOtwórz
Sprawy handlowe i kontrakty

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 kroków11 minOtwórz