Коригирайте цена на материал с индекс на разходите

Прочетете клаузата за корекция, заредете посочената индексна серия, добавете в сметката ред за оскъпяване, който назовава серията и двата периода, и издайте корекцията като документ, показващ собственото си изчисление.

5 стъпки16 минГлавен изпълнителСпециализиран подизпълнителКонсултиране по разходи / остойностяване

Как работи, стъпка по стъпка

5 стъпки през платформата - какво правите на всяка и защо е важно.

1

Read the clause before you compute anything

Договори

Open the contract and write down four things: which method it names, which materials are adjustable, what the base date is, and what movement has to occur before an adjustment is due. This case walks the price-index method; if your contract names the published-price method instead, the base data and the arithmetic are different and the clause will say so.

Защо: An adjustment computed correctly under the wrong method is worth nothing, and it is the sort of error that survives several months before anybody checks. Getting the four terms out of the contract once, in writing, saves rereading it every month and stops each month's calculation being a fresh interpretation.

ВходThe contractРезултатThe method namedBase date and adjustable materials
2

Load the series the contract names, period by period

Ценови индекс

Enter the index series with a value for each period, and keep it current as the publication comes out. The values you load are the published ones for your region; the product ships the mechanism and generic vocabulary rather than anybody's published book.

Защо: The series is the evidence. Loading it as data means the adjustment can be recomputed and audited a year later against the same values, instead of resting on a screenshot somebody took of a bulletin that has since been superseded.

ВходPublished index valuesРезултатSeries with its periodsPeriods you are missing
3

Put the adjustment on the bill as a named series and two periods

Количествена сметка

Add an escalation line to the bill's markup stack and give it the series and the two periods: the base period the contract names, and the period the work was done in. The factor comes from what the index did between them; you do not type a percentage.

Защо: Where the series has no value for one of the two periods, the bill refuses rather than guessing, and a refusal is the right answer: an interpolated index value is a number nobody published and nobody can defend. It also means an adjustment that looks complete really is complete, instead of quietly containing a line that priced at zero.

ВходThe bill and its quantitiesBase period and current periodРезултатEscalation line on the billA refusal instead of a wrong total
4

Issue it as a document that shows its working

Отчети

Report the adjustment with the series it used, the two periods, the factor and the base value it was applied to, so the reader can follow the arithmetic without asking you for the spreadsheet.

Защо: An adjustment presented as a single figure gets queried every time. The same adjustment presented with its inputs gets checked once and accepted, because the person checking it can do the multiplication themselves and stop.

ВходThe adjusted billРезултатAdjustment statementSeries, periods and factor shown
5

Submit it for the period and get the amount agreed

Кореспонденция

Send the statement to the other party as correspondence for the period it covers, and record the agreed figure against it. Carry the agreed amount into the period's payment application yourself, on its own line, so it can be seen and queried separately from the valuation.

Защо: An adjustment buried inside a valuation total is one that gets renegotiated at settlement, because nobody can find it. On its own line, submitted with its working and agreed period by period, it is closed each month rather than accumulated into an argument about two years of steel.

ВходThe adjustment statementРезултатSubmitted and datedAgreed amount for the period
Модули

Модули в този наръчник

5 / 190 модула на платформата

The market this case is written for

Китай

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GB 50500
  • GB 50854

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.

Още в Търговия и договори

Търговия и договори

Turn a change into a paid variation

Capture a scope change while it is fresh, price it as a contract variation on your agreed r…

3 стъпки11 минОтвори
Търговия и договори

Run a subcontractor package

Award a trade package to a subcontractor, place it on a subcontract with a schedule of valu…

3 стъпки11 минОтвори
Търговия и договори

Payment application and reconciliation

Value the work put in place this period against the contract, raise the application with th…

3 стъпки12 минОтвори