Basahin ang clause ng pagsasaayos, i-load ang index series na nakasaad dito, maglagay sa bill ng escalation line na nagsasaad ng series at ng dalawang panahon, at ilabas ang pagsasaayos bilang isang dokumentong nagpapakita ng sarili nitong kalkulasyon.

5 hakbang16 minGeneral ContractorEspesyalistang SubcontractorCost Consultancy / QS Practice

Paano ito gumagana, hakbang-hakbang

5 hakbang sa buong platform - ano ang gagawin mo sa bawat isa at bakit mahalaga ito.

1

Read the clause before you compute anything

Mga Kontrata

Open the contract and write down four things: which method it names, which materials are adjustable, what the base date is, and what movement has to occur before an adjustment is due. This case walks the price-index method; if your contract names the published-price method instead, the base data and the arithmetic are different and the clause will say so.

Screenshot, hakbang 1: Read the clause before you compute anything (Mga Kontrata, Isaayos ang presyo ng materyales gamit ang cost index)
Mga Kontrata: Read the clause before you compute anything

Bakit: An adjustment computed correctly under the wrong method is worth nothing, and it is the sort of error that survives several months before anybody checks. Getting the four terms out of the contract once, in writing, saves rereading it every month and stops each month's calculation being a fresh interpretation.

PapasokThe contractLumalabasThe method namedBase date and adjustable materials
2

Load the series the contract names, period by period

Index ng Presyo

Enter the index series with a value for each period, and keep it current as the publication comes out. The values you load are the published ones for your region; the product ships the mechanism and generic vocabulary rather than anybody's published book.

Screenshot, hakbang 2: Load the series the contract names, period by period (Index ng Presyo, Isaayos ang presyo ng materyales gamit ang cost index)
Index ng Presyo: Load the series the contract names, period by period

Bakit: The series is the evidence. Loading it as data means the adjustment can be recomputed and audited a year later against the same values, instead of resting on a screenshot somebody took of a bulletin that has since been superseded.

PapasokPublished index valuesLumalabasSeries with its periodsPeriods you are missing
3

Put the adjustment on the bill as a named series and two periods

Bill of Quantities (BOQ)

Add an escalation line to the bill's markup stack and give it the series and the two periods: the base period the contract names, and the period the work was done in. The factor comes from what the index did between them; you do not type a percentage.

Bakit: Where the series has no value for one of the two periods, the bill refuses rather than guessing, and a refusal is the right answer: an interpolated index value is a number nobody published and nobody can defend. It also means an adjustment that looks complete really is complete, instead of quietly containing a line that priced at zero.

PapasokThe bill and its quantitiesBase period and current periodLumalabasEscalation line on the billA refusal instead of a wrong total
4

Issue it as a document that shows its working

Mga Ulat

Report the adjustment with the series it used, the two periods, the factor and the base value it was applied to, so the reader can follow the arithmetic without asking you for the spreadsheet.

Screenshot, hakbang 4: Issue it as a document that shows its working (Mga Ulat, Isaayos ang presyo ng materyales gamit ang cost index)
Mga Ulat: Issue it as a document that shows its working

Bakit: An adjustment presented as a single figure gets queried every time. The same adjustment presented with its inputs gets checked once and accepted, because the person checking it can do the multiplication themselves and stop.

PapasokThe adjusted billLumalabasAdjustment statementSeries, periods and factor shown
5

Submit it for the period and get the amount agreed

Sulatan

Send the statement to the other party as correspondence for the period it covers, and record the agreed figure against it. Carry the agreed amount into the period's payment application yourself, on its own line, so it can be seen and queried separately from the valuation.

Screenshot, hakbang 5: Submit it for the period and get the amount agreed (Sulatan, Isaayos ang presyo ng materyales gamit ang cost index)
Sulatan: Submit it for the period and get the amount agreed

Bakit: An adjustment buried inside a valuation total is one that gets renegotiated at settlement, because nobody can find it. On its own line, submitted with its working and agreed period by period, it is closed each month rather than accumulated into an argument about two years of steel.

PapasokThe adjustment statementLumalabasSubmitted and datedAgreed amount for the period
Mga Module

Mga Module sa Playbook na Ito

5 / 190 na module ng platform

The market this case is written for

China

Everything in this case follows how construction work is measured, priced and paid for in this market. The forms, the cost breakdown and the payment rules are the ones used there, not a generic version of them.

Standards it follows

  • GB 50500
  • GB 50854

You do not have to set any of that up by hand. The first time you open the platform it asks which market you work in. Choose this one and it sets the interface language, loads the matching cost database and records the cost classification, and it adds an example project you can open straight away.

The rule checks for this market come with the platform too. Switch them on once and an estimate that misses something the market expects is flagged while you are still working on it, not after the tender has gone out.